Codes Amendment Subcommittee Meeting Schedule
Meeting Date Workgroup Reporting Scheduled Presentations Action Items Other Information
1/11/17



1/25/17



2/8/17 Mechanical;
Screening of code change proposals IMC and related IRC chapters
February 22 Accessibility

IBC, A117.1
IEBC
March 8 Plumbing; Electrical

IPC
NEC
IRC (P & E)
March 22 Energy

IECC and related IRC chapters
April 12 Residential Code - General
Last meeting accepting Code Change Proposals Proposal period ends 3/31/17.
April 26 Building Code – General; Existing Building



May 10 Structural; Resiliency



May 24

Maya Menlo

Peter Cloudas

IBC/IFC Chapters 7-10
June 14 Fire Safety - Fire Prevention Codes Coordination; IBC/Fire Safety New Common Requirements

 



June 28 IRC (Sprinklers) Discussion



July 12

Review/discuss all code change proposals
August 9 IRC (Sprinkders) Vote

Action by full Committee
 August 23  Draft State Building Code   Discuss proposal CP035-BC  
September 13

Final State Building Code

Draft State Fire Safety Code

     
 September 27      Approval to transmit to full committee  