PETITION NO. 1386 – New Cingular Wireless PCS, LLC (AT&T) petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed installation of a wireless telecommunications facility at an existing Eversource-owned electric transmission line structure (#917) within an existing Eversource electric transmission line right-of-way located at 5 Tall Pines Drive, Weston, Connecticut.

PETITION (received 10/15/19)

Petition Filing

PROCEDURAL CORRESPONDENCE

Council Letter to the Town of Weston, 10/16/19

Council Interrogatories to New Cingular Wireless PCS, LLC, Set One, 10/29/19

Council Acknowledgement of Comments from the Town of Weston, 11/14/19

Council Set Date for Decision, 12/06/19

Council Interrogatories to New Cingular Wireless PCS, LLC, Set Two, 12/10/19

Council Approval of New Cingular Wireless PCS, LLC Request for Extension to Respond to Interrogatories, 12/20/19

Council Approval of New Cingular Wireless PCS, LLC Request for Extension to Respond to Interrogatories, 01/03/20

STATE AGENCY COMMENTS

MUNICIPAL COMMENTS

Comments from the Town of Weston, 11/13/19

SCHEDULE

Schedule, 10/15/19

Revised Schedule, 12/06/19

SERVICE LIST

Service List, 10/16/19

PARTIES AND INTERVENORS

Petitioner - New Cingular Wireless PCS, LLC

New Cingular Wireless, PCS, LLC Response to Council Interrogatories, Set One, 11/12/19

New Cingular Wireless, PCS, LLC Response to Comments from the Town of Weston, 11/20/19

New Cingular Wireless, PCS, LLC Request for Extension to Respond to Interrogatories, 12/18/19

New Cingular Wireless PCS, LLC Request for Extension to Respond to Interrogatories, 01/03/20

New Cingular Wireless PCS, LLC Response to Council Interrogatories, Set Two, 01/17/19



DECISION


Council Decision and Staff Report, 01/31/2020

Close Out Letter - Professional Opinion Letter, 06/13/22
Notice of Construction Completion, 11/29/22