June 16, 2015
- Asnuntuck Community College New Manufacturing Center, Enfield
- Lathrop Road Extension Water Main, Plainfield
- NEW! Off Airport Obstruction Removal and Lighting Project, Windsor Locks, Willimantic, Groton, Oxford, Hartford, Killingly
"Scoping" is for projects in the earliest stages of planning. At the scoping stage, detailed information on a project's design, alternatives, and environmental impacts does not yet exist. Sponsoring agencies are asking for comments from other agencies and from the public as to the scope of alternatives and environmental impacts that should be considered for further study. Send your comments to the contact person listed for the project by the date indicated.
1. Notice of Scoping for Asnuntuck Community College New Manufacturing Technology Center
Project Title: Asnuntuck Community College New Manufacturing Technology Center (BI-CTC-488)
Project Description: The Connecticut State Colleges and Universities (ConnCSU), in conjunction with Asnuntuck Community College and the Connecticut Division of Construction Services, proposes to construct a new building to aid in the expansion of its existing manufacturing technology program. The new building will be approximately 27,000 gross square feet (GSF) and will contain state-of-the-art instructional spaces for manufacturing technologies, additive manufacturing, and metrology. It will also provide space for computer labs, classrooms, and faculty and administrative spaces. The proposed location for the project is the area to the south of the existing academic building, near the ball fields, where the walking track is currently located. This site was selected for its minimal parking disturbance, its potential for future expansion, and for the possibility of creating a new courtyard between the proposed building and existing campus building. A parking lot expansion of 44 additional parking spaces and a walkway around the perimeter of a park green are also proposed to the south of the proposed building location.
Project Maps: Click here to view the general location (950 kb) Click here to view the proposed site plan (852 kb)
Written comments from the public are welcomed and will be accepted until the close of business on: June 18, 2015.
Any person can ask the sponsoring agency to hold a Public Scoping Meeting by sending such a request to the address below. If a meeting is requested by 25 or more individuals, or by an association that represents 25 or more members, the sponsoring agency shall schedule a Public Scoping Meeting. Such requests must be made by May 29, 2015.
Written comments and/or requests for a Public Scoping Meeting should be sent to:
Name:
|
Jeff Bolton, Supervising Environmental Analyst |
Agency: | DAS - Division of Construction Services |
Address: | 165 Capitol Avenue, Room 483, Hartford, CT 06106 |
Fax: | 860-713-7251 |
E-Mail: | Jeffrey.bolton@ct.gov |
Name: | Jeff Bolton, Supervising Environmental Analyst |
Agency: | DAS - Division of Construction Services |
Address: | 165 Capitol Avenue, Room 483, Hartford, CT 06106 |
Phone: | 860-713-5706 |
Fax: | 860-713-7251 |
E-Mail: | Jeffrey.bolton@ct.gov |
The agencies expect to make a determination on whether an Environmental Impact Evaluation for this project is warranted in June/July 2015.
2. Notice of Scoping for Lathrop Road Extension Water Main
Municipality where proposed project might be located: Plainfield
Address of Possible Project Location: Norwich Road and Lathrop Road Extension
Project Description: The project consists of installation of a new 12-inch ductile iron water main and appurtenances to provide water service to both existing and proposed industrial businesses along Lathrop Road Extension and Community Avenue Extension. This project will be funded through a Small Town Economic Assistance Program (STEAP) Grant distributed by the Office of Policy and Management (OPM). The Connecticut Water Company will oversee this project for the Town and will own and maintain this water main as part of its distribution system once the project is completed.
Project Maps: Click here to view a map of the project area. Click here to view a map of the proposed water main installation.
Written comments from the public are welcomed and will be accepted until the close of business on: Monday, July 6, 2015.
Any person can ask the sponsoring agency to hold a Public Scoping Meeting by sending such a request to the address below. If a meeting is requested by 25 or more individuals, or by an association that represents 25 or more members, the sponsoring agency shall schedule a Public Scoping Meeting. Such requests must be made by Friday, June 12, 2015.
