Renderings of proposed station improvements
Current station conditions
Seymour will receive an upgraded station built on the existing site. Today, the station includes a small low-level platform, a mostly enclosed waiting building without climate control, limited commuter parking, and few other amenities.
A new 350-foot platform will be constructed parallel to Route 115 and the downtown area. The platform will be covered and enclosed with a wraparound windscreen, and will include real time arrival information, ticket vending, and an improved waiting area. The station will be fully ADA compliant, with added landscaping and wayfinding to create a safer and more comfortable passenger experience.
Construction Start: May 2026
New Platform Open: November 2027
Anticipated Construction Completion: May 2028
Anticipated Cost: $23.2 million