PETITION NO. 1272 - Bloom Energy Corporation, as an agent for Frontier Communications Corporation, petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, operation and maintenance of a Customer-Side 1.4-Megawatt Fuel Cell Facility to be located at the Frontier building, 310 Orange Street, New Haven, Connecticut.

Petition Filing, received 11/7/2016

PROCEDURAL CORRESPONDENCE

Department of Transportation Comments, 12/1/2016

Council Interrogatories to Petitioner, 12/8/16

Field Review Notice, 12/22/16

Council's Date of Decision Letter, 12/23/16

Petitioner's Responses to Council Interrogatories, 12/27/16

   Revised Interrogatory Exhibit 2, 1/18/17

Council Decision and Staff Report, 1/20/17

Notice of Project Cancellation, 01/09/23