NEW HAVEN

DOCKET NO. 17 - National Railroad Passenger Corporation Certificate for a telecommunications tower at the New Haven Railroad yard. (Findings of Fact)(Opinion),  and  (Decision and Order).

DOCKET NO. 23 - Department of Transportation Certificate for proposed revisions to telecommunication towers at Connecticut Transit Properties on Vernon Street in Hartford and on James Street in New Haven. (Findings of Fact)(Opinion), and (Decision and Order).

DOCKET NO. 115 - United Illuminating Certificate for the construction of two 115,000/13,800 volt substations and Connecticut underground transmission lines in New Haven. (Findings of Fact)(Opinion), and  (Decision and Order).

DOCKET NO. 135 - United Illuminating application for a Certificate for construction of one or two electric combustion turbines, one diesel engine-generator, and one associated 115-kV switchyard at English Station in New Haven. (Findings of Fact)(Opinion)(Dissenting Opinion),  and  (Decision and Order).

DOCKET NO. 140 - Metro Mobile CTS of New Haven, Inc. Certificate for cellular telephone antennas and associated equipment on a rooftop at 54 Meadow Street in New Haven. (Findings of Fact),   (Opinion),  and  (Decision and Order).

DOCKET NO. 163 - Connecticut Department of Transportation, Bureau of Public Transportation Certificate for a telecommunications facility at 470 James Street in New Haven. (Findings of Fact)(Opinion),  and  (Decision and Order).

DOCKET NO. 197 - TransEnergie U.S. Ltd. application for a Certificate of Environmental Compatibility and Public Need for the construction, operation, and maintenance of a high voltage direct current (HVDC) submarine electric transmission and fiber optic cable system from One Waterfront Street, New Haven, Connecticut to Brookhaven, New York.  (Findings of Fact),  (Opinion),  and  (Decision and Order)

DOCKET NO. 208 - Cross-Sound Cable Company, LLC application for a Certificate of Environmental Compatibility and Public Need for the construction, operation, and maintenance of a high-voltage direct current (HVDC) submarine electric transmission and fiber optic cable system from One Waterfront Street, New Haven, Connecticut to Brookhaven, New York. (Findings of Fact),  (Opinion),  and  (Decision and Order).

DOCKET NO. 298 - Sprint Spectrum, L.P. d/b/a Sprint PCS application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance and operation of a wireless telecommunications facility at 389 Forbes Avenue, New Haven, Connecticut.  (Findings of Fact) (Opinion),  and   (Decision and Order).

DOCKET NO. 301 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to establish a flagpole telecommunications facility at 100 Pond Lily Avenue, New Haven, Connecticut. (Findings of Fact),  (Opinion),  and  (Decision and Order).

DOCKET NO. 508 – The United Illuminating Company (UI) application for a Certificate of Environmental Compatibility and Public Need for the Milvon to West River Railroad Transmission Line 115-kV Rebuild Project that consists of the relocation and rebuild of its existing 115- kilovolt (kV) electric transmission lines from the railroad catenary structures to new steel monopole structures and related modifications to facilitate interconnection of the rebuilt 115-kV electric transmission lines at UI’s existing Milvon, Woodmont, Allings Crossing, Elmwest and West River substations along approximately 9.5 miles of the Connecticut Department of Transportation’s Metro-North Railroad corridor traversing the municipalities of Milford, Orange, West Haven and New Haven, Connecticut.  (Findings of Fact)  (Opinion)  and (Decision and Order)

PETITION NO. 47 - National Passenger Corporation (Amtrak) petition for four 100-foot high steel monopole telecommunications towers within Amtrak’s right-of-way located off Hallock Avenue, New Haven; off Whitfield Street, Guilford, east of the Boston Post Road overpass, Old Saybrook; and near Hamilton Street and Smith Street, New London.  Denied 11/30/79

