Frequently Asked Questions
Steel Strengthening of the Northbound Bridge: Construction is already in progress.
Rehabilitation of the Northbound Bridge: Construction to begin in June 2025.
Steel Strengthening of the Southbound Bridge: Construction is expected to begin in March 2025.
Pedestrian Improvements: Construction is expected to begin in May 2028.
Construction is already in progress on the Steel Strengthening of the Northbound Bridge (Project 0094-0256) and scheduled to be completed by June 2025.
Steel Strengthening of the Southbound Bridge (Project 0094-0268) will precede Pedestrian Improvements (Project 0094-0267) and Rehabilitation of the Northbound Bridge (Project 0094-0261) due to the crossover.
All projects are anticipated to be substantially completed by fall of 2029.