The Connecticut Department of Transportation (CTDOT) is announcing that the exit ramp from I-95 North to Route 9 North will be closed for concrete deck end repairs and asphaltic plug joints from June 7 to June 23, 2023 during the hours of 6 p.m. to 6 a.m.
The project involves the replacement of bridge joints at approximately 44 bridge locations on Route 9 Northbound and Southbound, ranging from Old Saybrook to Cromwell. The Bridge Joint Replacement Program will proactively replace bridge deck joints to systematically address the Route 9 corridor from Old Saybrook to Cromwell. Replacing the bridge joints proactively will address failing joints to prevent the intrusion of water and snow clearing materials from leaking onto major bridge components. Additionally, the project consists of deck ends repairs if necessary.
DOT Project No. 0105-0216 was awarded to Mohawk Northeast, Inc. at a cost of $4,877,911.60 on December 9, 2022, and is scheduled to be completed November 3, 2023. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 2 in Norwich.
LANE CLOSURE INFO
The exit ramp from I-95 North (Exit 69) to Route 9 North closure will take place during the hours of 6 p.m. to 6 a.m. from June 7 to June 23, 2023. Detour signs will be posted, and the detour is as follows.
Traffic will continue on I-95 North to exit 70. Traffic will take a left at the end of the ramp onto Route 1 North. Traffic will then turn left to merge onto I-95 South where they will take exit 69 for Route 9 North.