Written comments and/or requests for a Public Scoping Meeting should be sent to:
Name: | Mr. Eric McPhee |
Agency: |
Department of Public Health
Drinking Water Section
|
Address: | 410 Capitol Avenue, MS #51WAT |
PO Box 340308
Hartford, CT 06134-0308
|
|
Fax: | 860-509-7359 |
E-Mail: | DPH.SourceProtection@ct.gov |
If you have questions about the public meeting, or other questions about the scoping for this project, contact:
Name: | Patricia Bisacky |
Agency: |
Department of Public Health
Drinking Water Section
|
Address: |
410 Capitol Avenue, MS #51WAT
PO Box 340308
Hartford, CT 06134-0308
|
Phone: | 860-509-7333 |
Fax: | 860-509-7359 |
E-Mail: | Patricia.Bisacky@ct.gov |
3. Notice of Scoping for Connecticut Airport Authority (CAA) Off-Airport Obstruction Removal and Lighting Project
Municipalities where proposed project might be located: Windsor Locks (Bradley International Airport), Willimantic (Windham Airport), Groton (Groton-New London Airport), Oxford (Waterbury-Oxford Airport), Hartford (Hartford-Brainard Airport) and Killingly (Danielson Airport).
Address of Possible Project Location: Various (see above)
Project Description: The proposed undertaking involves preparation of National Environmental Policy Act (NEPA) and Connecticut Environmental Policy Act (CEPA) documentation as required to evaluate the potential impacts associated with tree obstruction removal and obstruction lighting at Bradley International Airport and the five state-owned general aviation airports as identified and listed above. The evaluation will address obstruction removals and lighting associated with Federal Aviation Regulations (FAR) Part 77, Safe, Efficient Use, and the Preservation of Navigable Airspace and published Terminal Instrument Procedures (TERPS), which define and regulate the airspace beyond the ends of runways through the establishment of imaginary surfaces. Objects that penetrate these surfaces are classified as airspace obstructions, and should be removed to safely accommodate approaching and departing aircraft.
The project sponsoring agency, the Connecticut Aviation Authority (CAA), and Federal Aviation Administration (FAA) have identified that trees penetrate the airspace at Bradley International Airport and airspace at the five state-owned general aviation airports, including locations beyond defined airport property boundaries. Per FAA practice, review of off-airport obstruction removal should be evaluated and documented per federal (NEPA) and state (CEPA) environmental guidelines and requirements. This project also includes the identification of each affected property owner and associated parcels (both public and private) with necessary obstruction removals, obstruction lighting, and anticipated project access routes.
Project Maps: Project maps for each airport can be found at the following locations:
Bradley International Airport Obstruction Removal and Lighting Documents
Danielson Airport Obstruction Removal and Lighting Documents
Groton-New London Airport Obstruction Removal and Lighting Documents
Hartford-Brainard Airport Obstruction Removal and Lighting Documents
Waterbury-Oxford Airport Obstruction Removal and Lighting Documents
Windham Airport Obstruction Removal and Lighting Documents
Written comments from the public are welcome and will be accepted until the close of business on: Friday, July 17, 2015.
Any person can ask the sponsoring agency (CAA) to hold a Public Scoping Meeting by sending such a request to the address below. If a meeting is requested by 25 or more individuals, or by an association that represents 25 or more members, the sponsoring agency shall schedule a Public Scoping Meeting. Such requests must be made by Friday, June 26, 2015.
Written comments and/or requests for a Public Scoping Meeting should be sent to:
Name: |
Mr. Robert J. Bruno, Director of Planning, Engineering & Environmental |
Agency: |
Connecticut Airport Authority |
Address: |
334 Ella Grasso Turnpike, Suite 160 |
Windsor Locks, CT 06096 |
|
Phone: |
(860) 254-5516 |
E-Mail: |
rbruno@ctairports.org |
If you have questions about the public meeting, or other questions about the scoping for this project, contact:
Name: |
Mr. Robert J. Bruno, Director of Planning, Engineering & Environmental |
Agency: |
Connecticut Airport Authority |
Address: |
334 Ella Grasso Turnpike, Suite 160 |
Windsor Locks, CT 06096 |
|
Phone: |
(860) 254-5516 |
E-Mail: |
rbruno@ctairports.org |
The agency expects to release an environmental document for this project, for public review and comment, in October 2015.
No State Land Transfer Notice has been submitted for publication in this edition.