PETITION NO. 64 - Connecticut Department of Transportation petition for the construction of a telecommunications tower, microwave antenna, and associated equipment to replace an existing tower on a rooftop at 470 James Street in New Haven. Staff Report.  Denied 2/25/81

PETITION NO. 69 - Connecticut Department of Transportation petition for the installation of a microwave parabolic antenna on an existing telecommunications tower located on West Rock Mountain in New Haven and two microwave antennas on an existing telecommunications tower located on Buckley Hill Road in Colchester. Staff Report.  Approved 7/2/81

PETITION NO. 94 - United Illuminating petition for reconstructing a section of the Grand Avenue Substation - Sackett Point Substation 115-kV transmission line in New Haven and North Haven. Staff Report.  Approved 6/20/83

PETITION NO. 104 - United Illuminating  petition for the residing of its New Haven Harbor generating Station in New Haven. Staff Report.  Approved 4/11/84

PETITION NO. 114 - United Illuminating petition for reconfiguration of West River Substation in New Haven. Staff Report.  Approved 10/9/84

PETITION NO. 115 - United Illuminating petition for reconductoring and reinsulating approximately 11.8 miles of 115-kV line between West River and Baird Substation, excluding the Mildale Substation to Devon Substation section. Staff Report.  Approved 10/9/84

PETITION NO. 161 - United Illuminating petition for a natural gas fired heating boiler system at English Station in New Haven. Staff Report.  Approved 10/6/86

PETITION NO. 202 - United Illuminating petition for proposed lightning protection at East Shore Substation in New Haven. Staff Report.  Approved 3/3/88

PETITION NO. 221HW - Statewide Environmental Services petition for short-term storage of Polychlorinated biphenyl contaminated electrical capacitors at a proposed “White Goods” scrap decontamination center located in New Haven County. Staff Report.  Approved 11/21/88

PETITION NO. 243 - United Illuminating petition for the proposed installation of four transmission shunt capacitor banks at substations in North Haven and New Haven. Staff Report.  Approved 1/16/90

PETITION NO. 329 - Metro Mobile CTS of New Haven, Inc. petition for the proposed installation of cellular antennas and associated equipment on an existing building at 153 Forbes Ave., New Haven. Staff Report.  Approved 8/30/94

PETITION NO. 414 - Comcast Cable Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a receive-only satellite dish antenna on the roof of an existing building located at 630 Chapel Street in New Haven. Staff Report.  Approved 4/27/99

PETITION NO. 424 - Wisvest-Connecticut, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of an electrical switchyard at New Haven Harbor Station, 1 Waterfront Street in New Haven. Staff Report.  Approved 8/16/99

PETITION NO. 437 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of receive-only telecommunications facilities associated with a remote network meter reading system within UI's service area. Staff Report.   Approved nine of eleven sites 11/9/99. Reconsideration of the Woodbridge site. Approved 3/22/00. Reconsidered and Approved Ansonia site 8/10/00.

PETITION NO. 438 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of transmitters and receivers associated with a remote network meter reading system within UI's service area. Staff Report.  Approved 11/9/99.

PETITION NO. 463HW - Active Oil, Inc. petition for a declaratory ruling that no Certificate of Public Safety and Necessity is required for a proposed waste oil transfer facility at 120 Forbes Avenue in New Haven, Connecticut. Staff Report.  Approved 6/20/00.

PETITION NO. 465 - TransEnergie U.S. Ltd. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of an electric substation and interconnection facility located adjacent to the East Shore Substation and the New Haven Harbor Generating Facility, One Waterfront Street, New Haven, Connecticut.  Decision & Order.   Opinion.  (Voted that Petition was moot, 3/28/01)

PETITION NO. 522 - Cross-Sound Cable Company, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need (Certificate) is required for the construction, maintenance, and operation of an electric substation and interconnection facility located adjacent to the East Shore Substation and the New Haven Harbor Generating Facility, One Waterfront Street, New Haven, Connecticut. Findings of Fact.   Opinion.   Decision & Order.  Approved 01/03/02

PETITION NO. 560 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modification and relocation of existing transmission line structures in connection with the Connecticut Department of Transportation's reconstruction of the Quinnipiac River Bridge, New Haven, Connecticut. Staff Report.  Approved 07/11/02.

