Route 146 Seawall Replacement Project in Branford

The Connecticut Department of Transportation is announcing the start of construction for the seawall replacement project on Route 146 (Limewood Avenue between Sybil Avenue and Crouch Road) in Branford, on September 9, 2021.

The project consists of the replacement of the existing wall, roadway reconstruction, drainage improvement and pedestrian safety improvements to the Indian Neck Trail.

DOT Project No. 0014 – 0186 was awarded to C.J. Fucci, Inc., at a cost of $5,824,577.40. The project is scheduled to be completed on May 31, 2022.

Lane closure information

Route 146- Limewood Avenue:

  • Motorists can expect alternating one way of traffic using temporary traffic signals for the duration of the project from approximately September 10, 2021, to May 1, 2022.

Wilford Road at Route 146:

  • The southern Leg of Wilford Road at Route 146 will be closed and traffic will be detoured during construction.