The Connecticut Department of Transportation (CTDOT) is announcing rehabilitation of Bridge Nos. 00058 & 03563 will be performed on I-95 at Exit 15 in Norwalk. This project is scheduled to occur on Monday, November 16 and be completed on September 28, 2027. The project 0102-0372 consists of superstructure and substructure repairs in addition to sidewalk improvements.
CTDOT Project No. 0102-0372 was awarded to McNamee Construction at a cost of $11,924,000.00 on September 15, 2026, and is scheduled to be completed by September 28, 2027. This project is administered by the Bureau of Engineering and Construction, Office Construction, District 3 in New Haven.
LANE CLOSURE/DETOUR INFO
There will be periodic lane closures on I-95 northbound and southbound near Exit 15, as well as a lane closure on the Exit 15 southbound off-ramp in Norwalk starting Monday, November 16, 2026, from 9:00 p.m. to 6:00 a.m.; Monday to Friday. The on-ramp at Exit 15 on I-95 northbound will be closed overnight (9:00 p.m. to 6:00 a.m.) with a detour in place through spring 2027. Traffic control personnel and signing patterns will guide motorists through the work zone and detour. The work schedule for this project is from 9:00 p.m. to 6:00 a.m., Monday to Friday.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.
This advisory was revised on 11/9/2026