Rehabilitation of the Dutch Point Viaduct
State Project No. 0063-0726
Construction Update
14-Day Lookahead for the weeks of June 30 and July 7
As the schedule is subject to change, please check our website for the most current updates.
TRAFFIC IMPACTS:
LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT:
The long-term closure of one of the three lanes of I-91 SB through the work zone will remain for the duration of the project. The project is being constructed in three stages. Stage 1 construction began on March 11, 2025. Stage 3 construction is scheduled to be completed in September 2026.
The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction. Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.
The Stage 1 traffic pattern includes a work zone and reduced travel way width on the Whitehead Highway on-ramp to I-91 SB.
Motorists on I-84 EB seeking I-91 SB will be required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. I-84 EB motorists entering I-91 SB traffic previously had a dedicated lane provided.
Temporary nighttime lane closures are expected on I-91 SB during the project from 8:00 pm to 6:00 am.
Temporary daytime shoulder closures are expected on I-91 SB during the project from 9:00 am to 3:00 pm.

State Street on-ramp to I-91 Southbound Detour Graphic
Motorists should anticipate single-lane closures on the I-91 NB off-ramp to Whitehead Highway (Exit 29A) Monday, June 30, through Thursday, July 3, and Monday, July 7, through Wednesday, July 9, between the hours of 9 AM and 5 PM.
On Monday, June 30, Van Dyke Avenue will be reduced to a single lane with alternating one-way traffic controlled by flaggers between the hours of 6 AM and 2 PM.
No work is scheduled for Friday, July 4, 2025, in observation of the Independence Day holiday.
June 30 through July 3:
• Bridge demolition behind the barrier on I-91 SB (day)
• Remove shielding from Whitehead highway bridge (day)
• Install rebar on Whitehead Highway bridge deck (day)
• Install foam on stay-in-place deck (day)
• Install conduit drop-downs (day)
• Install scuppers for drainage on the Whitehead Highway bridge deck (day)
July 7 through July 11:
• Bridge demolition behind the barrier on I-91 SB (day)
• Install rebar on Whitehead Highway bridge deck (day)
• Concrete pour on Whitehead Highway bridge deck (day)