Expanding DEEP Concierge Services


Goal 12 Header

In Goal 12, DEEP is broadening its Client Concierge Services to municipalities and small businesses through enhanced permit assistance, tools for smoother project implementation, better communication, and more information about relevant funding opportunities. Background on this goal is presented in DEEP’s 20BY26, Setting the Target: CT DEEP 2026 Goals (February 2024).

arrow-previous quarter Latest Progress (as of April 1, 2026) 

This goal is 75% complete.

In Q1 2026, the Concierge team sent out a Municipal Connections Newsletter featuring DEEP’s Remediation Programs and six (6) municipal email blasts with announcements and funding opportunities for towns. We also updated our Municipal Contacts lists with the new Municipal CEOs. 

Stakeholder engagement on the Community Renewable Energy Siting Tool (CREST) continued with an informational webinar to Sustainable CT in January 2026 and a UConn lecture on solar siting and permitting in February 2026. 

Photo of SBA Event HallThe Concierge team tabled at the Small Business Association’s Matchmaking Event on March 5, 2026, at the Convention Center in Hartford.

To help businesses stay on top of their permit compliance milestones, we published an interactive Compliance Calendar on our Compliance Assistance Hub. We also sent out three (3) Concierge email blasts with announcements, permitting updates, and funding opportunities for businesses.

Screenshot of DEEP's Compliance Calendar 

arrow-up next Up Next

We will continue to innovate around ways to connect small businesses and municipalities with permit assistance, compliance assistance, and funding opportunities. A new Small Business Assistance webpage and updated Municipal Primer webpage are coming soon!

In May 2026, we will issue a Municipal Connections edition about the Connecticut Wildlife Action Plan. Future Municipal Connections topics are planned to include Climate Resiliency and Natural Diversity Data Base (NDDB) Requests.

Please contact us anytime at DEEP.Concierge@ct.gov and subscribe to our permit updates and municipal news.

GOAL 12 PROGRESS FROM PREVIOUS QUARTERS

Fall 2025

In 2025, the Concierge Team held 22 Early Municipal Assistance meetings and 128 multi-media pre-application meetings for a grand total of 150 meetings, which is 1.5 times the amount held two years ago. We maintain a satisfaction rating of over 90%.

To ensure that the Concierge Team’s meetings are benefiting projects and business in Connecticut and making the application process easier to navigate, we analyzed multi-media pre-application metrics from 2023. As of September 30, 2025, of the approximately 100 pre-application meetings held in 2023, 60% of projects go on to apply for permits with DEEP. Of that 60%, half have completed the permitting process and half have started the permitting process. The top five categories of projects were solar, energy storage, dam repair, recycling, and redevelopment of brownfields. 19% of the pre-application meetings were for small businesses and 13% were for municipalities.

In Q4 2025, the Concierge Team organized multiple tabling events, including at the Council of Small Towns’ (COST) Fall Conference and the Connecticut Conference of Municipalities Annual (CCMA) Event. We also served on a panel at the Connecticut Power and Energy Society’s Fall Conference to discuss innovations and permit streamlining through the 20BY26 Initiative.

DEEP continued outreach through our Municipal Connections newsletter about the CREST map viewer, in addition to sending 4 Municipal and 2 Concierge email blasts with announcements and funding opportunities for towns and businesses. DEEP’s annual Permitting Report was published online.

Summer 2025
In Q3 2025, DEEP published a Municipal Connections Newsletter about the Expiring Federal Energy Tax Credits , in addition to monthly, tailored municipal email blasts with announcements and funding opportunities.

Photo of DEEP employees at a booth

We also made presentations at Connecticut Main Street Center  and Connecticut Water Works Association  and tabled at Sun Day  in September. 

DEEP continued to send monthly Concierge email blasts about permitting updates and public comment opportunities relevant to our small business partners, as well as holding regular meetings with CT organizations that support small businesses to coordinate on any assistance needed. 

