PETITION NO. 1352 - Nutmeg Solar, LLC, petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 19.6-megawatt AC solar photovoltaic electric generating facility on approximately 162 acres comprised of 9 separate parcels located generally south of Bailey Road and east of Route 191 (Broad Brook Road), and associated electrical interconnection to Eversource Energy’s Scitico Substation at 20 Bailey Road in Enfield, Connecticut.
PETITION (received 10/19/18)
- Narrative
- Exhibit A: Figures
- Exhibit B: Company Background/Project Team
- Exhibit C: Land Records
- Exhibit D: Environmental Site Conditions Report
- Exhibit E: Farmland Soil Mitigation Plan
- Exhibit F: Equipment Specifications
- Exhibit G: Detailed Site Plan Layout
- Exhibit H: Operations and Maintenance Plan
- Exhibit I: Photo Simulations
- Exhibit J: Construction Schedule/Duration
- Exhibit K: Stormwater Management Report
- Exhibit L: Decommissioning Plan
- Exhibit M: Greenhouse Gas Assessment
- Exhibit N: Project Outreach Information
- Exhibit O: NDDB Correspondence
- Exhibit P: Legal Notice and Notice Lists
- Exhibit Q: Acoustic Study
- Exhibit R: FAA Determinations
- Exhibit S: SHPO Correspondence
PROCEDURAL CORRESPONDENCE
- Council Letter to the Town of Enfield, 10/22/18
- Council Letter to the Town of Somers, 10/22/18
- Council Interrogatories to Petitioner, Set One, 11/14/18
- Council Acknowledgement of Town of Enfield's Requests, 11/19/18
- Petitioner Request for Extension to Respond to Interrogatories and Council Decision, 11/21/18
- Council Member Correspondence, 12/05/18
- Council Completeness Review, 12/06/18
- Council Decision on Town of Enfield's Request for Party Status, 12/7/18
- Council Interrogatories to Petitioner, Set Two, 12/13/18
- Council Interrogatory to Petition, Set Three, 12/19/18
- Field Review Notice, 12/28/18
- Council Member Correspondence, 1/15/19
- Council Request for Extension of Time for Decision, 3/27/19
STATE AGENCY COMMENTS
- State Agency Comment Memorandum, 10/22/18
- DEEP Request for Extension of Time for Comments with Council Response, 11/7/18
- Department of Energy and Environmental Protection Comments, 11/29/18
- Connecticut Airport Authority Comments, 12/14/18
MUNICIPAL COMMENTS
PUBLIC OFFICIAL COMMENTS
HEARING INFORMATION
- Hearing Package, 12/07/18
- Pre-Hearing Conference Memorandum, 12/11/18
- Hearing Procedures Memorandum, 12/18/18
- Council Memorandum on Continuation of Evidentiary Hearing, 1/11/19
SCHEDULE
- Schedule, 10/24/18
- Revised Schedule, 11/9/18
- Revised Schedule, 11/15/18
- Revised Schedule, 11/26/18
- Revised Schedule, 12/07/18
- Revised Schedule, 12/21/18
- Revised Schedule, 1/7/19
- Revised Schedule, 1/11/19
- Revised Schedule, 3/29/19
SERVICE LISTS
- Service List, 12/06/18
- Service List Request Change, 12/04/19
- Service List, 12/04/19
- Service List, 09/24/21
HEARING PROGRAMS
TRANSCRIPTS
- Evidentiary Hearing Transcript, 1/10/19
- Public Session Evening Transcript, 1/10/19
- Hearing Transcript Memorandum, 1/17/19
- Evidentiary Hearing Transcript, 1/24/19
- Hearing Transcript Memorandum, 1/29/19
PARTIES AND INTERVENORS
PETITIONER- NUTMEG SOLAR, LLC
Exhibits
- Nutmeg Solar, LLC Response to Council Interrogatories, 12/07/18
- Nutmeg Solar, LLC Amended Exhibit F - Specification Sheets for 400 watt Solar Modules, 12/07/18
- Nutmeg Solar, LLC Phase 1B Report Cultural Resources Reconnaissance Survey of Proposed Nutmeg Solar Facility in Enfield, Connecticut, 12/12/18
- Nutmeg Solar, LLC Update to Item #4 of Petition Exhibit N-Nutmeg Solar Project Outreach Log, 12/28/18
- Nutmeg Solar, LLC Revised Response to Council Interrogatory No. 14, 1/2/19
- Nutmeg Solar, LLC Revised Response to Council Interrogatory No. 45, 1/2/19
- Nutmeg Solar, LLC Responses to Council Interrogatories Nos. 73-94, 1/3/19
- Nutmeg Solar, LLC Response to Council Interrogatory No. 95, 1/3/19
- Nutmeg Solar, LLC Responses to Council's requested late field exhibits B, C, and D, 1/17/19
- Nutmeg Solar, LLC Response to Town of Enfield's Comments, 1/23/19
- Nutmeg Solar, LLC Correspondence from State Historic Preservation Office, 2/22/19
Correspondence
- Nutmeg Solar, LLC Administrative Notice List, 1/3/19
- Nutmeg Solar, LLC Witness List, 1/3/19
- Nutmeg Solar, LLC Additional Witness, 1/17/19
- Nutmeg Solar, LLC Field Staff Resume, 1/24/2019
- Nutmeg Solar, LLC Consent to Council Request for Extension of Time, 03/28/19
- Service List Change, 09/24/21
Motions and Objections
- Nutmeg Solar, LLC Motion for Protective Order, 1/15/19
- Signed Protective Order, 1/17/19
- Council Decision on Motion for Protective Order, 1/18/19
Post Hearing Briefs and Draft Findings of Fact
- Nutmeg Solar, LLC Post Hearing Brief, 2/25/19
- Nutmeg Solar, LLC Response to Draft Finding of Fact, 4/5/19
PARTY-TOWN OF ENFIELD
Exhibits
- Town of Enfield Motion for Party Status and Request for Public Hearing, 11/14/18
- Town of Enfield Pre-Filed Testimony, 1/16/19
Correspondence
Motions and Objections
Post Hearing Briefs and Draft Findings of Fact
DRAFT FINDINGS OF FACT
FINAL DECISION
DEVELOPMENT AND MANAGEMENT PLAN
- Development and Management Plan, 11/27/19
- Attachment B-Nutmeg Solar Site Plan Drawings, 12/3/19
- Council D&M Plan Interrogatories to Nutmeg Solar, LLC, Set One, 12/10/19
- Nutmeg Solar, LLC Responses to Interrogatories, 12/20/19
- Council Decision on Development & Management Plan, 1/17/20
- Stormwater Pollution Control Plan, 1/23/20
- Council Acknowledgement of Stormwater Pollution Control Plan, 1/24/20
- Commencement of Construction Letter, 1/31/20
- Nutmeg Solar, LLC Request for Development & Management Plan Modification, 6/15/20
- Council Decision on D&M Plan Modification, 06/17/20
- Nutmeg Solar, LLC Fence Revision Request, 10/16/20
- Council Decision on Revision Request, 10/19/20
- Revision Request and Council Decision, 02/01/23
D&M Monthly Construction Reports
Construction Report, 3/18/20
Construction Report, 4/21/20
Construction Report, 06/15/20
Construction Report, 07/14/20
Construction Report, 08/12/20
Construction Report, 09/15/20
Construction Report, 10/12/20
Construction Report, 11/16/20
Construction Report, 12/15/20
Construction Report, 02/01/21