PETITION NO. 574 - United Illuminating petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed underground transmission line relocation work in connection with the State of Connecticut Department of Transportation's Interstate 95 reconstruction project. Staff Report.  Approved 09/05/02.

PETITION NO. 598 - Yale University petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a fuel cell to be located on Yale's Campus in New Haven, Connecticut.  Staff Report.   Approved 12/19/02.

PETITION NO. 647 - Nxegen, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a fuel cell at the Water Pollution Control Authority at 345 East Shore Parkway, New Haven, Connecticut. Staff Report.   Approved 10/14/03.

PETITION NO. 688 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to establish a stealth flagpole telecommunications facility at the Quality Inn and Conference Center, 100 Pond Lily Avenue, New Haven, Connecticut. Staff ReportDenied 08/26/04.

PETITION NO. 699 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required to interconnect UI’s existing underground 115 kV 8700 transmission line with the Metro North rail yard 26.4 kV supply station located on Union Avenue in New Haven, Connecticut. Staff Report.   Approved 12/21/04.

PETITION NO. 753 - Omnipoint Communications, Inc. (T-Mobile) petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction of a ten foot (10’) extension to an existing wireless communication monopole located at 69 Wheeler Street, New Haven, Connecticut. Staff Report.  Approved 1/25/06.

PETITION NO. 876 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed Advanced Metering Infrastructure Project located at the proposed substations; Allings Crossing Substation, Frontage Road, West Haven; Ash Creek Substation, Poland Street, Bridgeport; Baird Substation, Stratford Avenue, Stratford, Barnum Substation Barnum Avenue, Stratford; Broadway Substation, Goffe Street, New Haven; Congress Substation, Congress Street, Bridgeport; Devon Tie Substation, Naugatuck Avenue, Milford; East Shore Substation, Waterfront Street, New Haven; Elmwest Substation, Elm Street, West Haven; June St. Substation, Hazell Terrace, Woodbridge; Mill River Substation, Grand Avenue, New Haven; Old Town Substation, Kachele Place, Bridgeport; Pequonnock Substation, Henry Street, Bridgeport; Sackett Substation, State Street, North Haven; and Water Street Substation, Water Street, New Haven. Staff Report.  Approved 12/18/08.

PETITION NO. 881 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of the existing switching station infrastructure and control building located at UI’s existing Grand Avenue Switching Station, New Haven, Connecticut. Staff Report.   Approved 02/19/09.

PETITION NO. 882 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of two low-noise transformers along with associated equipment located at UI’s Broadway 115/13.8 kV Substation, New Haven, Connecticut. Staff Report.   Approved 02/19/09.

PETITION NO. 908 - Youghiogheny Communications-Northeast, LLC d/b/a Pocket Communications petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Staff Report.  Approved 7/22/09.

PETITION NO. 925 - PSEG Power Connecticut LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation and operation of three 48.5 MW peaking units at New Haven Harbor Station, 1 Waterfront Street, New Haven, Connecticut. Staff Report.  Approved 01/07/10.

PETITION NO. 926 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to UI’s existing East Shore Substation and West River Switching Station, New Haven, Connecticut. Staff Report.  Approved 02/11/10.

PETITION NO. 946 - T-Mobile Northeast LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 181 Clifton Street, New Haven, Connecticut.  Withdrawal Letter. Withdrawn

PETITION NO. 948 - UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 360 State Street, New Haven, Connecticut. Staff Report.  Approved 06/17/10.

PETITION NO. 955 - The Clear Wireless LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Staff Report.  Approved 08/17/10

PETITION NO. 958 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the replacement of a pressurization plant to UI’s West River Switching Station located at 255 Ella T. Grasso Boulevard (State Route 10) Overpass, New Haven, Connecticut. Staff Report.  Approved 08/26/10.

