The Connecticut Department of Transportation (CTDOT) is developing plans to mill and pave 16 bridges along Route 7 in City of Norwalk. This project will be part of the state-wide bridge preservation program as follow up to pavement preservation projects with the purpose of repairing the bridge decks thus extending their service life and keeping the structures in a state of good repair.
The project involves removing the bridge overlay and membrane, the necessary repairs to the bridge deck and applying new membrane and overlay as well as replacing the bridge joints.
The present schedule indicates that the design will be completed in August 2025, with construction anticipated to start in the spring of 2026, assuming acceptance of the project, availability of funding and receipt of any required right-of-way and environmental permits. This project will be undertaken with 100% state funds.
The bridges and their locations can be found below:
Bridge No. |
Description |
Route |
Town |
03562 |
US Route 7 and Ramp 1 over I-95, Town Road 802 Route 7 Ramp 1 |
Route 7 |
Norwalk |
03565 |
US Route 7 southbound over Connecticut Avenue |
Route 7 |
Norwalk |
03566 |
US Route 7 northbound over Connecticut Avenue |
Route 7 |
Norwalk |
03567A |
US Route 7 northbound over Maple Street |
Route 7 |
Norwalk |
03567B |
US Route 7 southbound over Maple Street |
Route 7 |
Norwalk |
03568A |
US Route 7 northbound over Union Park Street |
Route 7 |
Norwalk |
03568B |
US Route 7 southbound over Union Park Street |
Route 7 |
Norwalk |
03569A |
US Route 7 northbound over US Route 1 (Belden Avenue) |
Route 7 |
Norwalk |
03569B |
US Route 7 southbound over US Route 1 (Belden Avenue) |
Route 7 |
Norwalk |
03570 |
US Route 7 ramp over US Route 1 |
Route 7 |
Norwalk |
03571 |
US Route 7 northbound over Norwalk River |
Route 7 |
Norwalk |
03572 |
US Route 7 southbound over Norwalk River |
Route 7 |
Norwalk |
03573A |
US Route 7 northbound and ramp over Route 123 |
Route 7 |
Norwalk |
03573B |
US Route 7 southbound over Route 123 |
Route 7 |
Norwalk |
06064 |
US Route 7 over Broad Street |
Route 7 |
Norwalk |
06065 |
US Route 7 over Norwalk River |
Route 7 |
Norwalk |
It is CTDOT's policy to keep the public informed and involved when such projects are undertaken and important that the community share its concerns with CTDOT to assist in the project's development.
If anyone has any questions or comments on this project, contact Jacob Booth, Supervising Engineer, at (860) 594-2862 or by e-mail at Jacob.Booth@ct.gov. Please make reference to State Project No. 0102-0380.