The Connecticut Department of Transportation (CTDOT) is announcing that joint crack seals will be performed on Route 7 southbound in Danbury and Brookfield. This project is scheduled to begin on Tuesday, December 3 and be completed on Monday, December 9, 2024.
This project is being performed by State Forces.
LANE CLOSURE/DETOUR INFO
There will be lane and ramp closures on Route 7 southbound between Exits 11-12. Traffic control signing patterns and detour signs will guide motorists through the work zone. The regular work schedule for this project is 7:00 a.m. to 4:00 p.m, Monday-Friday.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.