Due to the personally identifying information contained in written limited appearance statements from the public, any written limited appearance statements that are received by the Council for any matter are available to be viewed at the Council’s office Monday through Friday from 8:30 a.m. to 4:30 p.m. or available to be sent via e-mail upon request. Please allow adequate time for processing.

Long Island Sound Resource and Use Inventory/Long Island Sound Blue Plan Survey

Page 2

Petition       550   600   650   700   750   800   850   900   950

Previous in List (1-499)          Next in List (1000-1499)  (Next in List (1500-1999)

 

  

PETITION NO. 500  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to the Mix Avenue Substation located at 690 Mix Avenue, Hamden, Connecticut.  Staff Report Approved 02/08/01  

PETITION NO. 501  AT&T Wireless PCS, LLC d/b/a AT&T Wireless Services petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to an existing Connecticut Light and Power Company electric transmission facility located at 27 Cannon Road, Wilton, Connecticut.  Staff Report Approved 03/01/01  

PETITION NO. 501A  New Cingular Wireless PCS, LLC (AT&T) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the approval upgrade in Petition No. 501 for the existing Connecticut Light and Power Company electric transmission facility located at 27 Cannon Road, Wilton, Connecticut.  Staff Report Approved 12/01/11  

PETITION NO. 502  Sprint Spectrum L.P. (Sprint PCS) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to an existing Connecticut Light and Power Company electric transmission facility located off of Sunnyside Avenue, Watertown, Connecticut.  Staff Report Approved 03/15/01   

PETITION NO. 503 Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the Montville - Dudley - Bean Hill transmission line in Montville, Connecticut.  Staff Report Approved 04/12/01  

PETITION NO. 504  United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of telecommunications equipment associated with a remote network meter reading system at Mohegan Road Drive, Shelton, and Merrimac Drive, Trumbull, Connecticut.  Staff Report 1 Staff Report 2 Approved 04/12/01   

PETITION NO. 505  Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the 115-kV transmission line located at the Hawley Lane Mall rear parking lot, off of Hawley Lane in Trumbull, Connecticut.  Staff Report Approved 04/12/01   

PETITION NO. 506 VoiceStream Wireless Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission line support structure located on the eastern side of Old Mill Road, Waterford, Connecticut.  Staff Report Approved 04/26/01    

PETITION NO. 507 Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of a 115-kV capacitor bank and associated equipment at the existing Connecticut Light and Power Company Stony Hill Substation, located on Stony Hill Road, Brookfield, Connecticut.  Staff Report Approved 05/10/01   

PETITION NO. 508  Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of a 115-kV capacitor bank and associated equipment to the existing Connecticut Light and Power Company Rocky River Substation, located on Route 7, New Milford, Connecticut.  Staff Report Approved 05/10/01  

PETITION NO. 509 VoiceStream Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of telecommunications equipment at the Devon Power Station, located off of Naugatuck Avenue, Milford, Connecticut.  Staff Report Approved 05/10/01   

PETITION NO. 510 VoiceStream Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed antenna installation of an existing Connecticut Light and Power Company communications tower located off Willis Street, Bristol, Connecticut.  Staff Report Approved 05/25/01   

PETITION NO. 511 Sprint Sites USA petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility located at 782 Old Clinton Road, Westbrook, Connecticut.  Staff Report Approved 07/11/01  

PETITION NO. 512 VoiceStream Wireless Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility located at 1320 Chopsey Hill Road, Bridgeport, Connecticut.  Staff Report Approved 06/25/02   

PETITION NO. 513  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission facility located off Quarry Road, Trumbull, Connecticut.  Staff Report Approved 06/06/01   

PETITION NO. 514 Wisvest-Connecticut, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing Bridgeport Harbor Station facility, Bridgeport, Connecticut.  Staff Report Approved 06/06/01   

PETITION NO. 515  Sprint Spectrum L.P. (Sprint PCS) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility located at 8 Sky Edge, Bethel, Connecticut. Staff Report Approved 07/11/01

PETITION NO. 516  Sprint Spectrum L.P. (Sprint PCS) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing Connecticut Light & Power Company electric transmission facility located at 100 Quarry Road, Trumbull, Connecticut. Staff Report Approved 07/11/01

PETITION NO. 517  Sprint Spectrum L.P. (Sprint PCS) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing Connecticut Light & Power Company electric transmission facility located at 18 Hilltop View Lane, New Milford, Connecticut. Staff Report Approved 07/11/01  

PETITION NO. 518  Crown Atlantic Company LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed relocation of an existing telecommunications tower and related equipment off North Street and Bates Lane, Greenwich, Connecticut. Findings of Fact Opinion Decision & Order Approved 10/03/01   

PETITION NO. 519 Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the Campville Substation to Weingart Road Junction 115-kV transmission line, Harwinton, Connecticut. Staff Report Approved 08/29/01   

PETITION NO 520 Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed reconstruction of the Weingart Road Junction to Canton Substation 115-kV transmission line, Harwinton, New Hartford, and Canton, Connecticut. Staff Report Approved 08/29/01   

PETITION NO. 521  Dominion Energy Nuclear Connecticut, Inc. Dominion Nuclear Connecticut, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Millstone Power Station, Waterford, Connecticut. Staff Report. Approved 08/08/01 Name Change 07/31/17

PETITION NO. 522  Cross-Sound Cable Company, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need (Certificate) is required for the construction, maintenance, and operation of an electric substation and interconnection facility located adjacent to the East Shore Substation and the New Haven Harbor Generating Facility, One Waterfront Street, New Haven, Connecticut. Findings of Fact Opinion Decision and Order Approved 01/03/02  

PETITION NO. 523  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to a proposed telecommunications facility located at 652 Glenbrook Road, Stamford, Connecticut. Denied 08/29/01

PETITION NO. 524  The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications on the UI 115kV Mix-Glen Lake overhead transmission line, Woodbridge and Hamden, Connecticut. Staff Report Approved 09/12/01

PETITION NO. 525  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission facility located on Morehouse Road, Fairfield, Connecticut. Staff Report Approved 09/12/01  

PETITION NO. 526  VoiceStream Wireless petition for a declaratory ruling that no Certificate of Environmental compatibility and Public Need is required for proposed modifications to an existing Connecticut Light and Power electric transmission facility located off Sound View Road, Greenwich, Connecticut. Staff Report Approved 10/03/01

PETITION NO. 527 AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of an existing Connecticut Light and Power electric transmission facility located on Nichols Avenue, Trumbull, Connecticut. Staff Report Approved 11/07/01

PETITION NO. 528  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of an existing Connecticut Light and Power electric transmission facility located on Chapel Street, Stratford, Connecticut. Decision and Staff Report  Approved 11/07/01

PETITION NO. 529  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of an existing Connecticut Light and Power electric transmission facility located at the Noroton Heights Railroad Station, Darien, Connecticut. Staff Report Approved 11/7/01  

PETITION NO. 529A  AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement tower at an existing Connecticut Light and Power facility located at Norton Heights Train Station, Darien, Connecticut. Staff Report. Approved 09/25/02   

PETITION NO. 530  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of an existing Connecticut Light and Power electric transmission facility located on Flanders Road, East Lyme, Connecticut. Staff Report Approved 11/29/01

PETITION NO. 531  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of existing Connecticut Light and Power electric transmission lines located between the Ely Avenue Junction and Glenbrook Substation in the Towns of Norwalk, Darien, and Stamford, Connecticut. Staff Report Approved 11/29/01

PETITION NO. 532  Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need (Certificate) is required for the modification of the existing CL&P line between CL&P's Montville Substation and the Mohegan Tribal Utility Authority's Fort Hill Farms Substation, Montville, Connecticut. Staff Report Approved 12/11/02

PETITION NO. 533  VoiceStream Wireless Corporation petition for a declaratory ruling that the proposed installation of an Enhanced 911 System qualifies as an exempt modification to VoiceStream's existing telecommunications facilities under the Council's jurisdiction. Staff Report Approved 12/11/01

PETITION NO. 534  Connecticut Light and Power (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need (Certificate) is required for the modification of an existing CL&P Card Substation in Lebanon, Connecticut. Staff Report Approved 12/11/01

PETITION NO. 535 – AT&T Wireless PCS, LLC and Crown Atlantic Company LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modification of an existing telecommunications tower located at 1455 Forbes Street, East Hartford, Connecticut. Findings of Fact Opinion Decision & Order Approved 05/21/02

PETITION NO. 536  Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of a 115-kV capacitor bank and associated equipment at the existing Connecticut Light and Power Company Franklin Drive Substation, located on Franklin Drive, in Torrington, Connecticut. Staff Report Approved 01/03/02  

PETITION NO. 537  Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of approximately 400 feet of 115-kV solid dielectric cable, two 115-kV capacitor banks, and associated equipment at the existing Connecticut Light and Power Company Mystic Substation, located on Greenmanville Road (Route 27), in Stonington, Connecticut. Staff Report Approved 01/03/02  

PETITION NO. 538  Crown Atlantic Company LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing telecommunications facility located at 44 Fyler Road, Suffield, Connecticut. Staff Report Approved 01/17/02

PETITION NO. 539  Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed installation of a new 115-kV line termination structure, two 115-kV capacitor banks, and associated equipment at the existing Connecticut Light and Power Company Canton Substation located off Morgan Road, in Canton, Connecticut. Staff Report Approved 01/17/02

PETITION NO. 540  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing Iroquois Pipeline by the Addition of a Natural Gas Compressor Station, located off High Meadow Road, Brookfield, CT. Decision Opinion Findings of Fact Approved 09/25/02

PETITION NO. 541  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of telecommunications equipment associated with a remote network meter reading system at 74 Cottage Street, Derby, Connecticut. Staff Report  Approved 02/14/02

PETITION NO. 542  Nextel Communications Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing Connecticut Light and Power Company electric transmission facility located east of Hawley Lane, near the Trumbull/Stratford town boundary, Connecticut. Staff Report Approved 02/14/02

PETITION NO. 542A  Sprint Corporation (Sprint) request to amend its declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed relocation of an existing Sprint facility attached to an Eversource electric transmission line structure (#830) onto an approved replacement electric transmission line structure (#830) within the existing Eversource right-of-way located at 560B Hawley Lane, Stratford, Connecticut.  Approved 03/29/18  

PETITION NO. 543  Sprint Spectrum L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing Connecticut Light and Power Company electric transmission facility located between 645 and 695 Chapel Street, Stratford, Connecticut. Staff Report Approved 02/14/02

PETITION NO. 544  Crown Atlantic Company LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed shared use of an existing telecommunications tower located at 200 Stanley Street, New Britain, Connecticut. Staff Report. Approved 02/14/02  

PETITION NO. 545  Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing Connecticut Light & Power Company electric transmission facility located east of Highland Avenue, Wallingford, Connecticut. Findings of Fact  Opinion Decision and Order Approved 09/05/02

PETITION NO. 546  Pratt & Whitney petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the existing cogeneration power facility at the Pratt & Whitney manufacturing facility, 400 Main Street, East Hartford, Connecticut. Staff Report Approved 03/07/02

PETITION NO. 547  Town of Wethersfield petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to an existing telecommunications facility at 2111 Berlin Turnpike, Newington, Connecticut. Staff Report Approved 04/25/02

PETITION NO. 548  Yankee Gas Services Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, operation, and maintenance of a distribution line in Southington, Berlin, and Meriden, Connecticut. Findings of Fact Opinion Decision and Order Approved 08/01/02  

PETITION NO. 549  Kleen Energy Systems, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed transmission line interconnection from the proposed Electric Generating Facility and Switchyard on River Road to existing 345 kV Connecticut Light and Power transmission line number 353. Consolidated with Docket 225   

PETITION NO. 550  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition that no Certificate of Environmental Compatibility and Public Need is required for the emergency installation of up to two temporary mobile gas turbine generating units at the South Norwalk Electric Works generating facility in the City of Norwalk, Connecticut. Staff Report (Withdrawn)

PETITION NO. 551  Omnipoint Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing communications tower located off Route 1 between River Street and Ford Drive, Old Saybrook, Connecticut. Staff Report Approved 04/25/02

PETITION NO. 552  Spectrasite Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing communications tower located at 1069 Connecticut Avenue, Bridgeport, Connecticut. Staff Report Approved 04/03/02

PETITION NO. 553  Town of South Windsor petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a fuel cell at the South Windsor High School, 161 Nevers Road, South Windsor, Connecticut. Staff Report Approved 04/03/02 

PETITION NO. 554  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of its existing interstate natural gas pipeline by the addition of a compressor station at 962 New Oronoque Road in Milford, Connecticut. Consolidated with Docket 226  

PETITION NO. 555  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing Iroquois Pipeline by additions to a Natural Gas Compressor Station, located off High Meadow Road, Brookfield, Connecticut.   (See Petition No. 540 above to view Findings of Fact, Opinion, and Decision and Order.) Approved 09/25/02   

