Rehabilitation of the Dutch Point Viaduct
State Project No. 0063-0726
Construction Update
14-Day Lookahead for the weeks of December 1 and December 8
As the schedule is subject to change, please check our website for the most current updates.
TRAFFIC IMPACTS:
LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT:
The long-term closure of one of the three lanes of I-91 SB through the work zone will remain for the duration of the project. The project is being constructed in three stages. Stage 1 construction began on March 11, 2025. Stage 3 construction is scheduled to be completed in September 2026.
The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction. Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.
The Stage 1 traffic pattern includes a work zone and reduced travel way width on the Whitehead Highway on-ramp to I-91 SB.
Motorists on I-84 EB seeking I-91 SB will be required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. I-84 EB motorists entering I-91 SB traffic previously had a dedicated lane provided.
Temporary nighttime lane closures are expected on I-91 SB during the project from 8:00 pm to 6:00 am.
Temporary daytime shoulder closures are expected on I-91 SB during the project from 9:00 am to 3:00 pm.

State Street on-ramp to I-91 Southbound Detour Graphic
No construction activities are scheduled for the project from Thursday, November 27, through Sunday, November 30, in observation of the Thanksgiving holiday. Crews will return to the site on Monday, December 1.
December 1 through December 5:
- Lead abatement (day)
- Prep and prime for steel repairs (day)
- Remove and install shielding (day)
- Bridge edge formwork on I-91 SB (day)
- Setting and forming scuppers (day)
- Install stay-in-place deck and foam on I-91 SB (day)
- Install rebar on I-91 SB (day)
- Surveying on I-91 SB (day)
- Steel strengthening, repairs and inspections (day)
December 8 through December 12:
- Prep and prime for steel repairs (day)
- Remove and install shielding (day)
- Install hangers and overhang brackets (day)
- setting and forming scuppers (day)
- Install stay-in-place deck and foam on I-91 SB (day)
- Install rebar on I-91 SB (day)
- Surveying on I-91 SB (day)
- Steel strengthening, repairs and inspections (day)