Key Dates - 2024

March 20 at 11:45 PM
 Application Deadline
before May 1
 Notification to Applicants
after July 1 & Before July 8
 Return Exhibitor's Agreement Contract with payment.  Due to the State's fiscal year, we cannot accept payment prior to July 1.
before Friday, July 26
 Credential order due with payment (for tickets, parking, dead storage, delivery card, etc.)
before August 1
 Application for Food Permit with payment due to the Town of West Springfield's Health Department
Thursday, August 10 @ 1:30 PM
Vendors' meeting at Connecticut Building in West Springfield MA
Week of September 9
 Vendors move in
Friday, September 13
 Big E starts
Wednesday, September 18
 Connecticut Day @ the Big E
Sunday, September 29
 Big E ends
September 30 - October 4  Vendors move out