PETITION NO. 556  Berkshire Power petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a temporary 69.2 MW peaking project in Stamford, Connecticut. Findings of Fact Opinion Decision & Order Approved 04/25/02 Revised Development and Management Plan Approved 03/11/03 

PETITION NO. 557  Spectrasite Communications, Inc. and AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility located at 644 Rimmon Road, Beacon Falls, Connecticut. Staff Report Approved 05/07/02

PETITION NO. 558  Omnipoint Facilities Network 2, L.L.C. (VoiceStream) for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility located behind 5 High Ridge Park, Stamford, Connecticut. Staff Report Approved 05/21/02

PETITION NO. 559  New England Site Management, LLC for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed extension to an approved telecommunications facility to be located at Powder Forest Business Park, off of Grist Mill Road, Simsbury, Connecticut. Staff Report  Approved 05/21/02

PETITION NO. 560  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification and relocation of existing transmission line structures in connection with the Connecticut Department of Transportation's reconstruction of the Quinnipiac River Bridge, New Haven, Connecticut. Staff Report Approved 07/11/02

PETITION NO. 561  Robert J. Rigney, et. al., petition for a declaratory ruling ordering a hearing to determine the effects associated with the construction, operation, and maintenance of a telecommunications facility located at 319-321 New Britain Avenue, Farmington, Connecticut. Staff Report Decision Denied 09/05/02

PETITION NO. 562  Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the emergency installation of up to two temporary mobile turbine generating units at the Rowan Street Substation in the City of Norwalk, Connecticut. Staff Report Approved 06/03/02

PETITION NO. 563  The Torrington Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of two 70 kilowatt microturbine generators at 59 Field Street, Torrington, Connecticut. Staff Report Approved 06/25/02

PETITION NO. 564  SBA Properties, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed shared use of an existing telecommunications facility located at 39 Ciro Road in North Branford, Connecticut. Decision Staff Report Approved 06/25/02

PETITION NO. 565  SBA Properties, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 768 Gilead Street, Hebron, Connecticut. Staff Report Approved 06/25/02

PETITION NO. 566  Meriden Gas Turbines LLC and the Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, operation, and maintenance of the South Kensington Switching Station in Berlin, and a 345 kV electric transmission line between the proposed CL&P South Kensington Switching Station and the Meriden Combined Cycle Generating Facility in Meriden and Berlin. Staff Report Approved 07/11/02

PETITION NO. 567  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to two 345-kV electric transmission lines from the proposed CL&P South Kensington Switching Station and the Meriden Combined Cycle Generating Facility through Southington, Meriden, and Berlin. Staff Report Approved 07/11/02

PETITION NO. 568  Thames Valley Communications, Inc. and the City of Groton petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 295 Meridian Street, Groton, Connecticut. Staff Report Approved 06/25/02

PETITION NO. 569 – Dominion Nuclear of Connecticut petition for a declaratory ruling that no certificate of environmental compatibility and public need is required for proposed change in use of low-level radwaste reduction facility at the Millstone Power Station. Staff Report Withdrawn

PETITION NO. 570  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed lightning protection modifications to the Mix Avenue Substation, located at 690 Mix Avenue in Hamden, Connecticut.  Staff Report Approved 07/11/02  

PETITION NO. 571  Sprint Spectrum L.P. petition for a declaratory ruling that no certificate of environmental compatibility and public need is required for the addition of antennas to the existing NRG Energy, Inc. facility located at 1866 River Road, Middletown, Connecticut. Staff Report Approved 07/11/02   

PETITION NO. 572  PSEG Fossil LLC petition for a declaratory ruling that no transfer of certificate of environmental compatibility and public need is required or that the certificate of environmental compatibility and public need be transferred. Approved 08/01/02

PETITION NO. 573  National Grid Communications, Inc. petition for a declaratory ruling that no certificate of environmental compatibility and public need is required for proposed modifications to a municipally approved telecommunications facility located at 157 Chestnut Mountain Road (a/k/a Chestnut Hill Road, a/k/a Route 190), Stafford, Connecticut. Staff Report  Approved 08/01/02   

PETITION NO. 574  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed underground transmission line relocation work in connection with the State of Connecticut Department of Transportation's Interstate 95 reconstruction project. Staff Report Approved 09/05/02

PETITION NO. 575  AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 57 Cook Road, Montville, Connecticut. Staff Report Approved 09/05/02

PETITION NO. 577 Sprint Spectrum, L.P. d/b/a Sprint PCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Northeast Utility power line pole located at 35 Shelley Road, Bethel, Connecticut. Staff Report Approved 09/25/02

PETITION NO. 578  SBA Properties, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 859 Goshen Hill Road, Lebanon, Connecticut. Staff Report Approved 09/05/02  

PETITION NO. 579  Omnipoint Communications, Inc. d/b/a T-Mobile petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need for the proposed modifications to a telecommunications facility located on 2 Hinckley Hill Road, Norwich, Connecticut. Staff Report Approved 09/05/02

PETITION NO. 580 Sprint Spectrum L.P. d/b/a Sprint PCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need for the proposed modifications to a telecommunications facility located at 761 Federal Road in Brookfield, Connecticut. Staff Report Approved 09/25/02   

PETITION NO. 581  AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for two silos and that the proposed modifications constitute a tower facility located at 91 Maple Avenue, East Haddam, Connecticut. Decision. Staff Report Approved 09/25/02

PETITION NO. 582  Northeast Utilities Service Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications at the existing Connecticut Light and Power Company Farmington Substation, located off Old Mountain Road, Farmington, Connecticut. Staff Report Approved 09/25/02   

PETITION NO. 583  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 19 Old Town Road, Hartland, Connecticut. Staff Report

PETITION NO. 584  Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the CL&P Norwalk Substation located on New Canaan Avenue, Norwalk, Connecticut. Staff Report Approved 10/23/02

PETITION NO. 585  AT&T Wireless, PCS, Inc., d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Middletown Generating Plant located at 1866 River Road, Middletown, Connecticut. Staff Report Approved 10/23/02

PETITION NO. 586  SpectraSite Communications, Inc., d/b/a SpectraSite petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 330 Middletown Road, Columbia, Connecticut. Staff Report Approved 02/11/03

PETITION NO. 587  SpectraSite Communications, Inc., d/b/a SpectraSite petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 135 Honey Hill Road, East Haddam, Connecticut. Staff Report Approved 10/23/02

PETITION NO. 588  Sprint Spectrum L.P. d/b/a Sprint PCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power (CL&P) transmission facility on Vale Road, Brookfield, Connecticut. Staff Report Approved 10/23/02  

PETITION NO. 589  Pinnacle Towers. Inc. d/b/a Pinnacle petition for a declaratory ruling and acknowledgement of the co-location, structural capability, radio frequency emission status and approval of the tower sharing request by WEDW-DTV of October 24, 2001 for the telecommunications facility located at Video Lane, Trumbull, Connecticut. Staff Report Approved 12/19/02

PETITION NO. 590  Omnipoint Communications, Inc. d/b/a T-Mobile USA, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power (CL&P) transmission facility off Rood Avenue, Windsor, Connecticut. Staff Report Approved 11/07/02   

PETITION NO. 591  Tower Ventures, Inc., petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the operation and maintenance of a proposed telecommunications facility to be located at 229-231 Ashford Center Road, Ashford, Connecticut. Re-filed as Docket 239   

PETITION NO. 592  Southwestern Bell Mobile Systems, LLC petition for 1) reconsideration of exempt modification EM-CING-062-020930, or in the alternative 2) a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement and modifications to an existing telecommunications facility located at 975 Mix Avenue, Hamden, Connecticut. Staff Report Approved 10/23/02

PETITION NO. 593  Sprint Spectrum L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement and relocation of an existing telecommunications facility located in the Goddard Hall complex at Eastern Connecticut State University on Eastern Drive off High Street in Willimantic, Connecticut. Staff Report Approved 11/07/02

PETITION NO. 594  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission facility located at 74 Birdsley Avenue, Meriden, Connecticut. Staff Report Approved 11/21/02   

PETITION NO. 595 Sprint Spectrum, L.P. d/b/a Sprint PCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to replace an existing CL&P structure on 153 Old Salem Road, Norwich, Connecticut. Staff Report Approved 12/19/02

PETITION NO. 596  Northeast Utilities Service Company agent for The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Falls Village Substation located in Canaan, Connecticut. Staff Report Approved 12/19/02

PETITION NO. 597  Northeast Utilities Service Company agent for The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Connecticut Light and Power Transmission Line at Mystic Aquarium, Stonington, Connecticut. Staff Report Approved 12/19/02

PETITION NO. 598  Yale University petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a fuel cell to be located on Yale's Campus in New Haven, Connecticut.  Staff Report Approved 12/19/02

PETITION NO. 599  Connecticut Department of Public Works petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, operation, and maintenance of a 3.75-megawatt gas-fired reciprocating engine electric generation facility located at Central Connecticut State University, New Britain, Connecticut. Staff Report 01/28/03-Ruled not our jurisdiction  

PETITION NO. 600  AT&T Wireless PCS, Inc. d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 20 Post Office Road, Westport, Connecticut. Staff Report Approved 01/08/03

PETITION NO. 601 AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement and relocation of an existing telecommunications facility located at 130 Ingham Hill Road, Old Saybrook, Connecticut. Staff Report Approved 01/08/03

PETITION NO. 602  AT&T Wireless PCS, Inc. d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission facility located at 989 Church Street, Wallingford, Connecticut. Staff Report Approved 01/08/03   

PETITION NO. 603  Lake Road Generating Company L.P. petition for a declaratory ruling that its existing electric generating facility complies with the Certificate and Decision and Order for operation on low sulfur fuel oil for Unit 1 and implementation plans for Units 2 and 3 in Killingly, Connecticut. Staff Report Approved 01/28/03

PETITION NO. 604  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modificatons to an existing Connecticut Light and Power transmission tower located at 76 Lyons Plain Road, Weston, Connecticut.  

PETITION NO. 605  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing telecommunications facility located at 315 Old Hartford Road, Colchester, Connecticut. Staff Report Approved 02/11/03  

PETITION NO. 606  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing transmission line tower located off of Bartholomew Road, Middletown, Connecticut. Staff Report Approved 06/19/03  

PETITION NO. 607  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing transmission line tower located at 126 Old Colchester Road, Waterford, Connecticut. Staff Report Approved 03/11/03  

PETITION NO. 608  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing telecommunications tower located at 70 Platt Road, Shelton, Connecticut. Staff Report Approved 03/25/03

PETITION NO. 609  United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing transmission line along the Metro-North Railroad Corridor between Baird Substation in Stratford and Congress Street Substation, Bridgeport, Connecticut. Staff Report Approved 03/11/03

PETITION NO. 610T  Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power Company electric transmission facility located off of Shelter Rock Road, Danbury, Connecticut. Staff Report Approved 02/25/03

PETITION NO. 611T  Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 2 Sunny Lane, Westport, Connecticut. Withdrawn.  

PETITION NO. 612E  Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing Glenbrook Substation, Stamford, Connecticut. Staff Report Approved 04/23/03  

PETITION NO. 613T  Sprint Sites USA petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 1919 Boston Post Road, Guilford, Connecticut. Staff Report Approved 04/09/03

PETITION NO. 614T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing telecommunications tower located at 450-478 West Main Street, Meriden, Connecticut. Staff Report Approved 03/11/03  

PETITION NO. 615E  Northeast Utilities, as agent for Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Stony Hill Substation, Brookfield, Connecticut. Staff Report Approved 03/11/03

PETITION NO. 616T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction of a telecommunications facility at 2 Huckleberry Hill Road, Brookfield, Connecticut. Staff Report Approved 04/09/03

PETITION NO. 617E  Waterside Power, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a temporary 69.2 MW peaking project in Stamford, Connecticut. Findings of Fact. Staff Report Approved 05/06/03

PETITION NO. 618T  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to an existing Connecticut Light and Power Company transmission structure located at 67 Hawthorne Mead Drive, Glastonbury, Connecticut. Staff Report Approved 08/26/03

PETITION NO. 619E  Select Energy Services, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required is required for the construction, operation and maintenance of a fuel cell to be located at St. Francis Hospital and Medical Center, 114 Woodland Street, Hartford, Connecticut. Staff Report Approved 05/06/03

PETITION NO. 620E  Connecticut Municipal Electric Energy and the South Norwalk Electric Works petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a temporary 23 MW combustion turbine electric generating unit to be located at the South Norwalk Electric Works Power Plant and Substation off of State Street, Norwalk, Connecticut. Staff Report Opinion Approved 05/20/03

PETITION NO. 621T  Sprint Spectrum L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Northeast Utilities transmission pole located at 228 Highland Avenue, Norwalk, Connecticut. Staff Report Approved 05/20/03

PETITION NO. 622T  Omnipoint Facilities Network 2, L.L.C., a subsidiary of T-Mobile USA, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission line located west off of Huntington Avenue, Stratford, Connecticut. Staff Report Approved 06/03/03   

