The Connecticut Department of Transportation is announcing that construction work on Route 11 in Salem will begin on April 20, 2022.
Project 0120-0095 involves rehabilitation of an existing culvert (Bridge No. 06780) that is structurally deficient under State Route 11 in Salem, Conn. More specifically, the project will include slip-lining the existing 84-inch diameter by 400-foot-long culvert; whereby a new 72-inch diameter metal pipe will be installed through the existing culvert and the remaining annular void filled with grout. This project will also include the construction of a temporary construction access road to facilitate the construction and slip lining of the culvert under Route 11.
DOT Project No. 0120-0095 was awarded to Suchocki & Son, Inc. at a cost of $788,609.00 on March 23, 2022, and is scheduled to be completed November 23, 2022. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 2 in Norwich, CT.
LANE CLOSURE INFO:
There will be lane closures on Route 11 northbound and southbound, Monday through Sunday from 6 p.m. to 6 a.m. and 9 a.m. to 3 p.m. All travel lanes will remain open between 6 a.m. to 9 a.m. and 3 p.m. to 6 p.m.