The Connecticut Department of Transportation (CTDOT) is announcing that bridge work will be performed on I-95 in Darien. This project is scheduled to occur on Tuesday April 1 and be completed on Friday, August 15, 2025. The project 0035-0198 consists of relining the existing 72-inch x 42-inch structure with a 64-inch x 38-inch glass reinforced polymer (GRP) arch structure. Approximately 500 feet of guiderail and 400 feet of noise barrier wall will be temporarily removed and replaced to accommodate the work.
CTDOT Project No. 0035-0198 was awarded to Guerrera Construction at a cost of $2,298,820.50 on March 5 and is scheduled to be completed August 15, 2025. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 3 in New Haven.
LANE CLOSURE/DETOUR INFO
I-95 Southbound at Exit 10
There will be on-ramp shoulder closures on I-95 southbound at Exit 10 from Tuesday April 1, to Friday, August 15, 2025.
I-95 Northbound at Exit 10
There will be off-ramp shoulder closures on I-95 northbound at Exit 10 from Tuesday April 1 to Friday, August 15, 2025.
Traffic control signing patterns and State Troopers will guide motorists through the work zone. Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.