PETITION NO. 622A T-Mobile Northeast LLC (T-Mobile) request to amend its declaratory ruling pursuant to Connecticut General Statutes §4-176 and §16-50k for the proposed relocation of an existing T-Mobile facility attached to an Eversource electric transmission line structure (#826) onto an approved replacement electric transmission line structure (#826) within the existing Eversource right-of-way located at 1975 Huntington Road, Stratford, Connecticut.  Approved 03/15/18   

PETITION NO. 623  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement and relocation of an existing telecommunications located at 585 New Haven Road, Naugatuck, Connecticut. Staff Report Approved 05/06/03

PETITION NO. 624E  BTEC Turbines LP petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a temporary 54 MW peaking project located at the intersection of Dock, Jefferson and Canal Streets in Stamford, Connecticut. WITHDRAWN  

PETITION NO. 625E  BTEC Turbines LP petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a temporary 54 MW peaking project located at the intersection of Dock, Jefferson and Canal Streets in Stamford, Connecticut.  WITHDRAWN  

PETITION NO. 626T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of a wireless telecommunications facility at 111 Middle Turnpike, Mansfield, Connecticut. Staff Report Findings of Fact Approved 09/09/03

PETITION NO. 627T  Sprint Spectrum L.P. and Omnipoint Facilities Network 2, L.L.C. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 206 Everett Road, Easton, Connecticut. Staff Report Approved 06/19/03

PETITION NO. 628T  Sprint Spectrum L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 500 Moose Hill Road, Monroe, Connecticut. Staff Report Approved 06/19/03  

PETITION NO. 629T  Southwestern Bell Mobile Systems, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at the Quinnipiac College Carl Hansen Student Center, New Road, Hamden, Connecticut. Staff Report Approved 06/19/03

PETITION NO. 630E  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing CL&P Southington substation located off Belleview Ave., Southington, Connecticut. Staff Report Approved 06/19/03   

PETITION NO. 631T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at Spring Hill Lane, Bethel, Connecticut. Withdrawn   

PETITION NO. 632E  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the 345-kV transmission lines from the Millstone Substation to the Southington Substation and the Scovil Rock Substation to East Shore Substation, Middletown and Middlefield, Connecticut. Staff Report 1  Staff Report 2 Approved 07/08/03 and 08/26/03  

PETITION NO. 633T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of a privately-owned distribution pole located at 575 Hillstown Road, Manchester, Connecticut. Staff Report Approved 07/08/03

PETITION NO. 634T  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement to an existing telecommunications facility located at 259 Commerce Street, East Haven, Connecticut. Staff Report Approved 07/08/03  

PETITION NO. 635T  Omnipoint Communications, Inc., a subsidiary of T-Mobile USA, Inc. petition for a declaratory r/ling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to existing Connecticut Light and Power Company electric transmission line support structure located on the east side of Route 121 (North Street), Milford, Connecticut. Staff Report Approved 07/08/03   

PETITION NO. 636T  Omnipoint Facilities Network 2, L.L.C., a subsidiary of T-Mobile USA, Inc., petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to existing United Illuminating electric transmission line support structure off of Timko Street, Fairfield, Connecticut. Decision. Staff Report Approved 07/22/03   

PETITION NO. 637  AT&T Wireless PCS, LLC d/b/a AT&T Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed attachment of telecommunications antennas and related equipment to a replacement light pole at 33 Neptune Avenue, East Haddam, Connecticut. Staff Report Approved 11/20/03

PETITION NO. 638 Lake Road Generating Company L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Lake Road Generating substation off of Lake Road, Killingly, Connecticut. Staff Report Approved 09/09/03  

PETITION NO. 639 – University of Connecticut petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a proposed cogeneration plant and substation to be constructed off of North Eagleville Road, Storrs, Connecticut. Staff Report. Approved 09/23/03   

PETITION NO. 640  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an impressed current ground bed off of West Avenue and Schoolhouse Road, Milford, Connecticut. Staff Report Approved 09/09/03  

PETITION NO. 641  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the Todd 30L substation located off of Todd Road, Wolcott, Connecticut. Staff Report Approved 08/26/03  

PETITION NO. 642  Omnipoint Communications, Inc., a subsidiary of T-Mobile USA, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing facility at 46 Brendan Street, Stafford Springs, Connecticut. Staff Report Approved 08/26/03  

PETITION NO. 643 The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to Dooley Substation at South Main Street, Middletown, Connecticut. Staff Report Approved 09/09/03

PETITION NO. 644  Sprint Spectrum, L.P., d/b/a Sprint PCS and Southwestern Bell Mobile Systems, LLC, d/b/a Cingular Wireless for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the addition of Sprint PCS and Cingular Wireless Antennas to an existing Connecticut Light & Power Company electrical transmission structure at 45 Maple Ridge Drive, Farmington, Connecticut. Staff Report Approved 10/29/03  

PETITION NO. 645  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to re-establish CL&P’s access to structure number 2688, Brookfield Substation to Brookfield Junction 115-kV Line off Laurel Hill Road, Brookfield, Connecticut. Staff Report Approved 10/14/03

PETITION NO. 646  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 115-kV capacitor bank and associated equipment at Haddam Substation at Route 154, Haddam, Connecticut. Staff Report Approved 12/09/03  

PETITION NO. 647  Nxegen, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a fuel cell at the Water Pollution Control Authority at 345 East Shore Parkway, New Haven, Connecticut. Staff Report Approved 10/14/03
 
PETITION NO. 648  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to extend the height of an existing telecommunications facility located at 650 Albany Turnpike, Canton, Connecticut. Staff Report Approved 10/29/03  
 
PETITION NO. 649  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to extend the height of the proposed Sprint Spectrum L.P. tower at 170 Southeast Road, New Hartford, Connecticut. Staff Report Approved 02/03/04  

PETITION NO. 650  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to tap into its existing 115-kV 1977 line at Glenbrook Substation located at Hamilton Avenue and Culloden Road, Stamford, Connecticut. Staff Report 1. Staff Report 2. Approved 10/29/03       

PETITION NO. 651  Connecticut Architectural Towers LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing telecommunications tower located at 151 Berkshire Road, Newtown, Connecticut. Staff Report Approved 11/20/03   

PETITION NO. 652  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to Southington 4C Substation, off of Belleview Avenue, Southington, Connecticut. Staff Report Approved 12/09/03   

PETITION NO. 653  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Branford 11J Substation, East Main Street, Branford, Connecticut. Staff Report Approved 12/22/03 

PETITION NO. 654 – Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction of a telecommunications facility to be located at 388 Norwich Road, Plainfield, Connecticut. Staff Report Approved 01/12/04  

PETITION NO. 655  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility at 42 South Street, Plymouth, Connecticut. Staff Report Approved 01/12/04   

PETITION NO. 656  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunication facility at 528 Wheelers Farm Road, Milford, Connecticut. Staff Report Approved 02/03/04  

PETITION NO. 657  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing CL&P Torrington substation located on the town line between the City of Torrington and the Town of Litchfield, Connecticut. Staff Report Approved 02/03/04  

PETITION NO. 658  The Waterside Power LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the temporary 69.2 MW Peaking Project in Stamford, Connecticut. Staff Report Approved 03/04/04 

PETITION NO. 659  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing telecommunications facility at the Goshen Fire Department, Waterford, Connecticut. Staff Report Approved 03/17/04   

PETITION NO. 660  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed antenna installation on an existing smokestack at 14 Gilbert Street, West Haven, Connecticut. Staff Report Approved 03/04/04   

PETITION NO. 661  Connecticut Light & Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed substation expansion, the installation of 115-kV capacitor banks and the installation of associated equipment at CL&P’s Frost Bridge 8R Substation in Watertown, Connecticut. Staff Report Approved 03/04/04  

PETITION NO. 662  South Norwalk Electric Works (SNEW) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed emergency installation of a temporary 22.8 MW peaking project off of Dr. Martin Luther King Jr. Boulevard, South Norwalk, Connecticut. Staff Report Approved 03/04/04 

PETITION NO. 663  South Norwalk Electric and Water (SNEW) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed repowering of an existing SNEW Generating Station located at One State Street, Norwalk, Connecticut. Findings of Fact          Opinion Decision and Order Approved 10/07/04   

PETITION NO. 664  Lake Road Generating Company L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification in operations at the Lake Road Generating facility located off of Lake Road, Killingly, Connecticut. Staff Report Approved 05/19/04   

PETITION NO. 665  AT&T Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing Connecticut Light and Power transmission structure located off of Hebron Road, Andover, Connecticut. Staff Report Approved 04/15/04   

PETITION NO. 666  Dominion Energy Nuclear Connecticut, Inc. Dominion Nuclear Connecticut, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need nor a modification of the existing Certificate is required to establish an indoor firing range at the Millstone Power Station, Waterford, Connecticut. Staff Report Approved 04/26/04 Name Change 07/31/17   

PETITION NO. 667  Message Center Management, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 1055 Wintergreen Avenue (West Rock), Hamden, Connecticut. Staff Report Not within Council jurisdiction.

PETITION NO. 668  Sprint Spectrum L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the relocation of its existing facility on Forbes Avenue, New Haven, Connecticut. Staff Report Denied 05/20/04  

PETITION NO. 669  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications to its existing 115/23-kilovolt Haddam 11C Substation located in Haddam, Connecticut. Staff Report Approved 06/09/04     

PETITION NO. 670 – Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications to its existing 115/23-kilovolt transmission line in the vicinity of the Haddam 11C substation located in Haddam, Connecticut. Staff Report Approved 07/13/04  

PETITION NO. 671 – Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 95 kW emergency generator and associated equipment at Haddam Neck 14B Substation in Haddam, Connecticut. Staff Report Approved 05/19/04  

PETITION NO. 672 Connecticut Municipal Electric Energy Cooperative petition for a declaratory ruling that the proposed installation of four 2 MW emergency generators is exempt from Council jurisdiction or alternatively, that no Certificate of Environmental Compatibility and Public Need is required for the proposed installations at 100 John Street and South Cherry Street, Wallingford, Connecticut. Staff Report Approved 05/19/04   

PETITION NO. 673  Omnipoint Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed antenna installation on an existing lattice tower located at 347 East Street, Wolcott, Connecticut. Staff Report Approved 06/09/04  

PETITION NO. 674  Southwestern Bell Mobile Systems, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing wireless telecommunications facility at 705 West Johnson Road, Cheshire, Connecticut. Staff Report Requested it be submitted as a docket (06/09/04)   

PETITION NO. 675  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that a Certificate of Environmental Compatibility and Public Need is not required for the modification of an existing CL&P transmission structure off Hilltop View Lane, New Milford, Connecticut. Staff Report Approved 06/09/04

PETITION NO. 676  The Third Taxing District of the City of Norwalk petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of three 2MW diesel generators at Norden Place, East Norwalk, Connecticut. Staff Report Approved 06/23/04  
 
PETITION NO. 677 – Sprint Sites USA petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at Great Hollow Road, Woodbury, Connecticut. Staff Report Approved 08/12/04  
 
PETITION NO. 678  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 186 Minortown Road, Woodbury, Connecticut. Staff Report. Approved 07/13/04
 
PETITION NO. 679  Omnipoint Facilities Network 2, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing guyed, lattice tower at 4 Dittmar Road, Redding, Connecticut. Withdrawn.
 