PETITION NO. 961 - UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at 170 Dewitt Street, New Haven, Connecticut. Staff Report.  Approved 09/07/10

PETITION NO. 976 - PSEG New Haven LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the modifications relating to the installation and operation of three 48.5 MW peaking units at New Haven Harbor Station, New Haven, Connecticut. Staff Report.  Approved 12/16/10

PETITION NO. 1013 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed 8300 Line reconfiguration in New Haven, Connecticut. Staff Report.  Approved 12/01/11.

PETITION NO. 1015 – UTC Power Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a Customer-Side 400 kW Fuel Cell to be located at New Haven City Hall, 200 Orange Street, New Haven, Connecticut. Staff Report.  Status UpdateApproved 12/15/11

PETITION NO. 1018 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the East Shore Substation located at 1 Waterfront Street, New Haven, Connecticut.   Staff Report.  Approved 01/05/12

PETITION NO. 1051 – BE 2012 W LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the installation of a 400 kW Fuel Cell to be located at Walmart, 315 Foxon Boulevard, New Haven, Connecticut.  Staff Report.  Status Update - Constructed  Approved 01/10/13

PETITION NO. 1113 - United Illuminating declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, operation and maintenance of a 2.8 MW AC fuel cell facility to be located at an approximately .25 acre UI Tax Parcel (Map 67, Block 951, Lot 13) adjacent to Connecticut Avenue, Interstate 95 and Alabama Street in New Haven, Connecticut. Filing - Part 1.  Filing - Part 2.  Staff Report.  Approved 09/04/14.

PETITION NO. 1229 - Bloom Energy Corporation, as an agent for Ikea, petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, operation and maintenance of a Customer-Side 250-Kilowatt Fuel Cell Facility to be located at the Ikea store, 450 Sargent Drive, New Haven, Connecticut.  Approved 06/23/16.

PETITION NO. 1272 - Bloom Energy Corporation, as an agent for Frontier Communications Corporation, petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, operation and maintenance of a Customer-Side 1.4-Megawatt Fuel Cell Facility to be located at the Frontier building, 310 Orange Street, New Haven, Connecticut. Approved 1/19/17.

PETITION NO. 1321 - The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing East Shore Substation located at 1 Waterfront Street, New Haven, Connecticut. Approved 10/26/17

PETITION NO. 1403 - Bloom Energy Corporation petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 600-kilowatt customer-side fuel cell facility and associated equipment to be located at Southern Connecticut State University, North Campus, 201 Wintergreen Avenue, New Haven, Connecticut.  Approved 06/04/20

PETITION NO. 1404 - Bloom Energy Corporation petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1350-kilowatt customer-side fuel cell facility and associated equipment to be located at Southern Connecticut State University, East Campus, 501 Crescent Street, New Haven, Connecticut.  Approved 06/04/20

PETITION NO. 1430 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for proposed modifications to an existing rooftop telecommunications facility located at 54 Meadow Street, New Haven, Connecticut. Approved 12/03/20

PETITION NO. 1440 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed installation of a wireless telecommunications facility and associated equipment on an extension of the support structure above the top of an existing billboard located on a commercial property at 115 Peat Meadow Road, New Haven, Connecticut.  Approved 5/6/21

PETITION NO. 1462 – Distributed Solar Operations, LLC and IKEA Property, Inc. notice of election to waive exclusion from Connecticut Siting Council jurisdiction, pursuant to Connecticut General Statutes §16-50k(e), and petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 0.90-megawatt AC solar photovoltaic electric generating facility located at IKEA, 450 Sargent Drive, New Haven, Connecticut and associated electrical interconnection.  Approved 11/18/21

BANM notice of intent to modify an existing telecommunications facility located at 54 Meadow St., New Haven. November 22, 1995 Antenna Upgrade Filing - 54 Meadow Street and 153 Forbes Avenue

Dept. of Public Safety, Div. of State Police, notice of intent to modify an existing telecommunications facility at West Rock Ridge, New Haven.

