DOCKET NO. 474 - The Connecticut Light & Power Company d/b/a Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the Greater Hartford-Central Connecticut Reliability Project that traverses the municipalities of Hartford, West Hartford, and Newington, which consists of (a) construction, maintenance and operation of a new 115-kilovolt (kV) electric transmission line within existing Eversource, Amtrak and public road rights-of-way and associated facilities extending overhead approximately 2.4 miles and underground approximately 1.3 miles between Eversource’s existing Newington Substation in the Town of Newington and existing Southwest Hartford Substation in the City of Hartford; (b) modifications to a .01 mile section within existing Eversource right-of-way of the existing overhead 115-kV electric transmission line connection to the Newington Substation (Newington Tap); and (c) related modifications to Newington Substation and Southwest Hartford Substation.

APPLICATION, received 06/07/17
PROCEDURAL CORRESPONDENCE
 
PARTIES AND INTERVENORS
 
 
   Applicant - Eversource Energy
Exhibits
Correspondence
Motions and Objections
1.   Transmittal Letter and Certificate of Service dated June 9, 2017;
2.   Motion of Eversource Energy for a Protective Order with Respect to Volume 2, Exhibits 2.D3 and 2 D4 to the Application with Memorandum of Law;
3.   Affidavit of Robert J. Russo;
4.   Proposed Protective Order Re: Critical Energy Infrastructure Information;
5.   Proposed Non-Disclosure Agreement; and
6.   Proposed Request for CEII Pursuant to Protective Order.
 
Post Hearing Briefs and Draft Findings of Fact
COUNCIL'S DRAFT FINDINGS OF FACT
FINAL DECISION
   
         Council's Decision Package, 2/5/18 (complete package)
DEVELOPMENT AND MANAGEMENT PLAN (D&M)
SS/Tap and Underground D&M Plan

 

 

Overhead D&M Plan

 

   
   
 
 
 