Rehabilitation of the Dutch Point Viaduct

Construction Photos and Videos

Dutch Point Viaduct

Looking south toward the Dutch Point Viaduct.



Under the Viaduct

Underneath the viaduct.
Construction Photo

October 2024

The contractor is taking soil boring samples to gather data for designing micro piles.

Image of lagging being installed under the bridge in advance of demolition

February 2025

Lagging is being installed under the bridge in advance of demolition.

February 2025: Lagging being installed in advance of bridge demolition.

February 2025

Lagging is being installed in advance of bridge demolition.
February 2025: Lagging installed under the bridge in advance of demolition.

February 2025

Installed lagging under the bridge in advance of demolition. 
February 2025: Nighttime installation of signage.

February 2025

Nighttime signage installation.
Construction crew installing temporary barrier for Stage 1 construction on I-91SB

March 2025

Construction crew installs temporary barrier for Stage 1 construction on I-91 SB.
Lagging installation continues in advance of bridge demolition

March 2025

Lagging installation continues in advance of bridge demolition.
Temporary work area on the Whitehead Highway on-ramp to I-91SB

March 2025

Temporary work area on the Whitehead Highway on-ramp to I-91 SB.
Concrete bridge parapet (barrier) removal

March 2025

Concrete bridge parapet (barrier) removal
Concrete bridge parapet (barrier) removal

March 2025

Concrete bridge parapet (barrier) removal
Concrete bridge parapet (barrier) removal

March 2025

Concrete bridge parapet (barrier) removal

March 26, 2025

Bridge deck removal

Bridge deck removal

March 26, 2025

Bridge deck removal

Bridge deck removal

April 3, 2025

Bridge deck removal

Bridge Deck Removal

April 29, 2025

Deck demolition
View of the bridge demolition supports from the ground

April 29, 2025

View of deck demolition supports from the ground
Installing bridge demolition supports

April 29, 2025

Installation of deck removal supports
Crews demolishing the right lane of I-91 SB in Hartford.

May 2025

Crews demolishing the I-91 SB right most lanes in Hartford.
Bridge demolition on I-91 SB.

May 2025

I-91SB bridge demolition as seen from Van Dyke Avenue.

I-91SB bridge demolition.

May 2025

I-91SB right lane bridge demolition. 

Crews construction the new bridge deck on I-91SB.

May 2025

Crews construction the new I-91SB bridge.

Crews construction the new I-91SB bridge deck.

May 2025

Crews construction the new I-91SB bridge deck.
View of I-91SB construction from the sidewalk on Van Dyke Avenue looking towards Hartford.

May 2025

View of I-91SB construction from the sidewalk on Van Dyke Avenue looking towards Hartford.
Bridge demolition on the Whitehead Highway on-ramp to I-91SB.

June 2025

Bridge demolition on the Whitehead Highway on-ramp to I-91 SB.

Crews working at night to move barrier on I-91SB.

June 2025

Crews relocating barrier at night.

Reinforcing steel ready for concrete pours on I-91SB.

June 2025

Installed reenforcing streel (rebar) ready for concrete.

View of early August concrete pours curing.

August 2025

View of early August concrete pours curing. 
Crews pouring and shaping concrete for the new bridge deck on I-91 SB.

August 2025

Crews pouring and shaping concrete for the new bridge deck on I-91 SB.
Crews pouring concrete for the new bridge deck, shaping and covering it to cure.

August 2025

Crews pouring concrete for the new bridge deck, shaping and covering it to cure.
Wet concrete for the new bridge deck curing under a covering.

August 2025

Wet concrete for the new bridge deck curing under a covering.
Uncovering cured concrete for the new bridge deck on I-91 SB.

August 2025

Uncovering cured concrete for the new bridge deck on I-91 SB.
New concrete bridge deck on I-91 SB with parapet rebar on right ready for concrete.

August 2025

New concrete bridge deck on I-91 SB with parapet rebar on right ready for concrete.
Crews paving the Whitehead Highway on-ramp to I-91 SB.

October 2025

Crews paving the Whitehead Highway on-ramp to I-91 SB.
Paving continues on the Whitehead Highway on-ramp to I-91 SB.

October 2025

Paving continues on the Whitehead Highway on-ramp to I-91 SB.
Paving asphalt on the Whitehead Highway on-ramp to I-91 SB.

October 2025

Paving asphalt on the Whitehead Highway on-ramp to I-91 SB.