Skip to Content Skip to Chat
Report an accessibility issue.
Connecticut's official state website logo State of Connecticut
×
 
Close Search
  • Arabic
  • Chinese (Simplified)
  • Chinese (Traditional)
  • English
  • French
  • German
  • Haitian Creole
  • Hindi
  • Italian
  • Korean
  • Pashto
  • Polish
  • Portuguese Brazil
  • Russian
  • Spanish
  • Filipino
  • Ukrainian
  • Vietnamese
Department of Transportation
Department of Transportation logo
Department of Transportation
  • YouTube
  • Instagram
  • Linkedin
  • X
  • Facebook
  • Tiktok
Department of Transportation
☰ Department of Transportation Main Menu
× Close
⮐ Back
⮐ Back
  • Home
  • Travel
    • Roads & Highways
      • Park & Ride
      • Parkway Restrictions
      • Rest Areas
      • Traffic Monitoring Data
      • Transportation Maps
    • Motorcycle resources
      • CONREP
    • Public Transportation
      • CT Buses
      • CT Ferries
      • CT Rail
      • CTDOT Ridesharing
    • Bicycle & Pedestrian
  • Business
    • Resources
      • Consultant Resources
      • Contractor Resources
      • Disadvantaged Business Enterprise (DBE)
    • Contracting & Project Awards
    • Equal Opportunity & Diversity
    • Title VI/Opportunity and Business Development
    • Manuals
    • Permits
  • Careers
    • Find a job
  • Bureaus
    • Commissioner
    • Engineering & Construction
    • Finance & Administration
    • Operations & Maintenance
    • Policy & Planning
    • Public Transportation
  • News
    • Construction Advisories
    • Press Releases
    • Upcoming Meetings
  • Programs & Projects
    • Active Projects
    • Major Projects & Initiatives
    • Programs
  • About
    • Branding
    • Resources
    • FAQ
    • Contact
      • Report An Issue
      • Email Alerts Signup
      • Submit An FOI Request
      • Media Inquiry
      • Submit a Claim

You are about to Logout

Are you sure you want to log out of your account? If you do want to logout, please click "Logout".
Logout
Press Release Homepage
" "

Construction Update - December 15 and December 22

12/12/2025

Rehabilitation of the Dutch Point Viaduct

State Project No. 0063-0726

Construction Update

 

14-Day Lookahead for the weeks of December 15 and December 22

As the schedule is subject to change, please check our website for the most current updates.

TRAFFIC IMPACTS:

LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT:

The long-term closure of one of the three lanes of I-91 SB through the work zone will remain for the duration of the project. The project is being constructed in three stages. Stage 1 construction began on March 11, 2025. Stage 3 construction is scheduled to be completed in September 2026.

The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction. Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.

The Stage 1 traffic pattern includes a work zone and reduced travel way width on the Whitehead Highway on-ramp to I-91 SB.

Motorists on I-84 EB seeking I-91 SB will be required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. I-84 EB motorists entering I-91 SB traffic previously had a dedicated lane provided.

Temporary nighttime lane closures are expected on I-91 SB during the project from 8:00 pm to 6:00 am.

Temporary daytime shoulder closures are expected on I-91 SB during the project from 9:00 am to 3:00 pm.  

State Street on-ramp to I-91 Southbound Detour Graphic

PLANNED CONSTRUCTION: 

Friday, December 19, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Left lane closure from 6:30 AM to 2:30 PM

Monday, December 22, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Left lane closure from 6:30 AM to 2:30 PM

Tuesday, December 23, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Right lane closure from 6:30 AM to 2:30 PM

In observation of the Christmas holiday, there is no work scheduled on behalf of the project from Thursday, December 25, through Sunday, December 28. Work will resume on Monday, December 29.

December 15 through December 19: 

  • • Prep and prime for steel repairs (day)
    • Install hangers and overhang brackets (day)
    • Setting and forming scuppers (day)
    • Remove and install shielding (day)
    • Bridge edge formwork on I-91 SB (day)
    • Install stay-in-place deck and foam on I-91 SB (day)
    • Install rebar on I-91 SB (day)
    • Concrete repair and curing (day)
    • Steel strengthening (day)

December 22 through December 26:

• Prep and prime for steel repairs (day)
• Remove and install shielding (day)
• Install hangers and overhang brackets (day)
• Setting and forming scuppers (day)
• Install stay-in-place deck and foam on I-91 SB (day)
• Install rebar on I-91 SB (day)
• Steel strengthening (day)

 


 

Department of Transportation
Facebook external link Instagram external link Linkedin external link Tiktok external link X external link YouTube external link

Mailing address
2800 Berlin Turnpike
P.O. Box 317546
Newington CT 06131-7546

Report an Issue or Ask a Question
860-594-2560 
Online Webform

CTDOT Information and Contacts for Persons with Disabilities

ct.gov logo with flag embelishment
  • About CT
  • Policies
  • Accessibility
  • Directories
  • Social Media
  • For State Employees
US Flag Status icon
United States
Mast: (Full)
CT Flag Status icon
Connecticut
Mast: (Full)

© 2026 CT.gov - Connecticut's Official State Website