CDBG-DR Program

Funded Projects Transparency

(as of 08/31/2018)

Multifamily Housing

Funds Allocated: $30,000,000                        Funds Disbursed to Date:$29,671,387.66                        (99%)

No.

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

1

Bridgeport

#4101

Crescent Crossing Phase 1

$6,975,000

$6,975,000.00

Under Construction. CDBG-DR funds fully expended

2

Stamford

#4102

Summer Place

$6,400,000

$6,400,000.00

Project Completed & CDBG-DR funds fully expended.

3

Norwalk

#4103

Washington Village

$11,855,590

$11,855,590.00

Phase 1 Completed. CDBG-DR Funds fully disbursed.

4

N/A

Scattered Sites

$4,769,410

$4,440,797.66

.

Economic Revitalization

Funds Allocated:$194,000                        Funds Disbursed to Date:$194,000                        (100%)

No.

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

1

Milford

Charles Island Oyster Farm

$50,000

$50,000

Completed: Funds disbursed

2

Fairfield

Inn at Fairfield Beach

$44,000

$44,000

Completed: Funds disbursed

3

Branford

Lenny’s Indian Head Inn

$50,000

$50,000

Completed: Funds disbursed

4

Stratford

Main Enterprises

$50,000

$50,000

Completed: Funds disbursed

Public Facilities

Funds Allocated:$510,000.00                        Funds Disbursed to Date:$63,165.59                        (12%)

No.

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

1

Milford

#8102

Gulf Beach Breakwater Reconstruction

$503,500

$ 49,613.02

Assistance Agreement  fully executed on 1/29/16. Time Extension granted to 6/30/19.  

TOTAL

$503,500

$ 49,613.02

Planning

Funds Allocated:$9,500,000.00                        Funds Disbursed to Date: $7,187,850.67                        (76%)

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

Branford, Madison, Milford

#6107

Creating Coastal Resilience

$150,000

$150,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 12/15/14.

Branford

(Shoreline Shellfish)

#6108

Living & Artificial Reef: Creation & Restoration

$415,000

$415,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 12/8/14.

Bridgeport

#6109

Marina Village Resiliency

$100,000

$100,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 12/15/14.

CT Rises

#6229

Long Term Recovery

$111,550

$101,594.40

Assistance Agreement fully executed on 5/24/16.

DEEP

#6201

Develop tools to assess the vulnerability of infrastructure

$1,205,450

$1,115,720.10

Time Extension granted to 12/1/18. MOU Fully Executed on 9/23/15

DEEP

#6225

Water Supply Resiliency  - 17 towns

$530,000

$530,000.00

Project Completed and Fully executed on 2/15/18. MOU Fully Executed on 3/17/16.

DEMHS

#6215

Update CT Natural Hazard  Mitigation Plan

$50,000

$13,735.34

MOU fully executed 1/31/17

DPH

#6226

Statewide public drinking water vulnerability assessment & resilience plan.

$600,000

$600,000.00

Project completed and CDBG-DR funds fully disbursed. MOU Fully Executed on 4/28/16.

Fairfield

#6203

Pine Creek Dike Expansion

$300,000

$0.00

Project will not move forward – Request to Transfer funds approved. 

Fairfield

#6204

Fairfield Beach Engineered Design

$99,865.00

$99,865.00

Project completed and fully disbursed 3/15/18. . Assistance Agreement fully executed on 1/25/16.

Fairfield

#6205

Riverside Drive Coastal resiliency

$500,000

$227,853.54

Additional funds transferred Amended & reinstated Asst. Agreement fully executed on 3/16/18.

Fairfield

#6209

S. Benson Storm water Pump Station & Drainage

$300,000

$257,308.90

Sub agmt fully executed 8/30/16. Assistance Agreement fully executed on 3/17/16.

Fairfield

#6210

Downtown Using Green Infrastructure - Roadways

$100,000

$100,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 3/17/16.

Lower River Cog

#6202

Land Use Resiliency Plan

$100,000

$100,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 5/24/16.

Milford

#6206

Crescent Beach Study

$225,000

$151,850.00

Assistance Agreement  fully executed on 2/24/16.

Milford

#6207

Gulf St. & Welch’s Point Rd Study

$275,000

$138,247.50

Assistance Agreement fully executed on 2/24/16.