Springwich Cellular Ltd. Partnership notice of intent to modify existing telecommunications facilities located on Weingart Rd., Harwinton; Moses Mountain, Danbury; Parker Rd. East Haddam; Guinea Rd., Monroe; Orange St., New Haven; Aspetuck Ave, New Milford; Willard Rd, Norwalk; North St., Plymouth; Valcom Rd., Tolland; Oakdale Ave., Winchester.

Springwich Cellular Ltd. Partnership notice of intent to modify existing telecommunications facilities located on Farmdale Dr., Waterbury; 77 Pease Rd., Woodbridge; 438 Bridgeport Ave., Milford; 405 Brushy Plain Rd, Branford; 8 Dwight St., North Haven; and 310 Orange St., New Haven.

Dept. of Transportation notice of intent to modify an existing telecommunications facility located on West Rock Ridge, New Haven.

SNET notice of intent to modify an existing telecommunications facility located on the roof of SNET's New Haven Central Office Building at 310 Orange Street in New Haven.

Dept. of Public Safety, Division of State Police, notice of intent to modify an existing telecommunications facility located at Brookside Avenue in New Haven.

TS-SCLP-093-990426- Springwich Cellular Ltd. Partnership request for an order to approve tower sharing and replace an existing telecommunications facility located at 69 Wheeler Street in New HavenTown Letter  Decision

EM-SCLP-093-990727 - Springwich Cellular Limited Partnership notice of intent to modify an existing telecommunications facility located at West Rock Ridge in the City of New Haven.

EM-SIRIUS-093-000825 - Selective Site Consultants, Inc. on behalf of Sirius Satellite Radio, Inc. notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.

EM-VOICESTREAM-093-010719 - VoiceStream Wireless Corporation notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut.

EM-AT&T-093-020703AT&T Wireless PCS, LLC d/b/a AT&T Wireless notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.

EM-NEXTEL-093-020213 - Nextel Communications Inc. notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Decision

EM-SNET-034-020321 - Southern New England Telephone Company notice of intent to modify an existing telecommunications facility located at Moses Mountain, Danbury, and 310 Orange Street, New Haven, Connecticut.

EM-AT&T-093-020703 - AT&T Wireless PCS, LLC d/b/a AT&T Wireless notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.

EM-CING-014-060-062-093-107-020731 - SNET Mobility, LLC notice of intent to modify existing telecommunications facilities located in Branford, Guilford, Hamden, New Haven, and Orange, Connecticut. (Wheeler St.)  Decision

EM-CING-059-070-082-093-154-020828 - SNET Mobility, LLC notice of intent to modify existing telecommunications facilities located in Groton, Killingworth, Middlefield, New Haven, and Westbrook, Connecticut.

EM-CING-013-041-054-060-076-093-108-020913 - Southwestern Bell Mobile Systems, LLC notice of intent to modify existing telecommunications facilities located in Bozrah, East Haddam, Glastonbury, Guilford, Madison, Baldwin Dr. (West Rock Ridge) New Haven, and Oxford, Connecticut.

EM-CING-013-041-054-060-076-093-108-020913 - Southwestern Bell Mobile Systems, LLC notice of intent to modify existing telecommunications facilities located in Bozrah, East Haddam, Glastonbury, Guilford, Madison, New Haven, and Oxford, Connecticut.

EM-T-MOBILE-"UNIVERSAL"-020830 - Omnipoint Facilities Network 2., L.L.C. and Omnipoint Communications, Inc., subsidiaries of T-Mobile USA, Inc. notice of intent to modify existing telecommunications facilities throughout Connecticut.

EM-AT&T-"UNIVERSAL"-030221 - AT&T Wireless PCS LLC d/b/a AT&T Wireless notice of intent to modify existing telecommunications facilities throughout Connecticut.

