Answer: Sec. 10-286a-10(c). Computation of school building project grants
The amount of the grant approved by the Commissioner of Administrative Services under the provisions of this chapter for any completed school building project shall be computed as follows:
(3) for the period from July 1, 2006, to June 30, 2009, inclusive, for projects with total authorized project costs greater than ten million dollars, if total construction change orders or other change directives otherwise eligible for grant assistance under this chapter exceed five per cent of the authorized total project cost, only fifty per cent of the amount of such change order or other change directives in excess of five per cent shall be eligible for grant assistance; and
(4) after July 1, 2009, for projects with total authorized project costs greater than ten million dollars, if total construction change orders or other change directives otherwise eligible for grant assistance exceed five per cent of the total authorized project cost, such change order or other change directives in excess of five per cent shall be ineligible for grant assistance.