The Connecticut Department of Transportation (CTDOT) is announcing that milling and resurfacing project will be performed on Route 182A Colebrook from Route 182 to Route 183 on Friday, June 30 and be completed Friday, June 30, 2023. The project consists of milling and resurfacing a 1.29-mile segment of 182A in Colebrook. The milling of this project is scheduled to start on Friday, June 30 and be completed Friday, June 30, 2023. The resurfacing of this project is scheduled to start on Wednesday, July 5 and be completed on Thursday, July 13, 2023.
No work to be performed on the day before or the Fourth of July holiday.
This project is included in CTDOT’s 2023 Vendor Resurfacing Program.
LANE CLOSURE INFO
Motorists can expect delays and one lane alternating Traffic. Traffic control personnel and signing patterns will guide motorists through the work zone. The regular work schedule for this project is 7:00 a.m. to 4:00 p.m., Monday through Friday.