EM-VER-057-093-043-159-047-060310 - Cellco Partnership d/b/a Verizon Wireless notice of intent to modify existing telecommunications facilities located at 1111 East Putnam Avenue, Greenwich; 153 Forbes Avenue, New Haven; 886 Main Street, East Hartford; 100 Great Meadow Road, Wethersfield; and 232 South Main Street, East Windsor, Connecticut.

EM-CING-093-084-060613 - New Cingular Wireless PCS, LLC notice of intent to modify existing telecommunications facilities located at 310 Orange Street, New Haven; and 528-530 Wheelers Farm Road, Milford, Connecticut.

TS-T-MOBILE-093-060629 - Omnipoint Communications, Inc. request for an order to approve tower sharing at an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.

EM-CING-093-080917 - New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.

EM-CING-093-081218A - New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Decision  Revised Decision

EM-T-MOBILE-093-081218B - Omnipoint Communications, as subsidiary of T-Mobile USA, Inc., notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Decision

EM-CLEARWIRE-093-100407Clearwire Corporation notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Decision

TS-CLEARWIRE-093-110107 - Clearwire Corporation notice of intent to modify an existing telecommunications facility located at East Rock Park, New Haven, Connecticut. 

EM-CING-093-110802 - New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.
 
EM-VER-093-111007 - Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary cellular telecommunications facility located at Yale Bowl, New Haven, Connecticut.

EM-CING-093-111020 - New Cingular Wireless PCS, LLC notice of intent to install a temporary cellular telecommunications facility located at 2011 Yale Bowl, New Haven, Connecticut. 

EM-CING-093-120507New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Decision

EM-VER-093-120725- Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 100 Pond Lily Avenue, New Haven, Connecticut.

EM-T-MOBILE-093-120802 T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.

 

EM-SPRINT-NEXTEL-093-120927 – Sprint Nextel Corporation notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.

 

EM-CING-093-121031 - New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut.

EM-T-MOBILE-093-130114 – T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.

EM-METROPCS-093-130107MA - MetroPCS Massachusetts, LLC notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut.

EM-UI-093-130611The United Illuminating Company notice of intent to modify an existing energy facility located at 524 and 532 Grand Avenue, New Haven, Connecticut. Decision.  Completion Letter.

EM-SPRINT-062-130912 – Sprint Spectrum, L.P. notice of intent to modify an existing telecommunications facility located at 1065 Wintergreen Avenue, Hamden, Connecticut  (address also listed as 142 Baldwin Drive, New Haven).

EM-VER-093-131004 - Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary cellular telecommunications facility located at Yale Bowl, New Haven, Connecticut.

EM-VER-093-131028 – Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 100 Pond Lily Avenue, New Haven, Connecticut.

EM-VER-093-131211– Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 153 Forbes Avenue, New Haven, Connecticut.

EM-SPRINT-093-140127- Sprint Spectrum L.P. notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Decision. Completion Letter.

EM-T-MOBILE-093-140307 – T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 274 Derby Avenue, New Haven, Connecticut. DecisionCompletion Letter.

EM-T-MOBILE-093-140407T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut. DecisionCompletion Letter.

EM-T-MOBILE-093-140905 – T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  DecisionCompletion Letter.

EM-T-MOBILE-093-141020 – T-Mobile Northeast LLC notice of intent to modify an existing telecommunications facility located at 240 Baldwin Drive, New Haven, Connecticut. DecisionCompletion Letter.

EM-UI-093-141201(e) – The United Illuminating Company notice of intent to replace the outermost perimeter fence and remove the adjacent vegetation at the existing energy facility located at 1 Waterfront Street, New Haven, Connecticut. Decision. Completion Letter.
 
EM-CING-093-150220 - AT&T Mobility notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Incomplete Letter.Decision.  Completion Letter.