PETITION NO. 680  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to install a 40-foot stealth flagpole telecommunications tower on the roof of the existing Howard Johnson Hotel at 1052 Boston Post Road, Milford, Connecticut. Decision Staff Report. Approved 07/13/04   

PETITION NO. 681  Connecticut Light & Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of various equipment at CL&P’s Portland 21H Substation in Portland, Connecticut.  Staff Report  Approved  08/12/04  
 
PETITION NO. 682  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public need is required for the proposed installation of a power transformer and associated equipment at CL&P’s Canton 5R Substation in Canton, Connecticut. Staff Report Approved 07/13/04 
 
PETITION NO. 683  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications to its existing substation in the town of Redding, Connecticut.   Staff Report Approved 08/12/04  
 
PETITION NO. 684  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications to its existing substation in the town of Ridgefield, Connecticut.  Staff Report Approved 08/12/04   
 
PETITION NO. 685  Nextel Communications Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to Connecticut Light & Power’s Pole Structure # 10184 and Electric Transmission Line # 1618 in the Town of New Milford, Connecticut.  Tabled 08/26/04  
 
PETITION NO. 686 – Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a power transformer and associated equipment at CL&P’s Shaws Hill 24H substation in Watertown, Connecticut.  Staff Report Approved 08/12/04
 
PETITION NO. 687 – Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the establishment of a wireless telecommunications facility at the Harvest Baptist Church, 144 Litchfield Turnpike, New Hartford, Connecticut.  Findings of Fact Opinion Decision and Order Approved 12/01/04
 
PETITION NO. 688  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to establish a stealth flagpole telecommunications facility at the Quality Inn and Conference Center, 100 Pond Lily Avenue, New Haven, Connecticut. Decision.   Staff Report Denied 08/26/04
 
PETITION NO. 689  Connecticut Municipal Electric Energy Cooperative petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of an above ground 8000 gallon capacity fuel oil storage tank on South Cherry Street, Wallingford, Connecticut.   Staff Report Approved 08/12/04
 
PETITION NO. 690  GenCell Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Fuel Cell at 1432 Old Waterbury Road, Southbury, Connecticut and at 44 Weaver Road, Unit 5233, Storrs, Connecticut. Staff Report Approved 09/14/04   
 
PETITION NO. 691  Southwestern Bell Mobile Systems, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of cellular antennas and associated equipment at an existing CL&P electric transmission facility in Southington, Connecticut.  Staff Report Approved 08/26/04   
 
PETITION NO. 692  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a circuit breaker and associated equipment at Cos Cob Metro-North Railroad 35K Substation in Greenwich, Connecticut.  Staff Report Approved 09/14/04  
 
PETITION NO. 693  Southwestern Bell Mobile Systems, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of cellular antennas and associated equipment at an existing CL&P electric transmission facility in Manchester, Connecticut.    Staff Report Approved 09/14/04  
 
PETITION NO. 694 – Bozrah Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing electric substation located on Stockhouse Road in Bozrah, Connecticut. Staff Report Approved 10/07/04  
 
PETITION NO. 695  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a transformer and associated equipment at CL&P’s Windsor Locks 14K substation located in Windsor Locks, Connecticut.    Staff Report Approved 10/07/04  
 
PETITION NO. 696  Johnson Controls, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 200-kW Fuel Cell at the Water Pollution Control Facility located at 330 One Rod Highway, Fairfield, Connecticut. Staff Report Approved 10/26/04   
 
PETITION NO. 697  Nextel Communications of the Mid-Atlantic, Inc. d/b/a Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing monopole located at 143 Old Blue Hills Road, Durham, Connecticut. Decision and Staff Report  Approved 05/11/05   
 
PETITION NO. 698  Department of Public Works petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 25 kW fuel cell at the Dinosaur State Park, Rocky Hill, Connecticut.   Staff Report Approved 12/01/04   
 
PETITION NO. 699 The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to interconnect UI’s existing underground 115 kV 8700 transmission line with the Metro North rail yard 26.4 kV supply station located on Union Avenue in New Haven, Connecticut.  Staff Report Approved 12/21/04   
 
PETITION NO. 700  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the 115-kV transmission circuits at the Triangle 11A Substation in Danbury, Connecticut.  Staff Report Approved 01/24/05   
 
PETITION NO. 701  Nextel Communications Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to a Connecticut Light & Power Company electric transmission facility at 145 Beebe Hill Road, tower #2010 in Canaan, Connecticut.     Staff Report Approved 01/24/05   
 
PETITION NO. 702  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed Plumtree to Triangle 115-kV Transmission Upgrade Project in the towns of Bethel and Danbury, Connecticut. Findings of Fact Opinion Decision and Order Approved 06/28/05  
 
PETITION NO. 703  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to a light pole located at Chesley Park, 35 Wildwood Street, New Britain, Connecticut. Staff Report Acknowledged as not within Council's jurisdiction 03/03/05   
 
PETITION NO. 704 Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Norwalk Harbor Substation, Norwalk, Connecticut. Staff Report Approved 03/03/05   
 
PETITION NO. 705 The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Milvon Substation, Milford, Connecticut.    Staff Report Approved 03/15/05  
 
PETITION NO. 706 Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 115-kV series line reactors and associated equipment at the Southington 4C substation in Southington, Connecticut.  Staff Report  Approved 04/19/05  
 
PETITION NO. 707  Nextel Communications of the Mid-Atlantic, Inc. d/b/a Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Fuel Cell System at 188 Moody Road, Enfield, Connecticut.    Decision Approved 04/19/05   
 
PETITION NO. 708 Westport Broadcasting Co., LLC, Optasite, Inc. and New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to replace an existing tower or to add a second tower at an existing facility site located at 160 Deer Run Road, Wilton, Connecticut. Withdrawn.  
 
PETITION NO. 709 Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to the Long Mountain 13J Switching Station in New Milford, Connecticut. Staff Report  Approved 04/19/05  
 
PETITION NO. 710  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a power transformer and associated equipment at Barbour Hill Substation, South Windsor, Connecticut.  Staff Report Approved 04/19/05   
 
PETITION NO. 711  PPL Energy Services Holding, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Fuel Cell power plant for the Pepperidge Farm Inc. Facility located at 1414 Blue Hill Avenue, Bloomfield, Connecticut.  Staff Report  Approved 05/11/05  
 
PETITION NO. 712 Omnipoint Communications, Inc. (T-Mobile USA) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed pole replacement and antenna installation located at 41 Padanaram Road, Danbury, Connecticut.   Staff Report Approved 06/08/05   
 
PETITION NO. 713 – Sprint Spectrum, L.P. d/b/a Sprint PCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing Connecticut Light and Power transmission structure and antenna installation located at 595 Keeney Street, Manchester, Connecticut.  Staff Report Approved 06/08/05   
 
PETITION NO. 714  Sprint Spectrum LP petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 197 South Street, Vernon, Connecticut. Staff Report Approved 06/08/05  
 
PETITION NO.  715  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an emergency generator and associated equipment at CL&P’s Middletown Substation. Staff Report Approved 07/20/05 
 
PETITION NO. 716  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an emergency generator and associated equipment at CL&P’s Norwalk Harbor Substation.  Staff Report Approved 07/20/05  
 
PETITION NO. 717  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an emergency generator and associated equipment at CL&P’s Montville Substation.  Staff Report Approved 07/20/05  
 
PETITION NO. 718  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an emergency generator and associated equipment at CL&P’s Devon Substation, Milford, Connecticut.  Staff Report Approved 07/20/05   
 
PETITION NO. 719  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an emergency generator and associated equipment at CL&P’s South Meadow Substation, Hartford, Connecticut.  Staff Report Approved 06/08/05   
 
PETITION NO. 720  The University of Connecticut (UCONN) and Connecticut Light & Power Company petition for a declaratory ruling of no significant adverse environmental effect for the proposed 69-kV underground interconnection line between the UCONN substation and CL&P’s 800 line in Mansfield, Connecticut.   Staff Report Approved 06/08/05   
 
PETITION NO. 721  Nextel Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 171 Town Hill Road, Plymouth, Connecticut. Staff Report Approved 06/28/05  
 
PETITION NO. 722 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 70 Platt Road, Shelton, Connecticut.     Findings of Fact Opinion Decision and Order Approved 11/03/05   
 
PETITION NO. 723 – New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 5 Old Town Park Road, New Milford, Connecticut.   Staff Report Approved 07/20/05   
 
PETITION NO.  724  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing transmission structure located off Petersen Road in Granby, Connecticut. Staff Report Approved 11/03/05 
 
PETITION NO. 725 – Iroquois Gas Transmission System petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of an impressed current ground bed adjacent to its existing natural gas pipeline in Milford, Connecticut.  Staff Report Approved 07/20/05    
 
PETITION NO.726 Nextel Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to an existing telecommunications tower located at 331 Route 80, Guilford, Connecticut. Staff Report Approved 08/24/05  
 
PETITION NO. 727 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to expand an existing telecommunications facility located at 119 Empire Avenue, Meriden, Connecticut.   Staff Report Approved 08/24/05   
 
PETITION NO 728  New Cingular Wireless PCS, LLC d/b/a Cingular Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to a light pole located at Wicker Street, Putnam, Connecticut. Denied 09/28/05   
 
PETITION NO. 729  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the existing CL&P Green Hill 30R Substation located in Madison, Connecticut. Staff Report Approved 08/24/05  
 
PETITION NO. 730  Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications and replacement to an existing telecommunications facility located at 60 Commerce Street, East Haven, Connecticut. Staff Report Approved 08/24/05 Modified 12/21/05   
 
PETITION NO. 731  Omnipoint Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 287 Main Street, East Hartford, Connecticut. Staff Report Approved 08/24/05  
 
PETITION NO. 732 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 115-kV circuit breaker and associated equipment to its existing Flanders 11Y Substation in East Lyme, Connecticut. Staff Report Approved 09/28/05  
 
PETITION NO. 733  NextG Networks, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed microcellular antenna installations located in public rights-of-way throughout the State of Connecticut.  Withdrawn  
 
PETITON NO. 734  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power transmission line structure (#1102) located in Norwalk, Connecticut. Staff Report Approved 09/28/05  
 
PETITION NO. 735  Nextel Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 4 Dittmar Road, Redding, Connecticut.   Staff Report 1 Staff Report 2 Staff Report 3 Denied 12/14/05  
 
PETITION NO. 736  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 126 Ledge Road, Darien, Connecticut. Staff Report Denied 09/28/05  
 
PETITION NO. 737  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed Manchester to Hopewell 115-kV Transmission Line Reconductor Project in the Towns of  Manchester and Glastonbury.        Findings of Fact Opinion Decision and Order Approved 09/14/06 D&M Change Approval
 
PETITION NO. 738 – New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located on Knowlton Road, Ashford, Connecticut.    Staff Report
 
PETITION NO. 739 Dianet Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications on a number of existing street light poles/utility poles located in the Town of Greenwich, Connecticut. Withdrawn.  
 
PETITION NO. 740  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 229 Cheshire Road, Prospect, Connecticut.    Staff Report Approved 10/19/05   
 
PETITION NO. 741  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at Quinnipiac University on Mount Carmel Road in the Town of Hamden, Connecticut.    Staff Report Approved 10/19/05  
 
PETITION NO. 742  PSEG Power Connecticut LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for Phase 1 of Bridgeport Harbor Unit No.3  Mercury Emissions Reduction Project, Bridgeport, Connecticut.  Staff Report Approved 11/03/05.  Notification of Retirement 10/29/21 Council Acknowledgement of Retirement Transfer of Ownership of Surrendered Declaratory Ruling
 
PETITION NO. 743 New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located off Clintonville Road (Route 22), North Haven, Connecticut.      Staff Report Approved 12/14/05  
 
PETITION NO. 744  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located off Whitney Avenue (State Route 10), Hamden, Connecticut.    Staff Report Approved 12/14/05  
 
PETITION NO. 745  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of an existing CL&P telecommunication tower in the Town of Prospect, Connecticut. Staff Report Approved 11/17/05  
 
PETITION NO. 746  The Connecticut Municipal Electric Energy Cooperative petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 2 MW emergency generator at Falls Avenue, Hollyhock Island, Norwich, Connecticut.    Staff Report Approved 11/17/05   
 
PETITION NO. 747  The Connecticut Municipal Electric Energy Cooperative petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of two additional 2 MW emergency generators at 100 John Street, Wallingford and the relocation of one existing 2 MW emergency generator to South Cherry Street, Wallingford, Connecticut.    Staff Report Approved 11/17/05  
 
PETITION NO. 748  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a stealth pole at 1 Fairfield Avenue, Danbury, Connecticut. Staff Report Approved 12/14/05  
 
PETITION NO. 749 Nextel Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed extension of a telecommunications facility at 3 Edmond Road, Newtown, Connecticut.    Staff Report Approved 12/14/05
 
PETITION NO. 750  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a pole within an existing wireless communication tower and array located at 100 Berlin Road, Cromwell, Connecticut.  Staff Report Approved 01/25/06 Facilities Subject to a Maintenance Agreement with American Tower Corporation, 11/19/24
 
PETITION NO. 751  Manchester Methane, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a 3.2 megawatt methane renewable energy project at the NORCAP Landfill in East Windsor, Connecticut.  Staff Report Approved 2/22/06 Staff Report for Modifications Modified 07/27/06  
 
PETITION NO. 752 – Nextel Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of a Connecticut Light & Power Company electric transmission structure east of Highland Avenue, Wallingford, Connecticut.  
 
