Rehabilitation of the Dutch Point Viaduct

Construction Update: Lookahead for the weeks of March 24 and March 31

Read the full Construction Update here.

LONG-TERM LANE CLOSURE/DETOUR REMAINS IN EFFECT: 
The long-term closure of one of the three lanes of I-91 SB through the work zone will remain for the duration of the project.
The project is being constructed in three stages. Stage 1 construction began on March 11, 2025. Stage 3 construction is scheduled to be completed in September 2026. 

The State Street on-ramp to I-91 SB located at the Founders Bridge will remain CLOSED for the duration of the project to facilitate the temporary traffic patterns on I-91 SB throughout staged construction.
Detours are posted to direct motorists seeking I-91 SB to use either the South Morgan Street on-ramp to I-91 SB at Columbus Boulevard or the Sheldon Street on-ramp to the Whitehead Highway at Columbus Boulevard, where they can access I-91 SB.

The Stage 1 traffic pattern includes a work zone and reduced travel way width on the Whitehead Highway on-ramp to I-91 SB. 

Motorists on I-84 EB seeking I-91 SB will be required to merge with I-91 SB traffic due to the temporary traffic patterns on I-91 SB during staged construction. Currently, I-84 EB motorists entering I-91 SB traffic have a dedicated lane provided.

Temporary nighttime lane closures are expected on I-91 SB during the project from 8:00 pm to 6:00 am.

Temporary daytime shoulder closures are expected on I-91 SB during the project from 9:00 am to 3:00 pm.  

 

Monday, March 24, through Friday, March 28, motorists should expect the following traffic impacts and closures:

  • On-ramp to I-91 NB from Whitehead Highway eastbound
    • Lane shift from 6:00 AM to 3:00 PM
    • Left lane closure from 6:00 AM to 3:00 PM
  • I-91 NB Exit 29A off-ramp to Whitehead Highway
    • Lane closures from 9:00 AM to 3:00 PM

Monday, March 31, through Friday, April 4, motorists should expect the following traffic impacts and closures:

  • On-ramp to I-91 NB from Whitehead Highway eastbound
    • Lane shift from 6:00 AM to 3:00 PM
    • Left lane closure from 6:00 AM to 3:00 PM
  • I-91 NB Exit 29A off-ramp to Whitehead Highway
    • Lane closures from 9:00 AM to 3:00 PM
Project Location Map

About the Project

The Dutch Point Viaduct is an 1,800 foot long elevated bridge structure carrying three lanes of Interstate 91 (I-91) southbound over the Connecticut Southern Railroad and the I-91 northbound ramps to and from Whitehead Highway in Hartford, CT. The purpose of this project is to upgrade the bridge’s structural elements to current design standards, which will improve its load carrying capacity and extend its service life. This project is located along I-91 southbound between the Connecticut Convention Center and the Colt Armory.

The project includes a new bridge deck with an upgraded drainage system, new parapets that meet the latest federal standards, and new standard highway lights. The project also includes the metallizing of bridge girder beam ends and steel strengthening repairs to bridge girders to increase load carrying capacity. Bridge bearings will be replaced or repaired. New micropiles and concrete encasement of steel pier bents will strengthen the substructure of the bridge and increase load carrying capacity.

 

Project Detour

Reconstruction of the bridge deck requires the closure of the State Street on-ramp to I-91 southbound for approximately 18 months. The closure and implementation of the detour began on March 11, 2025. Visit the Traffic Alerts and Detours page for more details.

 

Project Schedule

This project is being delivered using the Design-Build method. The design phase will continue concurrently with construction activities, which began in February 2025. Replacement of the bridge deck will continue through 2026. The project is expected to be completed by fall 2026.

 

Construction Open House

The Construction Open House for this project was held on January 13, 2025. Thank you to those who were able to attend. Use the following links to download materials from the open house: Exhibit Boards | Presentation | Fact Sheet (English) | Fact Sheet (Español). If you would like to receive project updates by e-mail, click here.

Traffic Volume Image

Traffic Alerts and Detours

Check here for detours and construction-related traffic updates.
Construction Photo

Construction Photos and Videos

See the latest photos and videos of construction in progress.
Message icon

Contact Us

Send us an email with your questions and/or comments.



Detour icon

Sign Up for Project Updates

Stay up to date on construction activities and detours that may impact traffic.



Traffic camera icon

View CTDOT's Live Traffic Cams

CTroads is your source for real-time travel information in CT.