EM-SIRIUS-093-150721Sirius XM Satellite Radio notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.  Decision

EM-UI-093-151002e - The United Illuminating Company notice of intent to modify an existing telecommunications facility located at 1100 Quinnipiac Avenue, New Haven, Connecticut. Decision  Completion Letter

EM-UI-093-151006e - The United Illuminating Company notice of intent to modify an existing telecommunications facility located at 524 Grand Avenue, New Haven, Connecticut. DecisionCompletion Letter

EM-T-MOBILE-093-151008 – T-Mobile notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Decision.

EM-VER-093-151027 - Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary cellular telecommunications facility located at Yale Bowl, New Haven, Connecticut. Decision.

EM-CING-093-160324New Cingular Wireless PCS, LLC (AT&T) notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. DecisionCompletion Letter

EM-T-MOBILE-093-160701T-Mobile notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut. Decision.Completion Letter

EM-T-MOBILE-093-160826T-Mobile notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Decision.  Completion Letter.

EM-VER-093-160914 - Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 153 Forbes Avenue, New Haven, Connecticut. DecisionCompletion Letter

EM-CING-093-160926 -New Cingular Wireless PCS, LLC (AT&T) notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive (West Rock Ridge), New Haven, Connecticut. Decision. Condition 1 ComplianceExtension Request and CSC ApprovalCompletion Letter

EM-T-MOBILE-093-161005 - T-Mobile notice of intent to modify an existing telecommunications facility located at 274 Derby Avenue, New Haven, Connecticut. DecisionRequest for Withdrawal and CSC Approval

EM-CING-093-170206 – New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. DecisionCompletion Letter

EM-UI-093-170615e - The United Illuminating Company notice of intent to modify an existing energy facility located at 1100 Quinnipiac Avenue, New Haven, Connecticut. DecisionCompletion Letter

EM-UI-093-170630e – United Illuminating Company notice of intent to modify an existing energy facility located at 56 Goffe St., New Haven, Connecticut. Decision Completion Letter

EM-T-MOBILE-093-170822 –T-Mobile notice of intent to install a temporary telecommunications facility located at Yale Bowl, 150 Yale Avenue and 165 Central Avenue, New Haven, Connecticut. Decision

EM-VER-093-171006 (cow) – Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary telecommunications facility located at Yale Bowl, New Haven, Connecticut. Decision

EM-SPRINT-093-180803 - Sprint notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Incomplete LetterResponse and Acknowledgement to IncompleteDecision Construction Complete

EM-AT&T-093-180912 – AT&T notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut. DecisionCompletion Status Sheet

EM-T-MOBILE-093-190103 - T-Mobile notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut. Decision Council Extension Denial Dept. of Transportation Comments

EM-AT&T-093-190328 – AT&T Mobility, LLC notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Incomplete Letter 2nd Incomplete Letter Response and Acknowledgement to Incomplete Decision Extension Request and Council Approval  Completion Letter

EM-CING-093-190729 - New Cingular Wireless PCS, LLC notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut. Decision  Notice of Completion

EM-AT&T-093-190816 – AT&T Mobility notice of intent to modify an existing telecommunications facility located at Wintergreen Avenue (West Rock Ridge), New Haven, Connecticut. Incomplete Letter  Decision Letter - Denial

EM-T-MOBILE-093-191007(temp) – T-Mobile notice of intent to install a temporary telecommunications facility located at 150 Yale Avenue and 165 Central Avenue, New Haven, Connecticut. Decision

EM-VER-093-191010(temp) – Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary telecommunications facility at 150 Yale Avenue and 165 Central Avenue, New Haven, Connecticut. Decision

EM-UI-093-200402e – The United Illuminating Company (UI) notice of intent to modify an existing energy facility located at 56 Goffe St., New Haven, Connecticut. Decision  Extension Request and Council Decision  Notice of Completion

EM-T-MOBILE-093-200423 - T-Mobile notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut. Decision  Notice of Cancellation

EM-AT&T-093-200622 – AT&T Wireless notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Proof of Delivery  Incomplete Letter Response to Incomplete and Council Acknowledgement Decision Notice of Completion

