The Connecticut Department of Transportation (CTDOT) is announcing that milling will be performed on Route 6 in Columbia, Coventry, Mansfield, and Windham. This project is scheduled to occur on Tuesday, June 16, 2026, and be completed on November 26, 2026. The project 0030-0099 consists of mill and overlay on Route 6.
CTDOT Project No. 0030-0099 was awarded to Palmer Paving Corporation at a cost of $11,481,900.98 on 3/3/2026 and is scheduled to be completed 11/26/2026. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 2 in Norwich.
LANE CLOSURE/DETOUR INFO
There will be ramp closures on Route 6 starting June 16 to around November 26, 2026, from 8:00 p.m. to 6:00 a.m. Ramp closures will take place between mile markers 87.78 and 93.14 eastbound and between 87.81 and 93.37 westbound.
There will be lane closures on Route 6 starting June 16 to around November 26, 2026, from 7:00 p.m. to 6:00 a.m. Lane closures will take place between mile markers 87.78 and 93.14 eastbound and between 87.81 and 93.37 westbound.
Traffic control signing patterns and State Troopers will guide motorists through the work zone.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.