PETITION NO. 753  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a ten foot (10’) extension to an existing wireless communication monopole located at 69 Wheeler Street, New Haven, Connecticut.    Staff Report Approved 01/25/06  
 
 
PETITION  NO. 755 Iroquois Gas Transmission System, L.P. petition for declaratory ruling that the Connecticut Siting Council does not have jurisdiction over additions to Iroquois’ authorized Natural Gas Compressor Station located off of High Meadow Road in Brookfield, Connecticut. Staff Report Approved 02/22/06 
 
PETITION NO. 755A  (Petition Record)  Iroquois Gas Transmission System, L.P. application submitted to the Federal Energy Regulatory Commission to modify the existing interstate natural gas pipeline by the addition of a compressor station off of High Meadow Road in Brookfield, Connecticut. Findings of Fact Opinion and Recommendations Voted on 06/27/06  
 
PETITION NO. 756  PSEG Power Connecticut LLC petition for declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for Phase 2 of Bridgeport Harbor Unit No. 3 Mercury Emissions Reduction Project, Bridgeport, Connecticut. Staff Report Approved 03/22/06 Notification of Retirement 10/29/21 Council Acknowledgement of Retirement  Transfer of Ownership of Surrendered Declaratory Ruling
 
PETITION NO. 757 Algonquin Gas Transmission, LLC petition for declaratory ruling that the Connecticut Siting Council does not have jurisdiction over the proposed installation of a natural gas compressor station located in Oxford, Connecticut. Staff Report Approved 02/22/06   
 
PETITION NO. 757A – An application by Algonquin Gas Transmission, LLC submitted to the Federal Energy Regulatory Commission.  Algonquin proposes to construct a Natural Gas Compressor Station at one of two locations in (Petition Record) Oxford, Connecticut, and a Natural Gas Meter Station off High Meadow Road, Brookfield, Connecticut.      Findings of Fact Opinion and Recommendations Voted on 06/27/06  
 
PETITION NO. 758  Optasite, Inc. petition for a declaratory ruling that an amended Certificate of Environmental Compatibility and Public Need is not required for the modification of an existing facility located at 3 Edmond Road in Newtown, Connecticut. Approved 03/08/06 
 
PETITION NO. 759 – Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of a Connecticut Light & Power Company electric transmission structure located at 61 Hawthorne Drive North, New London, Connecticut. Staff Report Approved 03/08/06
 
PETITION NO. 760  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Sasco Creek Substation located at Clayton Street, Westport, Connecticut. Staff Report Approved 03/22/06  
 
PETITION NO. 761 Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Frost Bridge Substation, located on Frost Bridge Road, Watertown, Connecticut. Staff Report Approved 04/27/06 
 
PETITION NO. 762  Dominion Energy Nuclear Connecticut, Inc. Dominion Nuclear Connecticut, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of a generator step-up transformer and four new towers to support on-site power lines at Millstone Power Station, Waterford, Connecticut. Staff Report Approved 05/17/06 Name Change 07/31/17
 
PETITION NO. 763 – Dr. Carl Bornemann petition for a declaratory ruling to void the Connecticut Siting Council’s ruling on Petition No. 701 submitted by Nextel Communications, Inc. to modify CL&P transmission structure #2010 located near 145 Beebe Hill Road, Canaan, Connecticut. Decision Dismissed 10/12/06
 
PETITION NO. 764  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a ten foot (10’) extension to an existing CL&P transmission tower located at 437 Hobart Street, Southington, Connecticut. Staff Report Approved 05/17/06
 
PETITION NO. 764A  T-Mobile Northeast LLC (T-Mobile) request to amend its declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to relocate an existing T-Mobile facility attached to an Eversource transmission line structure (#1814) onto an approved replacement electric transmission line structure (#1814) within the existing Eversource right-of-way located at 437 Hobart Street, Southington, Connecticut. Approved 09/15/16  
 
PETITION NO. 765  Optasite, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing tower facility at 107 Wilcox Road, Stonington, Connecticut. Staff Report Approved 06/07/06  
 
PETITION NO. 766  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing facility located at 850 West Main Street, Branford, Connecticut. Staff Report Approved 05/17/06 
 
PETITION NO. 767  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the CL&P’s South End Substation, Stamford, Connecticut. Staff Report Approved 06/07/06   
 
PETITION NO. 768  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the CL&P’s Waterside Substation, Stamford, Connecticut. Staff Report Approved 06/07/06  
 
PETITION NO. 769  Optasite, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed relocation of the telecommunications facility approved at 459 Burr Road, Southbury, Connecticut. Approved 06/07/06
 
PETITION NO. 770 / DOCKET NO. 272 Middletown Royal Oak Residents petition for a declaratory ruling to intervene or be designated as parties in Docket No. 272, stating the Royal Oak Bypass proposed by The Connecticut Light and Power Company in its proposed Development and Management Plan (D&M Plan) for Docket No. 272 is not in accordance with the Findings of Fact, Opinion, and Decision and Order issued on April 7, 2006; proper notice was not given to the Royal Oak Bypass residents; and the new route would adversely affect their properties and way of life.  Petition rendered moot by Council decision on Royal Oak Bypass Plan, 06/07/06  
 
PETITION NO. 771  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing transmission structure located at 652 River Road (State Route 12), Lisbon, Connecticut. Staff Report Approved 06/07/06  
 
PETITION NO. 772  Waterside Power, LLC, petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to the Waterside 69.2 MW peaking project, 17 Amelia Place, Stamford, Connecticut. Staff Report Approved 07/27/06
 
PETITION NO. 773  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing facility located at 8 Park Lane, Newtown, Connecticut.  Staff Report Approved 07/27/06
 
PETITION NO. 774  Omnipoint Communications, Inc. and New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing facility located at 136 Vinegar Hill Road, Ledyard, Connecticut. Staff Report Approved 07/27/06  
 
PETITION NO. 775 – T-Mobile petition for a declaratory ruling that no Certificate is required for the proposed modifications to an existing facility at 259 Commerce Street, East Haven, Connecticut. Withdrawn  
 
PETITION NO. 776  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing facility located at 575 Hillstown Road, Manchester, Connecticut. Staff Report Approved 07/26/06  
 
PETITION NO. 777  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing facility located at 126 South Street (a/k/a 42 South Street), Plymouth, ConnecticutStaff Report Approved 07/26/06  
 
PETITION NO. 778  Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed repowering of the Alfred L. Pierce Generating Station located at 195 East Street, Wallingford, Connecticut. Staff Report 1  Staff Report 2 Approved 09/28/06
 
PETITION NO. 779 – New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing facility located at 138 Main Street, Coventry, Connecticut. Decision/Staff Report Approved 08/31/06  
 
PETITION NO. 780  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Plumtree Substation, Bethel, Connecticut. Staff Report Approved 08/31/06  
 
PETITION NO. 781 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 36 Ayer Road, Franklin, Connecticut. Staff Report Approved 08/31/06  
 
PETITION NO. 782  ClearLinx Network Corporation petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the proposed construction of a stealth Distributed Antenna System along the Merritt Parkway corridor from east of New York state line to Westport, Connecticut.  Withdrawn  
 
PETITION NO. 783  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Barbour Hill Substation, South Windsor, Connecticut. Staff Report Approved 09/28/06  
 
PETITION NO. 784 – Plainfield Renewable Energy, LLC petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance, and operation of a 37.5 MW Wood Biomass Generating Project, Plainfield, Connecticut. Record Findings of Fact Opinion Decision and Order Approved 05/22/07 
 
PETITION NO. 785  Bridgeport Fuel Cell Park petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 14.4 MW Fuel Cell Electric Project located on Hancock Street, Bridgeport, Connecticut. Filing Staff Report Approved 10/31/06  
 
PETITION NO. 786  The United Illuminating Company petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing United Illuminating Company’s transmission line for the Fairfield Rail Station, located off of Timko Street and Frank Street, Fairfield, Connecticut. Staff Report Approved 09/14/06  
 
PETITION NO. 787  The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to install two new steel poles within an existing United Illuminating Company’s transmission line (Circuit Nos. 1560 and 1594) north of the Ansonia Substation 3 Riverside Drive, Ansonia, Connecticut. Staff Report Approved 09/28/06  
 
PETITION NO. 788  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Cedar Heights Substation, located at Rapids Road, Stamford, Connecticut. Staff Report Approved 09/28/06  
 
PETITION NO. 789  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the Connecticut Light & Power Company’s Stony Hill Substation, located on Stony Hill Road, Brookfield, Connecticut.  Staff Report Approved 09/28/06  
 
PETITION NO. 790  The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed Distribution Automation Master Radio Project at four of The United Illuminating Company’s substations: Trap Falls Substation, Armstrong Road, Shelton; Indian Well Substation, Roosevelt Drive, Derby; Ansonia Substation, Riverside Drive, Ansonia; and North Haven Substation, State Street, North Haven, Connecticut.   Staff Report Approved 10/10/06  
 
PETITION NO. 791  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing telecommunications facility located at 130 Ledge Road, Darien, Connecticut.  Staff Report Approved 10/31/06  
 
PETITION NO. 792  Global Signal petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the relocation, construction, maintenance and operation of a telecommunications facility located at 1919 Boston Post Road, Guilford, Connecticut.  P&I Approval and Request to be Resubmitted as a Docket
 
PETITION NO. 793 Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power Company 115-kV transmission line, Brookfield, Connecticut. Staff Report Decision Approved 02/06/07  
 
PETITION NO. 794  Clearview Renewable Energy, LLC petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 29.0 MW Mixed Biomass Generating Project located at the Kofkoff Egg Farm, Bozrah, Connecticut.  Withdrawn 10/07/09  
 
PETITION NO. 795 – Sprint Nextel Corporation Petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is Required for the temporary placement of a cell on wheels (COW) adjacent to the Danbury Fair Mall at 10 Precision Road, Danbury, Connecticut. Approved 11/22/06 Extension of Time Approval
 
PETITION NO. 796 – Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power Company transmission line, located at 8 Sky Edge Lane, Bethel, Connecticut.   Staff Report Approved 01/04/07  
 
PETITION NO. 797  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power Company substation, located at 401 Flax Hill Avenue, Norwalk, Connecticut. Decision Approved 01/18/07  
 
PETITION NO. 798  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing telecommunications facility located at 477 Route 7, Sharon, Connecticut. Decision and Staff Report  Approved 02/06/07  
 
PETITION NO. 799  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing gas station sign with a telecommunications pole located at 207 West Street, Cromwell, Connecticut.  Decision and Staff Report Approved 01/18/07  
 
PETITION NO. 800  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing telecommunications facility located at Willis Street, Bristol, Connecticut. Decision and Staff Report Approved 01/18/07  
 
PETITION NO. 801  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power Company substation, located at Naugatuck Avenue, Milford, Connecticut.  Decision and Staff Report Approved 01/18/07   
 
PETITION NO. 802  Petition for a Declaratory Ruling filed by the Town of Middlebury, Mr. Raymond Pietrorazio, Citizens for the Defense of Oxford, William Stowell, and Mira Schachne (Petitioner) contending that the Connecticut Siting Council actions to extend the Certificate deadline are void in accordance with Conn. Gen. Stat. § 16-50k(c), § 16-50l(d), § 16-50m(b), or § 4-181a(b). Decision Decided on 01/04/07  
 
PETITION NO. 803 – Sprint Nextel Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 130 Ledge Road, Darien, Connecticut. Staff Report Decision Approved 04/10/07  
 
PETITION NO. 804 – Sprint Nextel Corporation Petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility, located at 234 Melba Street, Milford, Connecticut. Staff Report Decision Approved 04/10/07  
 
PETITION NO. 805 - Ansonia Generation LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance, and operation of a 58.4 MW combined heat and power natural gas-fired electric generating facility and transmission line tap located at 75 Liberty Street, Ansonia, Connecticut. Link to Other Documents in this Proceeding Decision Approved 07/26/07    
 
PETITION NO. 806 – Omnipoint Communications, Inc. (T-Mobile) Petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility, located at 191 Middle Haddam Road, Portland, Connecticut. Staff Report Decision Approved 5/01/07  
 
PETITION NO. 807  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 723 Farmington Avenue, New Britain, Connecticut. Staff Report Decision Approved 5/01/07   
 
PETITION NO. 808  FirstLight Hydro Generating Company petition for a declaratory ruling that the Connecticut Siting Council does not have jurisdiction for the proposed upgrade modifications to an existing Shepaug Hydroelectric Facility located on the Housatonic River, Southbury, Connecticut. Decision Ruling issued on 05/01/07  
 
PETITION NO. 809  Extenet Systems, Inc. petition for a declaratory ruling that the Connecticut Siting Council does not have jurisdiction or, in the alternative, that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction of a Distributed Antenna System along the Merritt Parkway from New York state line to Westport, Connecticut.   Findings of Fact Opinion and Decision and Order Record Ruling issued on 11/05/07   
 
PETITION NO.  810  City of Middletown petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance, and operation of a 200 kW fuel cell located at the new Middletown High School, Wilderman’s Way, Middletown, Connecticut. Staff Report Decision Approved 06/07/07  
 
PETITION NO. 811  Reconsideration of Issues Decided in Petition No. 344. Decision and Staff Report
 
PETITION NO. 812  Connecticut Jet Power LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance, and operation of two 20 MW peaking units located at the Cos Cob facility, Sound Shore Drive, Greenwich, Connecticut. Decision Staff Report Approved 07/26/07   
 
PETITION NO. 813  Kimberly-Clark Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance, and operation of a combined heat and power electric generating facility, located at 58 Pickett District Road, New Milford, Connecticut. Staff Report Decision Approved 06/07/07    
 
PETITION NO. 814  Connecticut Light & Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to two existing 115-kV transmission lines, located between Carpenter Lane Junction and North Wallingford Substation, and associated conductor work near Colony Substation, Wallingford, Connecticut. Staff Report Decision Approved 06/07/07   
 