EM-T-MOBILE-093-200724 – T-Mobile notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Decision  Notice of Completion

EM-T-MOBILE-093-200820 - T-Mobile  notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Decision Completion Letter

EM-T-MOBILE-093-210126 – T-Mobile notice of intent to modify an existing telecommunications facility located at 389 Forbes Avenue, New Haven, Connecticut. Decision  Notice of Construction Start  Notice of Completion

EM-T-MOBILE-093-210623 – T-Mobile notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Decision  Extension Request and Council Extension Decision  Withdrawn

EM-T-MOBILE-093-210805 - T-Mobile notice of intent to modify an existing telecommunications facility located at 150 Yale Avenue (a/k/a 274 Derby Avenue), New Haven, Connecticut. Decision  Notice of Cancellation

EM-T-MOBILE-093-210902 (temp) - T-Mobile notice of intent to install a temporary telecommunications facility located at 81 Central Avenue, New Haven, Connecticut. Decision Notice of Completion

EM-AT&T-093-220414 - AT&T notice of intent to modify an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut. Decision  Extension Request and Council Extension Approval  Notice of Construction Commencement

EM-CING-093-220516 -  New Cingular Wireless PCS, LLC (AT&T) notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.  Decision  Notice of Completion

EM-VER-093-220727 - Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 115 Peat Meadow Road, New Haven, Connecticut.  Decision  Notice of Construction Commencement Revision Request  Council Revision Decision  Extension Request and Council Acknowledgement

EM-VFS-093-221219eVFS, LLC notice of intent to modify an existing telecommunications facility located at 200 Orange Street, New Haven, Connecticut.  Decision  Notice of Completion

EM-VER-093-230330 - Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 54 Meadow Street, New Haven, Connecticut.   Decision Notice of Construction Completion

EM-VER-093-230412(temp) - Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary telecommunications facility located at Yale University, 344 College Street, New Haven, Connecticut. 2023 Yale University Commencement CeremonyDecision

EM-VER-093-230608(temp) - Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary telecommunications facility located at 181 Mitchell Drive (Wilbur Cross High School), New Haven, Connecticut. New Haven Fireworks Display.  Decision

TS-DISH-093-230728 - Dish Wireless, LLC request for an order to approve tower sharing at an existing telecommunications facility located at 69 Wheeler Street, New Haven, Connecticut.  Town Letter  Incomplete Letter  Response to Incomplete and Council Acknowledgement  Decision

EM-T-MOBILE-093-230816 (temp)- T-Mobile notice of intent to install a temporary telecommunications facility located at 81 Central Avenue, New Haven, Connecticut.  Decision

EM-VER-093-230911Cellco Partnership d/b/a Verizon Wireless notice of intent to modify an existing telecommunications facility located at 153 Forbes Avenue, New Haven, Connecticut. Decision Notice of Construction Commencement  Notice of Completion

EM-VER-093-231012 (temp) - Cellco Partnership d/b/a Verizon Wireless notice of intent to install two temporary telecommunications facilities located at 150 Yale Avenue and 40 Central Avenue, New Haven, Connecticut. Yale/Harvard Football GameDecision

EM-ATT-093-231213 New Cingular Wireless PCS, LLC (AT&T) notice of intent to modify an existing telecommunications facility located at 310 Orange Street, New Haven, Connecticut.  Decision

EM-ATT-093-240322 - New Cingular Wireless PCS, LLC (AT&T) notice of intent to modify an existing telecommunications facility located at 142 Baldwin Drive, New Haven, Connecticut.  Incomplete Letter  Response to Incomplete and Council Acknowledgement  Decision

EM-VER-093-240405 (temp)Cellco Partnership d/b/a Verizon Wireless notice of intent to install a temporary telecommunications facility located at Yale University, 344 College Street, New Haven, Connecticut. 2024 Yale University Commencement CeremonyDecision