The Connecticut Department of Transportation (CTDOT) is announcing the construction of ADA (Americans with Disabilities Act) concrete sidewalk ramps on Route 137 in Stamford. This project is scheduled to occur on Monday, September 16 and be completed on Thursday, September 17, 2024. The project DOT01703719CN consists of ADA construction of concrete sidewalk ramp on Route 137 in Stamford.
This project is being performed by Laydon Industries.
LANE CLOSURE/DETOUR INFO
Motorists can expect lane closures to occur on Route 137 in Stamford between Square Acre Drive and Olga Drive. Traffic control personnel and signing patterns will guide motorists through the work zone. The regular work schedule is 7:00 a.m. to 5:00 p.m.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.