DEEP updated forms and guidance for multi-media permit transfers that should clarify procedures for these transactions.

The Concierge Team rolled out project-specific Gantt charts to supplement our pre-application meeting summaries and further assist in project planning and permit sequencing.

Example Gantt Chart

Spring 2025

In April, DEEP issued a Municipal Connections newsletter about the re-launch of the CT Coalition for Sustainable Materials Management. DEEP also sent out two municipal update emails with time-sensitive information for municipalities on upcoming webinars/events, funding opportunities, and announcements.

The Concierge Team tabled at the June 2025 Sustainable CT annual meeting with representatives from DEEP’s Brownfields, Open Space, Urban and Community Forestry, and Sustainable Materials Management programs.

Photo of food scrap compost binWe updated our pre-permit application questionnaire with additional questions and information to help better guide applicants through the permitting process, including information about Natural Diversity Database reviews and questions for small businesses. We also posted a Municipal Composting sector permitting factsheet to provide a clear pathway for obtaining this popular permit.

Winter 2025

In January 2025, DEEP’s Concierge Team, along with our Brownfields, MS4, and Wildlife programs, tabled at the Council of Small Towns annual meeting. DEEP also issued a Municipal Connections newsletter edition about the impacts of salt on the environment to highlight our recently published cross-program informational website . DEEP published a new permit application for the Large-Scale Beneficial Filing Pilot Program, along with associated permitting factsheets and instructions.

In March 2025, DEEP’s Client Concierge Service celebrated its 5th anniversary of providing excellent customer service and permit assistance to municipal and business applicants. In celebration, DEEP created a flyer about our Concierge services and a factsheet about our Permitting and Siting Resources .

In support of DEEP’s permitting program progress on Goals 2 and 3, the Concierge Team upgraded our Permit Timeliness Dashboards to include interactive charts.

In addition to networking with organizations that support small businesses, we participated in EPA’s annual Small Business Environmental Assistance Program (SBEAP)  survey to collaborate on a national scale with other organizations.

Fall 2024

In December 2024, DEEP returned to the 2024 Connecticut Conference of Municipalities annual convention with staff from 7 different programs to connect with the over 1,000 attendees. Also in December, DEEP staff from the Concierge Team, Office of Environmental Review and Strategic Initiatives, Recreational Trails Program, and Brownfields Program presented a webinar for the Connecticut Main Street Coalition titled “DEEP & Downtown: An Update on DEEP's Municipal Services and Grant Programs.” DEEP sent out two Municipal Connections Newsletter editions, themed to Dam Safety and Wildfires, along with regular email updates to both our municipal and permit assistance subscribers.

As a first step in building out our specialized small business assistance, DEEP met with small business partners, such as CBIA, Connecticut Innovations, Climate Haven, CT Green Bank, and AdvanceCT, to understand how we can better support their entrepreneurs

Summer 2024
DEEP Municipal team

The Municipal Team coordinated with the Bureau of Information Technology Solutions (BITS) to launch an internal customer relationship management database solution to track municipal correspondence and inquiries, pre-application projects, Concierge projects, and environmental review projects.

The team issued a Municipal Connections newsletter about DEEP’s Bear Toolkit in September and sent municipal update emails with grant opportunities, announcements, events, and public comment opportunities approximately biweekly to 1,140 recipients, with an average open rate of 42% and a 11.5% click rate. DEEP now has an archive webpage for all past editions of the Municipal Connections newsletter.

The Concierge Team also began to hold Early Municipal Assistance meetings, bringing together municipal and DEEP permitting and grant staff to discuss prospective projects and provide guidance on potential regulatory requirements and funding opportunities.

Winter and Spring 2024

DEEP's Municipal Team began providing tailored services to municipalities through the launch of the new Municipal Hub webpage, Early Municipal Assistance Program, and Municipal Connections newsletter and email updates. 