Submitting completed school construction change order package for DAS review

Article
Read time: 6 minutes

Email the completed Change Order Summary (SCG-043.CO), Notice of Change Order (SCG-042.CO), and change order backup to DAS.scg.changeorder@ct.gov.

  • Summary sheets are collected in a mailbox that is monitored.
  • Do not include salutations or information in the body of the email,
  • Subject line of the email must:
    • Start with:
      • The State Project Number
      • The designated project type (CV, RNV, RR, E/A, etc.),
    • Followed by:
      • Project name,
      • School Type (High school, M/S, E. S., Pre-k~3, etc.)
      • State Change Order Number.
  • Emailed summary sheets not formatted correctly will delay review

NOTE:- Examples of acceptable
                        - 099-0234 RNV   Springfield MS – CO #01
                        - SPN#034-0119 RR   Springfield High School CO 12,
                        - 004-0001 E/A Springfield PreK-5 school: change order No. 3
- Examples of unacceptable
                        - JFK high school – change order
                        - Springfield 151 - C/O 12,
                        - TMP-004-JJLP:  No. 3.