Yes. The entire facility, as it is intended to operate upon final licensure, must be built and inspected prior to the expiration of the provisional license and meet all minimum requirements for operation as outlined in the department’s policies and procedures. The department intends to inspect facilities around 25 percent, 50 percent, 75 percent, and 100 percent build milestones to help registrants avoid unforeseen issues and delays that may arise.
Is the entire facility buildout and inspection required for the final license before the expiration of the provisional license?