Rehabilitation of the Dutch Point Viaduct
State Project No. 0063-0726
Construction Update
14-Day Lookahead for the weeks of December 15 and December 22
As the schedule is subject to change, please check our website for the most current updates.
TRAFFIC IMPACTS:
LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT:
The long-term closure of one of the three lanes of I-91 SB through the work zone will remain for the duration of the project. The project is being constructed in three stages. Stage 1 construction began on March 11, 2025. Stage 3 construction is scheduled to be completed in September 2026.
The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction. Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.
The Stage 1 traffic pattern includes a work zone and reduced travel way width on the Whitehead Highway on-ramp to I-91 SB.
Motorists on I-84 EB seeking I-91 SB will be required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. I-84 EB motorists entering I-91 SB traffic previously had a dedicated lane provided.
Temporary nighttime lane closures are expected on I-91 SB during the project from 8:00 pm to 6:00 am.
Temporary daytime shoulder closures are expected on I-91 SB during the project from 9:00 am to 3:00 pm.

State Street on-ramp to I-91 Southbound Detour Graphic
Friday, December 19, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Left lane closure from 6:30 AM to 2:30 PM
Monday, December 22, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Left lane closure from 6:30 AM to 2:30 PM
Tuesday, December 23, motorists should expect the following traffic impacts and closures:
• Whitehead Highway EB on-ramp to I-91 NB
o Right lane closure from 6:30 AM to 2:30 PM
In observation of the Christmas holiday, there is no work scheduled on behalf of the project from Thursday, December 25, through Sunday, December 28. Work will resume on Monday, December 29.
December 15 through December 19:
- • Prep and prime for steel repairs (day)
• Install hangers and overhang brackets (day)
• Setting and forming scuppers (day)
• Remove and install shielding (day)
• Bridge edge formwork on I-91 SB (day)
• Install stay-in-place deck and foam on I-91 SB (day)
• Install rebar on I-91 SB (day)
• Concrete repair and curing (day)
• Steel strengthening (day)
December 22 through December 26:
• Prep and prime for steel repairs (day)
• Remove and install shielding (day)
• Install hangers and overhang brackets (day)
• Setting and forming scuppers (day)
• Install stay-in-place deck and foam on I-91 SB (day)
• Install rebar on I-91 SB (day)
• Steel strengthening (day)