PETITION NO. 815 – Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that the Connecticut Siting Council has an advisory role to the Federal Energy Regulatory Commission regarding Iroquois’s 08/09 expansion project in Brookfield, Newtown, and Milford, Connecticut.  Findings of Fact   Opinion/Recommendations  Decided 11/29/07  
 
PETITION NO. 816  Waterbury Generation LLC petition for a declaratory ruling regarding the process to be used by the Connecticut Siting Council for review and approval of a proposed combustion turbine peaking facility, located at 725 Bank Street, Waterbury, Connecticut. Decision Letter of 7/03/07
 
PETITION NO. 817  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a 2 MW emergency generator located at John Street, Wallingford, Connecticut. Staff Report Approved 07/03/07  
 
PETITION NO. 818  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Frost Bridge 8R Substation located at Frost Bridge Road, Watertown, Connecticut. Staff Report Approved 07/03/07
 
PETITION NO. 819  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Weston Substation, Weston Road, Weston, Connecticut. Decision and Staff Report   Approved 07/03/07  
 
PETITION NO. 820 Omnipoint Communications, Inc. a.k.a. T-Mobile petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of antennas inside an existing silo located at 90 Hattertown Road, Newtown, Connecticut. Staff Report Approved 07/26/07  
 
PETITION NO. 821  Connecticut Light & Power Company’s petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing CL&P substation located at Depot Hill Road, Enfield, Connecticut. Staff Report Approved 07/26/07 Notice of Temporary Mobile Transformer Placement and Council Acknowledgement
 
PETITION NO. 822  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications tower located at 1662 Gold Star Highway, Groton, Connecticut. Staff Report Approved 07/26/07  
 
PETITION NO. 823 Sprint Nextel Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light & Power electrical transmission structure (pole #8012) located at Maple Ridge Drive, Farmington, Connecticut. Staff Report Approved 08/29/07  
 
PETITION NO. 824 The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing telecommunications facility located on Chapel Hill Road, Montville, Connecticut. Staff Report Approved 07/26/07  
 
PETITION NO. 825 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed visual improvements at the Triangle Substation facility in Danbury, Connecticut. Staff Report Approved 08/29/07  
 
PETITION NO. 826 Sprint Nextel Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the placement of a temporary mobile radio communications facility (COW) at Quinnipiac University Law School, 60 West Woods Road, Hamden, Connecticut.  Staff Report Decision Approved 07/26/07  
 
PETITION NO. 827  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification of an existing telecommunication tower owned by Northeast Utilities located at 705 West Johnson Avenue, Cheshire, Connecticut.  Staff Report Approved 09/25/07  
 
PETITION NO. 828  DFG-ERG Milford, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a fuel cell facility located at 775 Oronoque Road, Milford, Connecticut.   Staff Report Status Update - Not Constructed Letter Approved 10/16/07  
 
PETITION NO. 829  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of an existing telecommunications tower located at 626 Glenbrook Road, Stamford, Connecticut.   Staff Report Approved 11/05/07   
 
PETITION NO. 830  Wesleyan University petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed 2,398 kW natural gas-powered cogeneration project located at 280 Williams Street, Middletown, Connecticut. Staff Report Approved 10/16/07 
 
PETITION NO. 831  Waterbury Generation LLC petition for a declaratory ruling no Certificate of Environmental Compatibility and Public Need is required for the construction of an electric generating facility and associated transmission line tap located at 725 Bank Street, Waterbury, Connecticut. Record Findings of Fact Opinion Decision and Order Approved 04/10/08  
 
PETITION NO. 832  Nextel Communications, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at North Main Street, Marlborough, Connecticut. Staff Report Approved 02/28/08  
 
PETITION NO. 833  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing double-circuit 115-kV transmission line from Christian Street Junction in Oxford, Connecticut, to Beacon Falls Substation in Beacon Falls, Connecticut.  Staff Report Approved 11/29/07  
 
PETITION NO. 834  Watertown Renewable Power, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 30 MW biomass gasification generating project located at Echo Lake Road, Watertown, Connecticut.  Record Findings of Fact Opinion Decision Approved 04/24/08  
 
PETITION NO. 835  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing telecommunications facility located at 1294 Pleasant Valley Road North, Groton, Connecticut.  Staff Report Approved 12/13/07  
 
PETITION NO. 836 – Waterside Power LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction and operation of a permanent peaking facility located at 17 Amelia Place, Stamford, Connecticut. Record Findings of Fact Opinion Decision and Order Approved 05/08/08  
 
PETITION NO. 837  United Recycling and Energy, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed 5-12 MW Biomass Renewable Energy Plant located at 90 Oliver Terrace, Shelton, Connecticut. Status Letter No Decision  
 
PETITION NO. 838  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modification to an existing 345/115-kV Substation located on Walnut Hill Road, Bethel, Connecticut. Staff Report Approved 04/10/08 
 
PETITION NO. 839  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need for a modification to an existing 345/115-kV Switching Station located on Long Mountain Road, New Milford, Connecticut.   Staff Report Staff Report for Revised Plan Approved 02/28/08  Revision Approved 08/28/08  
 
PETITION NO. 840 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the Stepstone Substation, Guilford, Connecticut.  Staff Report Approved 01/10/08  
 
PETITION NO. 841 – The Bridgeport Energy II, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, operation and maintenance of a 350 MW Peaking Facility at the existing Bridgeport Energy Facility located at 10 Atlantic Street, Bridgeport, Connecticut.   Record  Findings of Fact Opinion Decision and Order Approved 06/05/08  
 
PETITION NO. 842The Sprint Nextel Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the attachment of Sprint’s Antennas to an existing CL&P Tower located at 40 Barton Lane, Ledyard, Connecticut. Withdrawal Letter Withdrawn  
 
PETITION NO. 843  The NRG Energy, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of four 50 MW Peaking Units at its Devon Facility located at 700 Naugatuck Avenue, Milford, Connecticut.     Staff Report Approved 01/24/08  Amended 06/04/09  
 
PETITION NO. 844  The Omnipoint Communications, Inc. a/k/a T-Mobile petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a ten (10) foot extension of an existing monopole located at 188 Moody Road, Enfield, Connecticut. Staff Report Approved 01/24/08 
 
PETITION NO. 845  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed 115-kV Transmission Line Removal Project in the Towns of East Haddam, Lyme, East Lyme and Montville, Connecticut. Staff Report Approved 01/24/08  
 
PETITION NO. 846 – The Pfizer Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed addition to the combined heat and electric generating facility located at 445 Eastern Point Road, Groton, Connecticut. Staff Report Approved 02/28/08  
 
PETITION NO. 847  Pepperidge Farm, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 1.2 megawatt fuel cell located at 1414 Blue Hills Avenue, Bloomfield, Connecticut.  Staff Report Approved 02/14/08  
 
PETITION NO. 848  Frito-Lay, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a 5MW electric generating facility located at 1886 Upper Maple Street, Dayville, Connecticut.  Staff Report Approved 03/13/08  
 
PETITION NO. 849 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications tower located at 651 Paddock Avenue, Meriden, Connecticut.  Withdrawn 02/19/08  
 
PETITION NO. 850 – Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the expansion of an existing site compound located at 35 Wildwood Street, New Britain, Connecticut. Staff Report Approved 03/13/08  
 
PETITION NO. 851 – Dominion Nuclear Connecticut, Inc.      Dominion Energy Nuclear Connecticut, Inc.  petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement and relocation of two existing auxiliary boiler fuel tanks and sandblasting facility building located at the Millstone Power Station, Waterford, Connecticut.  Staff Report Approved 04/24/08 Name Change 07/31/17
 
PETITION NO. 852  MediaFLO USA petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 49B Cow Hill Road, Clinton, Connecticut. Verbally Withdrawn  
 
PETITION NO. 853  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed lighting modification to the Housatonic River transmission towers in Town of Stratford and City of Milford, Connecticut.   Staff Report Approved 04/10/08  
 
PETITION NO. 854 – PPL Savage Alert, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of an ORMAT Energy Converter (OEC) at the Naugatuck Wastewater Treatment Facility located at 500 Cherry Street, Naugatuck, Connecticut.   Staff Report Approved 04/24/08  
 
PETITION NO. 855 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing substation in the Town of Litchfield and City of Torrington, Connecticut.  Staff Report Approved 05/08/08  
 
PETITION NO. 856  Dominion Energy Nuclear Connecticut, Inc.  Dominion Nuclear Connecticut, Inc.     petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of the Unit 3 Generator Step-Up Transformer located at Millstone Power Station, Waterford, Connecticut.   Staff Report Approved 05/08/08 Name Change 07/31/17
 
PETITION NO. 857 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing Norwalk Harbor Substation in the City of Norwalk, Connecticut. Staff Report Approved 06/26/08  
 
PETITION NO. 858 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing North Bloomfield 2A Substation located at 2 Hoskins Road in the Town of Bloomfield, Connecticut. Staff Report Approved 07/10/08  
 
PETITION NO. 859  Dominion Energy Nuclear Connecticut, Inc.  Dominion Nuclear Connecticut, Inc.   petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of five enclosures to house new variable frequency drive systems to be connected to the circulating water system pump motors located at Millstone Power Station, Waterford, Connecticut.  Staff Report Approved 07/24/08 Name Change 07/31/17
 
PETITION NO. 860 – The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing Mystic Substation located east of Dennison Avenue (Route 27) and north of Pleasant Street, Stonington, Connecticut.    Staff Report Approved 08/28/08  
 
PETITION NO. 861 – Bridgeport Energy II, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, operation and maintenance of the transmission line tap for the approved 350 MW peaking facility located at 10 Atlantic Street, Bridgeport, Connecticut.    Staff Report Approved 09/11/08   
 
PETITION NO. 862  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a temporary telecommunications facility at 500 Queen Street, Southington, Connecticut.  Staff Report Approved 08/28/08  Extended 06/04/09  
 
PETITION NO. 863  Examination of whether statutory changes should be made to clarify jurisdiction to renewable and/or alternative sources of energy (wind, solar, hydro, tidal, wave, geothermal, biofuel, biomass, etc).  Staff Report Approved 05/07/10  
 
PETITION NO. 864  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing single-circuit 115kVtransmission line between Cook Hill Junction in Cheshire, Connecticut and Lucchini Junction in Meriden, Connecticut.     Staff Report Approved 10/16/08  
 
PETITION NO. 865  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed relocation of an existing 115kV transmission line structure (#1966) east of Nonnewaug Road, Woodbury, Connecticut. Staff Report Approved 10/16/08   
 
PETITION NO. 866  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the existing Flax Hill Substation located at 401 Flax Hill Road, Norwalk, Connecticut.  Staff Report Approved 10/16/08  
 
PETITION NO. 867  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the existing CL&P Waterside Substation located at 39 Amelia Place, Stamford, Connecticut. Staff Report Approved 11/20/08   
 
PETITION NO. 868  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing 115Kv transmission line structure (#9950) located off of Crow’s Nest Lane, Danbury, Connecticut.     Staff Report Approved 11/20/08  
 
PETITION NO. 869  Algonquin Gas Transmission, LLC petition for declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed interconnection of Algonquin’s existing W-System with the Kleen Energy Generating facility off River Road in Middletown, Connecticut.    Staff Report Approved 12/04/08  
 
PETITION NO. 870 – The Hartford Steam Company petition for declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed location, installation and operation of a 3.5 megawatt co-generation facility located at 60 Columbus Boulevard, Hartford, Connecticut. Staff Report Approved 11/20/08  
 
PETITION NO. 871  Algonquin Gas Transmission Company Federal Energy Regulatory Commission (FERC) application (Docket No. 08-426) for the construction and operation of the HubLine/East to West Project located in Massachusetts, Connecticut, Rhode Island and New Jersey. Connecticut segment includes replacement of 11 miles of existing pipeline, appurtenant infrastructure, and installation of access roads in the Towns of Norwich, Preston, Ledyard, and North Stonington as well as upgrades to an existing compressor station in Cromwell.    Final EIS Staff Report Approved 12/18/08   
 
PETITION NO. 872  Omnipoint Communications, Inc. a.k.a. T-Mobile petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need for the proposed antennas to be installed on an existing Connecticut Light and Power Company-owned transmission line structure located at 48 Quail Trail, Trumbull, Connecticut.    Staff Report Approved 12/04/08  
 
PETITION NO. 873  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed transmission Separation Project of a 1.8 mile segment of an existing 345-kV double-circuit (#s 310/368) from south of Manchester substation to Manchester Junction and relocation/replacement of the adjacent 115-kV circuit (#1767) of this route located in Manchester, Connecticut.    Staff Report Approved 12/04/08  
 
PETITION NO. 874  The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing fence line at UI’s Old Town Substation located at 280 Kaechele Place, Bridgeport, Connecticut.    Staff Report Approved 12/04/08   
 
PETITION NO. 875  GenConn Energy LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation and operation of four 50 MW peaking units at the Middletown Station located at 1866 River Road, Middletown, Connecticut.     Staff Report Approved 12/04/08  
 
