Rehabilitation of the Dutch Point Viaduct
State Project No. 0063-0726
Construction Update
14-Day Lookahead for the weeks of October 11 and 18
As the schedule is subject to change, please check our website for the most current updates.
TRAFFIC IMPACTS:
LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT:
The Stage 2 traffic pattern includes a work zone in the center lane of I-91 SB beginning just after Exit 29A (Capitol Area) and continuing for approximately one-third of a mile (1800 feet) south to the Colt Building. Motorists traveling on I-91 SB will be split into two lanes, one on either side of the center lane work zone (as depicted in the signage below). Advance warning signage will be in place to assist motorists through the work zone. The Stage 2 traffic pattern will be in place for approximately 3 to 4 months. Click here to learn more about Stage 2.
Advance warning signage of upcoming traffic split
The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction. Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.

State Street on-ramp to I-91 Southbound Detour Graphic
Motorists on I-84 EB seeking I-91 SB are required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. I-84 EB motorists entering I-91 SB traffic previously had a dedicated lane.
Temporary nighttime lane closures are also expected to continue on I-91 SB during the project from 7:00 pm to 6:00 am.
Temporary daytime lane closures are also expected on the Whitehead Highway ramps to and from I-91 NB during the project from 9:00 am to 3:00 pm.
Traffic control signing patterns, along with State Troopers during temporary lane and shoulder closures as needed, will guide motorists through the work zone.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.
PLANNED CONSTRUCTION:
Construction activities and associated traffic impacts are weather dependent. Schedule updates will be shared here and on the project social media.
Motorists should expect the following traffic impacts and closures:
October 11 through October 17:
Tuesday night, October 13
• I-91 SB between Exit 29A (Capital Area) and the Colt Building
• Left lane closure from 7 PM to 5 AM
Thursday night, October 15
• I-91 SB between Exit 29A (Capital Area) and the Colt Building
• Left lane closure from 7 PM to 5 AM
October 18 through October 24:
Thursday night, October 22
• I-91 SB between Exit 29A (Capital Area) and the Colt Building
• Right lane closure from 7 PM to 5 AM
• Form columns and stubs (day)
• Install rebar for columns (day)
• Pour concrete columns (day)
• Install shielding (day)
• Wet cure deck (day)
• Surface repairs (day)
• Surface concrete pours (day)
• Deck repairs (day)
• Install rebar for spans (day)
• Pour concrete spans (night)
• Blasting and metallizing (day)
• Set up drilling operation (day)
• Paving operations (day)
October 18 through October 24:
• Form columns (day)
• Install rebar for columns (day)
• Pour concrete columns (day)
• Excavate footings (day)
• Install shielding (day)
• Wet cure deck (day)
• Prep and repair surfaces (day)
• Pour concrete surfaces (day)
• Install rebar for spans (day)
• Pour concrete spans (night)
• Containment removal (day)