School Construction Non-Priority List Grant Process

Classroom

A step-by-step breakdown of the Non-Priority List process

The workflow on this page describes each step of the life cycle of Non-Priority List school construction project grants. Districts considering applying for Non-Priority List school construction projects should review this information carefully.
Learn more about the Non-Priority List

Lifecycle of Non-Priority List school construction grant projects

Looking for similar information about Priority List school construction grant projects? View School Construction Priority List grant process page (CT.gov)


Calendar icon

Step 1: Office of Grants Administration (OGA) Posts Non-Priority Event

Districts can submit Non-Priority List applications between the first and tenth of each month for projects that fall into one of the seven categories specified in 10-283(b).
Calendar with Checkmark

Step 2: OGA Reviews Applications

All applications received during a monthly event are reviewed by OGA during that month.
Checklist icon

Step 3: Communication with Districts

After review, OGA will notify applicants as to whether their application is complete or more information is required.
Megaphone icon

Step 4: DAS Plan Review Approval

The district must receive DAS approval of final designs prior to any phase of a project being let out for bid to be eligible for reimbursement. Districts should contact the DAS Plan Review team during early design stages or after receiving grant commitment.
building with heart

Step 5: Construction Begins

Per statute, construction must begin within two years of the effective date of the legislation authorizing the grant.
briefcase icon

Step 6: Change Orders

Construction change orders must be submitted to the Plan Review team within six months of its issuance.
icon of a dollar sign in a circle

Step 7: Estimated Payments

As work on the project moves forward, the district can submit estimated payment requests for reimbursement. For smaller projects, a district may opt to submit one final payment request in lieu of estimated payments.
Icon of a clipboard with a checkmark

Step 8: Construction Completion and Final Payment Request

Once construction is complete, the district must formally accept the project as complete. The district then has one year to submit the final payment request to DAS.
Icon of a hand in a circle

Step 9: Audit

After the district submits a final payment request, OGA will transmit the grant file to the DAS Audit Unit to conduct an in-depth audit of project expenses and grant requirements.
Icon of a letter

Step 10: Final Payment / Refund Due

Upon completion of the audit, OGA will process either a release of the final payment for the project, or, if the audit determines the project was overpaid, a notice of refund due to the State.
icon of a handshake

Step 11: Grant Complete

Once final payment is sent to the district or the refund is received by DAS, the grant is complete and the file is closed at DAS.