PETITION NO. 876  The United Illuminating Company petition for a declaratory ruling that noCertificate of Environmental Compatibility and Public Need is required for the proposed Advanced Metering Infrastructure Project located at the proposed substations; Allings Crossing Substation, Frontage Road, West Haven; Ash Creek Substation, Poland Street, Bridgeport; Baird Substation, Stratford Avenue, Stratford, Barnum Substation Barnum Avenue, Stratford; Broadway Substation, Goffe Street, New Haven; Congress Substation, Congress Street, Bridgeport; Devon Tie Substation, Naugatuck Avenue, Milford; East Shore Substation, Waterfront Street, New Haven; Elmwest Substation, Elm Street, West Haven; June St. Substation, Hazell Terrace, Woodbridge; Mill River Substation, Grand Avenue, New Haven; Old Town Substation, Kachele Place, Bridgeport; Pequonnock Substation, Henry Street, Bridgeport; Sackett Substation, State Street, North Haven; and Water Street Substation, Water Street, New Haven.    Staff Report Approved 12/18/08  
 
PETITION NO. 877  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Amendment to the Certificate of Environmental Compatibility and Public Need is required for the extension of an existing tower located at 125 Mile Creek Road, Old Lyme, Connecticut.    Staff Report Approved 01/08/09   
 
PETITION NO. 878  Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 85 Plainfield Avenue, West Haven, Connecticut.  Staff Report  Approved 02/19/09  
 
PETITION NO. 879  Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 117 Washington Street, North Haven, Connecticut.  Staff Report Approved 03/12/09   
 
PETITION NO. 880  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a permanent replacement flagpole tower and associated equipment located at 500 Queen Street, Southington, Connecticut.    Staff Report Approved 01/22/09  
 
PETITION NO. 881  The United Illuminating Company (UI)  petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of the existing switching station infrastructure and control building located at UI’s existing Grand Avenue Switching Station, New Haven, Connecticut.  Staff Report Approved 02/19/09 
 
PETITION NO. 882  The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two low-noise transformers along with associated equipment located at UI’s Broadway 115/13.8 kV Substation, New Haven, Connecticut.  Staff Report Approved 02/19/09  
 
PETITION NO. 883  Omnipoint Communications, Inc. a.k.a. T-Mobile petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for modifications to an existing telecommunications facility located at 70 Platt Road, Shelton, Connecticut. Staff Report Approved 01/22/09  
 
PETITION NO. 884  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed removal of an out-of-service transmission line segment between Portland Substation and Ames Junction in the Town of Portland, Connecticut.     Staff Report Approved 02/19/09  
 
PETITION NO. 885  Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 115 Industrial Park Road, New Hartford, Connecticut.    Staff Report Approved 03/12/09  
 
PETITION NO. 886  American Tower Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to replace and expand an existing telecommunications facility located at 15 Miner Lane, Waterford, Connecticut. Staff Report Approved 04/07/09  
 
PETITION NO. 887  Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 150 North Main Street, Branford, Connecticut.     Staff Report Approved 03/12/09  
 
PETITION NO. 888  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing single-circuit 115-kV transmission line (circuit #1860) between Larson Junction United Technologies Substation in the Town of Southington, Connecticut.    Staff Report Approved 03/12/09  
 
PETITION NO. 889  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 219 New Park Avenue, Hartford, Connecticut. Staff Report Approved 03/12/09  
 
PETITION NO. 890  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed removal of a single-circuit 345-kV transmission line segment between Chestnut Junction in Middletown, Connecticut and Oxbow Junction in Haddam, Connecticut.  Staff Report Approved 04/07/09  
 
PETITION NO. 891  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing Willimantic Substation in the Town of Windham located at 1270 Main Street, Willimantic, Connecticut. Staff Report Approved 04/07/09  
 
PETITION NO. 892 The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of a 2.5 megawatt electric generator and associated equipment located at 31 School Street, Jewett City (Griswold), Connecticut.    Staff Report Approved 04/23/09  
 
PETITION NO. 893  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of two 2.5 megawatt electric generators and associated equipment on each property located at 57 Salem Turnpike, 145 Old Salem Road and 10 Wisconsin Avenue in the Town of Norwich, Connecticut. Staff Report and Decision Letter  CMEEC Partial Withdrawal Request and CSC Acknowledgement of Request Approved 04/23/09  
 
PETITION NO. 894  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing six CL&P Substations located at Tomac Avenue, Greenwich; 7 Prange Road, Brookfield; 52 Peaceable Street, Redding; 85 ½ Weston Road, Weston; 164 North Eagleville Road, Mansfield; and Roosevelt Avenue, Preston, Connecticut. Staff Report Approved 05/07/09  
 
PETITION NO. 895  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing wireless telecommunications tower located at 29 Bogus Hill Road, New Fairfield, Connecticut.    Staff Report Approved 06/04/09  
 
PETITION NO. 896  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of four 2.5 megawatt emergency generators at two locations, adjacent to existing electrical substations and infrastructures located at 1268 Poquonnock Road, and 170 Gary Court in the Town of Groton, Connecticut. Staff Report Approved 07/16/09  
 
PETITION NO. 897  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed removal of an existing single-circuit 115-kV transmission line segment between Carpenter Lane Junction and Colony Substation in Wallingford, Connecticut.    Staff Report Approved 06/04/09  
 
PETITION NO. 898  Cellco Partnership d/b/a Verizon Wireless petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is Required for the temporary placement of a cell on wheels at 1100 Boston Avenue, Bridgeport, Connecticut.  Staff Report Approved 05/12/09  
 
PETITION NO. 899  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed extension of an existing telecommunications tower at 370 Rockland Road, Guilford, Connecticut. Staff Report Approved 06/04/09  
 
PETITION NO. 900  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to the existing CL&P Norwalk Substation located at New Canaan Avenue, Norwalk, Connecticut.   Staff Report Approved 06/04/09  
 
PETITION NO. 901  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of two 2.5 MW electric generators and associated equipment located at 37 Camp Moween Road, Lebanon, Connecticut.    Staff Report Approved 07/16/09  
 
PETITION NO. 902  Pratt & Whitney petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the existing cogeneration power facility at the Pratt & Whitney manufacturing facility located at 400 Main Street, East Hartford, Connecticut.    Staff Report Approved 06/29/09  
 
PETITION NO. 903  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing CL&P switching station located at Haley Road, Montville, Connecticut.    Staff Report Approved 08/13/09  
 
PETITION NO. 904  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing CL&P substation located at 109 Olcott Street, Manchester, Connecticut.    Staff Report Approved 07/16/09 Amendment Approved 03/26/10  
 
PETITION NO. 905  New Cingular Wireless PCS, LLC petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is Required for the temporary placement of a cell on wheels (COW) at 1114 East Putnam Avenue, Greenwich, Connecticut. Staff Report Approved 07/16/09 
 
PETITION NO. 906  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing 0.8 mile single-circuit 345-kV transmission line (circuit #353) segment between the CL&P Middletown Junction and Kleen Energy in Middletown, Connecticut.     Staff Report Approved 07/16/09  
 
PETITION NO. 907  Montville Power LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the retrofit and operation of a 40 MW Biomass-Fueled Generation Unit at the Montville Station in Montville, Connecticut.  Record Findings of Fact Final Decision Approved 02/25/10  
 
PETITION NO. 908  Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.    Staff Report Approved 07/22/09  
 
PETITION NO. 909  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 138 Main Street, Coventry, Connecticut. Staff Report Approved 07/22/09  
 
PETITION NO. 910  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 349 Mountain Street, Willimantic, Connecticut. Staff Report Approved 08/27/09  
 
PETITION NO. 911  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 60 Rice Lane, Beacon Falls, Connecticut.  Decision Staff Report Approved 08/27/09  
 
PETITION NO. 912  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located on Taugwonk Road, Stonington, Connecticut. Staff Report Approved 08/27/09  
 
PETITION NO. 913  MetroPCS petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 99 Briar Hill Road, Groton, Connecticut. Staff Report Approved 08/27/09  
 
PETITION NO. 914  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Plumtree switching station, located at Walnut Hill Road, Bethel, Connecticut. Staff Report Approved 08/27/09  
 
PETITION NO. 915  Omnipoint Communications, Inc., a subsidiary of T-Mobile USA, petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at Rocky Hill Road, Trumbull, Connecticut.    Staff Report Approved 09/17/09  
 
PETITION NO. 916 New Cingular Wireless PCS, LLC petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is Required for the Ten Foot extension of an existing telecommunications facility located at 150 Lost Acres Road, North Granby, Connecticut. Staff Report Approved 10/08/09  
 
PETITION NO. 917 MetroPCS New York, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 48 Newtown Road, Danbury, Connecticut. Staff Report Approved 10/22/09  
 
PETITION NO. 918  The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications at three locations located at Bob White Lane, Trumbull; 36 Center Road, Easton; and corner of Route 80 and Twin Lakes Road, Branford, Connecticut.   Staff Report Approved 11/19/09  
 
PETITION NO. 919  MetroPCS Massachusetts, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to co-locate on a Council-approved Connecticut Light and Power Company transmission structure associated with the Waterford substation located on Oil Mill Road, Waterford, Connecticut.    Staff Report Approved 11/05/09  
 
PETITION NO. 920  The Clearwire Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed extension of an existing tower at 289H Mountain Street in Hartford, Connecticut.    Staff Report Approved 11/19/09  
 
PETITION NO. 921  DFC-ERG CT, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Fuel Cell generating facility located at 535 Simsbury Road, Bloomfield, Connecticut.   Staff Report Status Update - Not Constructed Approved 12/03/09  
 
PETITION NO. 922 UIL Distributed Resources, LLC declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Fuel Cell generating facility located at 1835 Hebron Avenue, Glastonbury, Connecticut. Record Staff Report and Decision Approved 12/03/09  
 
PETITION NO. 923 Fuel Cell Energy, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of a Fuel Cell test facility located at 539 Technology Park Drive, Torrington, Connecticut.   Staff Report Approved 12/03/09  
 
PETITION NO. 923A – Fuel Cell Energy, Inc. amended petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed installation and operation of a Fuel Cell test facility and associated equipment located at 539 Technology Park Drive, Torrington, Connecticut, and associated electrical interconnection. Approved 02/06/25  
 
PETITION NO. 924  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two (2) 2.5 MW electric generators and associated equipment located at 70 Bridge Street, Groton, Connecticut.    Staff Report Approved 12/18/09  
 
PETITION NO. 925  GB II Connecticut LLC  PSEG Power Connecticut LLC petition for declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of three 48.5 MW peaking units at New Haven Harbor Station, 1 Waterfront Street, New Haven, Connecticut. Staff Report Ownership Transfer, 09/23/21 Council Acknowledgment of Transfer Letter Regarding PSEG Power Name Change Approved 01/07/10 
 
PETITION NO. 926 The United Illuminating Company (UI)  petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to UI’s existing East Shore Substation and West River Switching Station, New Haven, Connecticut.  Staff Report Approved 02/11/10  
 
PETITION NO. 927 The Clearwire Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 940 Meriden Road, Waterbury, Connecticut.  Staff Report Approved 01/07/10 
 
PETITION NO. 928  The Metropolitan District for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction and operation of a Heat Recovery Facility with 1.7 (MW) rated power production via steam generator at the existing Hartford Water Pollution Control Facility (HWPCF) located at 240 Brainard Road, Hartford, Connecticut.    Staff Report Approved 01/07/10  
 
PETITION NO. 929  The MetroPCS New York, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the Attachment of Antennas to an Existing Tower at 30 Oliver Terrace in Shelton, Connecticut.    Staff Report Approved 02/11/10  
 
PETITION NO. 930 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a wireless repeater telecommunications facility at Pride’s Corner Farm Nursery, 122 Waterman Road, Lebanon, Connecticut.  Decision and Staff Report Staff Report Approved 02/11/10  
 
PETITION NO. 931  The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 181 Clapboard Ridge Road, Danbury, Connecticut.   Staff Report Approved 02/25/10  
 
PETITION NO. 932  Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications of an existing smokestack facility located at 1-3 Oakland Avenue, East Hartford, Connecticut.   Staff Report Approved 03/26/10  
 
PETITION NO. 933– The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the attachment of antennas, dishes and remote radio heads to an existing rooftop telecommunications facility at Danbury Hospital located at 24 Hospital Lane, Danbury, Connecticut. Withdrawal Letter Withdrawn 04/09/10  
 
PETITION NO. 934  Yankee Gas Services Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 60-foot wooden pole and associated radio communications equipment located at Howe Avenue, Shelton, Connecticut.    Staff Report Semi-Annual Status of Construction Report, 12/23/16 Semi-annual Status of Construction Report, 7/03/17 Semi-annual Status of Construction Report,12/21/17 Approved 04/08/10  
 
PETITION NO. 935 The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed switchyard control house expansion to UI’s existing Devon Tie Switch Yard located at 732 Naugatuck Avenue, Milford, Connecticut.   Staff Report Approved 04/08/10  
 
