Road Closure and Detour for Bridge Replacement of Bridge No. 02128, Carrying Route 12 Over Sunset Hill Brook in Thompson

The Connecticut Department of Transportation (CTDOT) is announcing that a Road Closure and Detour for Bridge Replacement of Bridge No. 02128, Carrying Route 12 Over Sunset Hill Brook in Thompson will begin on Monday, June 17 ending Sunday August 25, 2024.

The contract was awarded to Hammonasset Construction, LLC of Clinton, CT on August 28, 2023, at a cost of $2,673,261.73 and is scheduled to be completed October 17, 2024.

Bridge No. 02128 is a single span concrete cast-in-place bridge, approximately 22’ long with a 27’-8” curb to curb width. The structure will be replaced with an integral abutment bridge with a 40’ clear span and a 32’ curb to curb width.

LANE CLOSURE INFO

The contractor will not be permitted to perform any work which will require interruptions to traffic on Route 12 as follows during non-road closure times: Sunday through Monday between 9:00 p.m. and 6:00 a.m.

A 70-day Road Closure and Detour will be implemented starting 12:01 a.m. on Monday, June 17, 2024, and ending 11:59 P.M. on Sunday, August 25, 2024, to remove existing structure and construct new structure, including installation of new full depth paving. During this time, the contractor will not be permitted to perform any work on the project on Route 12 as follows: Sunday through Monday between 9:00 p.m. and 6:00 a.m.

Route 12 North will be detoured along Route 193 East to Route 200 West to Route 12.

Route 12 South will be detoured on Route 200 East to Route 193 West to Route 12.


FOR MORE INFORMATION: