PETITION NO. 1286 - Eversource Energy petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed West Brookfield Reliability Project that includes reconductoring of approximately 1.4 miles of its existing No. 1887 115-kilovolt (kV) electric transmission line within existing Eversource electric transmission line right of way between the existing West Brookfield Substation located at 83 Prange Road and the existing West Brookfield Junction near Pocono Road in Brookfield, Connecticut, installation of two 14.4 Megavolt Ampere Reactive (MVAR) capacitor banks at the West Brookfield Substation located at 83 Prange Road, Brookfield, Connecticut and related substation and transmission line structure improvements.
PETITION
PROCEDURAL CORRESPONDENCE
DECISION
DEVELOPMENT AND MANAGEMENT PLAN (D&M)
Request for Extension of Construction Time and Council Approval, 12/23/19
Condition Submission - Relocation of Day Care Play Area, 06/24/20
Council Acknowledgement of Condition Submission, 06/26/20
Request for Relocation of Structures 2688 and 2688A, 07/23/20
Council Incomplete Letter on Request for Relocation of Structures, 07/23/20
Revised Request for Relocation of Structures, 07/24/20
Council Decision on Request for Relocation of Structures, 07/24/20
Request for Temporary Work Hour Change and CSC Decision, 08/28/20
Request for Temporary Work Hour Change and CSC Decision, 08/31/20
Request for Temporary Work Hour Change and CSC Decision, 10/15/20
Request for Temporary Work Hour Change and CSC Decision, 11/06/20
Request for Temporary Work Hour Change and CSC Decision, 11/17/20
Notice of Construction Completion, 03/16/21
Condition Submission - Relocation of Day Care Play Area, 06/24/20
Council Acknowledgement of Condition Submission, 06/26/20
Request for Relocation of Structures 2688 and 2688A, 07/23/20
Council Incomplete Letter on Request for Relocation of Structures, 07/23/20
Revised Request for Relocation of Structures, 07/24/20
Council Decision on Request for Relocation of Structures, 07/24/20
Request for Temporary Work Hour Change and CSC Decision, 08/28/20
Request for Temporary Work Hour Change and CSC Decision, 08/31/20
Request for Temporary Work Hour Change and CSC Decision, 10/15/20
Request for Temporary Work Hour Change and CSC Decision, 11/06/20
Request for Temporary Work Hour Change and CSC Decision, 11/17/20
Notice of Construction Completion, 03/16/21
Monthly Construction Reports
Semi-Annual Status of Construction Report, 6/18/19
Semi-Annual Status Report (multiple projects), 02/08/21
Semi-Annual Status Report (multiple projects), 02/08/21