PETITION NO. 936  The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed transmission structure relocation work in connection with the Department of Transportation Moses Wheeler Bridge that carries I-95 over the Housatonic River between Milford and Stratford, Connecticut.   Staff Report Approved 04/08/10  
 
PETITION NO. 937  The Connecticut Municipal Electric Energy Cooperative (CMEEC) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two 2.5 MW electric generators and associated equipment at two existing substation locations, 15 Old Colony Road and 130 Thorpe Avenue, Wallingford, Connecticut.  Withdrawn  
 
PETITION NO. 938  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P substation, located at 52 Columbus Avenue, Middletown, Connecticut.   Staff Report Approved 05/06/10  
 
PETITION NO. 939 The MetroPCS New York, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the Attachment of Metro’s Antennas to an existing CL&P transmission structure (#848) located at 2225 Reservoir Avenue, Trumbull, Connecticut.   Staff Report Approved 05/06/10  
 
PETITION NO. 940  The United Illuminating Company (UI) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed transmission structure relocation work in connection with the Department of Transportation West Haven Railroad Station project located in West Haven, Connecticut. Staff Report Approved  05/18/10    
 
PETITION NO. 941 – The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 148 Roberts Street, East Hartford, Connecticut.   Staff Report Approved 05/06/10  
 
PETITION NO. 942  The Clear Wireless LLC  petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 82 Lovely Street, Farmington, Connecticut. Record Withdrawal Letter Withdrawn 07/22/10  
 
PETITION NO. 943 UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Customer-Side 400 kW Fuel Cell to be located at 931 Torringford Street, Torrington, Connecticut.   Staff Report Approved 05/06/10  
 
PETITION NO. 944  The Sprint Nextel Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the placement of a temporary mobile radio communications facility (COW) located at 1000 Middle Street, Middletown, Connecticut.    Staff Report Approved 05/27/10  
 
PETITION NO. 945  The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed Ansonia Substation Bus addition project located at 3 Riverside Drive, Ansonia, Connecticut.       Staff Report Approved 05/18/10  
 
PETITION NO. 946 T-Mobile Northeast LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 181 Clifton Street, New Haven, Connecticut. Withdrawal Letter Withdrawn  
 
PETITION NO. 947  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the planned addition of an Odorant System to the Iroquois pipeline located at 840 Oronoque Road, Milford, Connecticut. Staff Report Approved 06/17/10  
 
PETITION NO. 947A  Iroquois Gas Transmission System, L.P. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an Odorant System to the Iroquois pipeline located at 840 Oronoque Road, Milford, Connecticut.      Staff Report Approved 04/28/11  
 
PETITION NO. 948  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 360 State Street, New Haven, Connecticut.    Staff Report Approved 06/17/10  
 
PETITION NO. 949  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 835 Washington Street, Middletown, Connecticut.        Staff Report Approved 07/15/10  
 
PETITION NO. 950  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Cos Cob substation, located at Sound Shore Drive, Greenwich, Connecticut.   Staff Report Approved 06/17/10  
 
PETITION NO. 951  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Southington substation, located at 315 Belleview Avenue, Southington, Connecticut.   Staff Report Approved 06/17/10  
 
PETITION NO. 952 The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 25.5 foot wall mounted steel pipe-mast and associated equipment radio communications equipment located at 112 Prospect Hill Road, East Windsor, Connecticut.   Staff Report Approved 07/15/10 
 
PETITION NO. 953  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two 400 kW Fuel Cell to be located at 1 Aircraft Road, Middletown, Connecticut.    Staff Report Approved 07/15/10  
 
PETITION NO. 954  The Connecticut Resources Recovery Authority (CRRA) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to the existing CRRA South Meadow Generating Station located at Reserve Road, Hartford, Connecticut.    Staff Report Approved 07/29/10  
 
PETITION NO. 955  The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.  Staff Report Approved 08/17/10  
 
PETITION NO. 956  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 151 Young Street, East Hampton, Connecticut.    Staff Report Approved 08/17/10  
 
PETITION NO. 957 Bridgeport Fuel Cell Park, LLC Dominion Bridgeport Fuel Cell, LLC declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a fuel cell generating facility located at Hancock Street, Bridgeport, Connecticut. Staff Report Approved 09/23/10    
 
PETITION NO. 958  The United Illuminating Company The petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of a pressurization plant to UI’s West River Switching Station located at 255 Ella T. Grasso Boulevard (State Route 10) Overpass, New Haven, Connecticut.     Staff Report Approved 08/26/10  
 
PETITION NO. 959 The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing CL&P substation in the Forestville section located at 158 Cronin Street, Bristol, Connecticut.     Staff Report Approved 08/26/10  
 
PETITION NO. 960 The Clearwire Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing facility located at 777 Talcottville Road, Vernon, Connecticut.    Staff Report Approved 09/07/10  
 
PETITION NO. 961 UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 170 Dewitt Street, New Haven, Connecticut.    Staff Report Approved 09/07/10  
 
PETITION NO. 962  The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a ten-foot extension to an existing facility at 41 Padanaram Road, Danbury, Connecticut.     Staff Report Approved 09/23/10  
 
PETITION NO. 963  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Waterside Substation located at 39 Amelia Place, Stamford, Connecticut. Staff Report Approved 09/23/10  
 
PETITION NO. 964 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 1593 Exeter Road, Lebanon, Connecticut.  Staff Report Approved 10/07/10  
 
PETITION NO. 965  Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 95 High Street, Portland, Connecticut.   Staff Report Approved 11/05/10  
 
PETITION NO. 966  The Connecticut Light and Power Company (CL&P) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing CL&P Williams Substation located at 469 Williams Street, New London, Connecticut.    Staff Report Approved 11/05/10  
 
PETITION NO. 967 Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the attachments of antennas to a smokestack of an existing facility located at 2825 Fairfield Avenue, Bridgeport, Connecticut. Staff Report Approved 11/05/10  
 
PETITION NO. 968 Algonquin Gas Transmission, LLC petition for declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed addition to the Algonquin interstate natural gas transmission, comprised of a 12-inch diameter lateral located at 1866 River Road, Middletown, Connecticut. Staff Report Approved 11/05/10  
 
PETITION NO. 969  Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a telecommunications facility located at 33 Neptune Avenue, East Haddam, Connecticut. Staff Report Approved 11/05/10  
 
PETITION NO. 970  Yankee Gas Services Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a 60-foot wooden pole and associated radio communications equipment located at 10 Murphys Lane, Shelton, Connecticut.    Staff Report Semi-Annual Status of Construction Report, 12/23/16 Semi-Annual Status of Construction Report, 07/03/2017 Semi-annual Status of Construction Report, 12/21/17  Approved 11/18/10  
 
PETITION NO. 971  T-Mobile USA, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the attachment of antennas to an existing CL&P transmission structure located at Oil Mill Road, Waterford, Connecticut.    Staff Report Approved 06/09/11  
 
PETITION NO. 972  MetroPCS Massachusetts, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the expansion of a unipole structure located at the Goshen Fire Department, 1 Palmer Road, Waterford, Connecticut.  Staff Report Approved 11/18/10 Staff Report for Amended Decision Decision Amended 04/14/11  
 
PETITION NO. 973  American Towers, LLC declaratory ruling that no Certificate of Environmental Compatibility and Public Needs required to replace and expand an existing structure located at 880 Andrew Mountain Road, Naugatuck, Connecticut.  Record Findings of Fact Opinion Decision and Order Approved 04/28/11  
 
PETITION NO. 974  T-Mobile Northeast LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification of an existing Connecticut Light and Power transmission line tower located at the Oak Hills Golf Course off of Charles Marshall Drive, Norwalk, Connecticut.   Staff Report Approved 12/02/10  
 
PETITION NO. 975 Dominion Energy Nuclear Connecticut, Inc. Dominion Nuclear Connecticut, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of the Unit 2 Reserve Station Service Transformer and associated disconnect switch and the Unit 2 Normal Station Service Transformer located at Millstone Power Station, Waterford, Connecticut. Staff Report Approved 12/02/10 Name Change 07/31/17
 
PETITION NO. 976  GB II Connecticut LLC   PSEG New Haven LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications relating to the installation and operation of three 48.5 MW peaking units at New Haven Harbor Station, New Haven, Connecticut. Staff Report Ownership Transfer, 09/23/21 Council Acknowledgment of Transfer Letter Regarding PSEG Power Name Change Approved 12/16/10 
 
PETITION NO. 977 The Connecticut Light and Power Company notice of intent to modify an existing telecommunications facility located at 26 Chapin Road, New Milford, Connecticut.   Staff Report Approved 11/05/10  
 
PETITION NO. 978  PPL Savage Alert, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 1.9 MW Cogeneration Plant at the ASML Lithography Facility located at 77 Danbury Road, Wilton, Connecticut. Staff Report Ruling Issued on 12/16/10  
 
PETITION NO. 979  Bridgeport Energy, LLC  etition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the approval modification in Petition No. 377 for the existing Bridgeport Harbor Station 520 MW combined cycle gas turbine generating facility, in Bridgeport, Connecticut.    See Petition No. 377A
 
PETITION NO. 980 BNE Energy, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 3.2 MW Wind Renewable Generating facility located at 178 New Haven Road, Prospect, Connecticut.  Record Findings of Fact Opinion Conclusions of Law Dissent to Conclusions of Law Decision and Order Denied 05/12/11  
 
PETITION NO. 981 New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power electric transmission line support structure facility located at 945 North Street, Milford, Connecticut.    Staff Report Approved 01/06/11  
 
PETITION NO. 982  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two 400 kW Fuel Cells to be located at 451 Main Street, East Hartford, Connecticut.   Staff Report Status Update Approved 03/03/11  
 
PETITION NO. 983  BNE Energy, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 4.8 MW Wind Renewable Generating facility located on Flagg Hill Road, Colebrook, Connecticut.  Record Findings of Fact Opinion Dissenting Opinion Conclusions of Law Decision and Order Approved 06/02/11  
 
PETITION NO. 984  BNE Energy, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 4.8 MW Wind Renewable Generating facility located on Winsted-Norfolk Road (Route 44), Colebrook, Connecticut.   Record, Findings of Fact Opinion Conclusions of Law Decision and Order. Approved 06/09/11  
 
PETITION NO. 985  T-Mobile Northeast LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification to an existing telecommunications facility located at 366 Old Long Ridge Road, Stamford, Connecticut. Staff Report Approved 02/08/11  
 
PETITION NO. 986  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power substation located at 185 Cherry Hill Road, Newington, Connecticut.    Staff Report Approved 03/03/11  
 
PETITION NO. 987  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a ten foot extension of an existing telecommunications facility located at 6 Mountain Road, Washington, Connecticut. Staff Report Approved 06/09/11  
 
PETITION NO. 988  New Cingular Wireless PCS, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for a ten foot (10’) extension of an existing telecommunications facility located at 50 Fairchild Road, Middletown, Connecticut. Staff Report Petition Denied 03/31/11/ Docket 316 Reopened  
 
PETITION NO. 989  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 350 Grasmere Avenue, Fairfield, Connecticut.    Staff Report Status Update Approved 04/28/11  
 
PETITION NO. 990 Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the extension of an existing telecommunications facility located at 577 Bell Street, Glastonbury, Connecticut.    Staff Report Approved 06/23/11  
 
PETITION NO. 991 The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power substation located at 970 Corbin Avenue, New Britain, Connecticut. Staff Report Approved 07/14/11  
 
PETITION NO. 992  United Illuminating Company -petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the expansion of an existing control house at Ash Creek Substation located at 66 Poland Street, Bridgeport, Connecticut.    Filing Field Review DecisionStaff Report Change to Service List Approved 07/14/11  
 
PETITION NO. 993  Logan Energy Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 300 kW Fuel Cell project to be located at 50 Talbot Lane, South Windsor, Connecticut. Staff Report Approved 07/14/11 Decommissioned in 2017 - See Petition No. 1355  
 
PETITION NO. 994 Algonquin Power Windsor Locks, LLC Petition for a Declaratory Ruling that no Certificate of Environmental Compatibility and Public Need is required for construction, maintenance, and operation of a 15 MW combined heat and power unit at an existing cogeneration facility located at 26 Canal Bank Road, Windsor Locks, Connecticut.    Staff Report Approved 07/14/11  
 
PETITION NO. 995  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell at 195 Governors Highway, South Windsor, Connecticut. Staff Report Status Update Approved 07/14/11  
 
PETITION NO. 996  UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell located on High Street, Hartford, Connecticut. Staff Report Status Update Approved 07/28/11  
 
PETITION NO. 997  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power substation located at 315 Bellview Avenue, Southington, Connecticut.    Staff Report Approved 07/28/11 
 
PETITION NO. 998 The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power substation located at Franklin Drive, Torrington, Connecticut. Staff Report Approved 08/11/11  
 
PETITION NO. 999  The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing Connecticut Light and Power substation located at Manhattan Street, Stamford, Connecticut. Staff Report Approved 08/11/11