7/7/2023
Metallizing of 19 Bridges Along the I-395 Corridor Between Thompson and Montville
CTDOT is announcing that 19 bridges will be metalized along the I-395 Corridor Between Thompson and Montville starting on July 17, 2023.
-
7/7/2023
Milling and Resurfacing Project: Route 372 Plainville
CTDOT is announcing a milling and resurfacing project that will be performed on Route 372 in Plainville from Whiting Street to Route 10 Farmington Avenue on Monday, July 17 to Thursday, July 20, 2023.
-
7/7/2023
Mill and Fill Project: Interstate 95 N/B & S/B in Westport-Fairfield
CTDOT is announcing a mill and fill resurfacing project will be performed on Interstate 95 North and Southbound alternating lanes from the exit 17 on-ramp to the exit 24 off-ramp from Wednesday, July 19 through Wednesday, August 9, 2023.
-
7/7/2023
Installation and Revision of Traffic Control Signals in District 1
CTODOT is announcing that start of work at various intersections in Ellington, Manchester, South Windsor, Vernon, and Windsor will begin on July 10, 2023.
-
7/7/2023
Milling and Resurfacing Project: Service Road 718 in Guilford
CTDOT is announcing a milling and resurfacing project that will be performed on Service Road 718 in Guilford from Sunday, July 16 to Monday, July 24, 2023.
-
7/7/2023
Rehabilitation of Bridge No. 02166: Route 337 Over Morris Creek in East Haven and New Haven
CTDOT is announcing that a drainage improvement project will be temporarily detouring traffic for a 32-hour weather dependent consecutive time frame starting on Monday, July 10 and ending on Friday, July 14, 2023.
-
6/30/2023
Culvert Replacements: Route 167 in Farmington
CTDOT is announcing there will be culvert replacements on Route 167 over an unnamed tributary to Roaring Brook in Farmington from July 10 to July 27, 2023.
-
6/29/2023
Milling and Resurfacing Project: Service Road 718 in Guilford
CTDOT is announcing a milling and resurfacing project that will be performed on Service Road 718 in Guilford from Sunday, July 16 to Monday, July 24, 2023.
-
6/28/2023
Bridge Deck Milling Project: Bridge No. 02602 on State Maintained 908 (Colman St.) in New London
CTDOT is announcing a bridge deck milling project that will be performed at Bridge No. 02602 on State Maintained 908 (Colman St.) in New London on Friday, July 7, 2023.
-
6/28/2023
Bridge Deck Milling Project: Bridges No. 01392, 01393 and 01394 on Route 156 in Old Lyme
CTDOT is announcing that a bridge deck milling project will be performed at Bridges No. 01392, 01393 and 01394 on Route 156 in Old Lyme from Monday, July 24 through Tuesday, July 25, 2023.
-
6/28/2023
Milling Project: Route 8 South Bound Thomaston on Bridges 03348 & 03347
CTDOT is announcing that milling will take place on Route 8 South Bound Thomaston to Bridges 03348 & 03347 on July 9, 2023, from 7:00 p.m. to 5:00 a.m.
-
6/28/2023
Bridge Deck Joint Repair Project, Bridge No. 03819 on I-95 northbound on the Gold Star Memorial Bridge in New London
CTDOT is announcing that a bridge deck repair project will be performed Gold Star Memorial Bridge in New London
-
6/27/2023
Nighttime Closure: I-95 Northbound Exit 74 Entrance Ramp
CTDOT is announcing that to facilitate construction work associated with the I-95 project in East Lyme, the exit 74 on-ramp to I-95 Northbound will need to be closed on Thursday, June 29, 2023, beginning at 8:00 p.m. and re-opening at 5:00 a.m.
-
6/27/2023
Construction and Maintenance Activities Restricted for Independence Day
CTDOT is announcing that there will be no maintenance or construction activities on limited-access highways from 6 a.m. Monday, July 3, 2023 to 6 a.m. Wednesday, July 5, 2023.
-
6/27/2023
Freight Street Partial Closure
CTDOT is announcing that in order to facilitate construction work associated with the Route 8/I-84 Interchange (Mixmaster) rehabilitation project in Waterbury, the intersection of Freight Street with Northbound Riverside Street will need to be closed.