Milford

#6208

Walnut & Wildemere Beach Study

$525,000

$344,700.00

Additional $200K granted on 1/24/17. Assistance Agreement  fully executed on 2/29/16.

Milford

#6227

Pelham St Planning & Design

$150,000

$32,642.62

Assistance Agreement fully executed on 3/8/16.

New Haven

#6101

Bulkhead Engineering and Design

$342,000

$221,573.45

Assistance Agreement fully executed on 11/21/14. Project completed. Residual balance of $120,426.55 to be reallocated to another project

New Haven

#6102

Hill Neighborhood & Union Ave. Drainage Improvements

$500,000

$500,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 4/7/15.

New Haven

#6103

Long Wharf Flood Protection

$400,000

$400,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 4/7/15..

New Haven

#6104

Mill River Shoreline Analysis/Coastal Zone Management

$191,250

$180,395.00

Assistance Agreement fully executed on 1/6/15.. Project completed. Residual balance of $10,855 to be reallocated to another project. 

New Haven

#6216

Resiliency Plan for Redevelopment - Church Street

$500,000

$500,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement  fully executed on 3/30/16.

New London

#6105

Bank Street Drainage Improvement

$200,000

$198,933.00

Assistance Agreement fully executed on 12/15/14. Project Complete. Residual balance of $1,067 to be reallocated to another project.

Old Saybrook

#6213

Resiliency Study & Infrastructure Evaluation

$125,000

$125,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement  fully executed on 2/29/16.

Stratford

#6106

Coastal Resiliency Plan

$100,000

$100,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 5/4/15..

Stonington

#6211

Town of Stonington Coastal Resilience Plan

$150,000

$150,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement fully executed on 2/29/16.

West Haven

#6212

Resiliency Plan & Wastewater Treatment Facility Outfall

$278,000

$277,999.70

Project Completed and fully expended on 6/19/17. Assistance Agreement fully executed on 3/17/16.

New London

#6224

Shaw's Cove Pump Station

$120,000

$46,576.50

Assistance Agreement fully executed on 3/30/16.On 11/30/17 NL requested to use the balance of funds for an infrastructure project.

UCONN -

CIRCA

#6220

Scoping for Green Infrastructure Resiliency Projects

$317,709

$316,175.36

MOU fully executed on 3/14/16. Time Extension granted to 3/31/18. 

Waterford

#6228

Climate Change Vulnerability

$175,000

$175,000.00

Project completed and CDBG-DR funds fully disbursed. Assistance Agreement  fully executed on 3/30/16.

Westport

#6222

Master Drainage Plan - Downtown

$650,000

$599,894.37

Assistance Agreement fully executed on 3/30/16.

Infrastructure

Funds Allocated:$36,719,000                            Funds Disbursed to Date: $9,946,616.57                      (27%)

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

Bridgeport

#7201

Crescent Crossing for Housing Development

$3,277,992

$3,277,992.00

Under Construction. All CDBG-DR funds have been fully disbursed for this project.

Bridgeport

DOT

#7203

Yellow Bridge Resiliency

$2,625,000

$2,160,538.17

MOU fully executed 12/8/16RROF issued by HUD on 12/5/16.

East Haven

#7204

Hemingway & Coe Avenue Reconstruction

$1,214,831

$149,798.00

Time Extension granted to 6/30/19.  Assistance Agreement mailed out to municipality on 1/24/17.

Fairfield

#7101

Pine Creek Culvert Upgrade

$607,500

$605,803.04

Assistance Agreement fully executed on 2/29/16.

Fairfield

#7102

W.P.C.F. Outfall Pipe

$74,500

$12,325.00

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 9/6/16.

Fairfield

#7205

Penfield Beach Resiliency Improvements - Bulkhead

$225,000

$8,897.92

Project will not move forward. Assistance Agreement fully executed on 9/15/16.

Fairfield

#7206

Wastewater Treatment Plant Resiliency

$2,316,000

$166,044.06

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 5/31/16.

Fairfield

#7207

Water Pollution Control Micro-Grid

$2,813,939

$1,414,143.57

Time Extension granted to 12/31/18.  Assistance Agreement fully executed on 5/31/16.

Milford

#7103

Morningside Revetment Reconstruction

$1,180,480

$132,031.25

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 1/29/16.

Milford

#7208

Essential Generators

$177,000.00

$177,000.00

A Project Completed and fully expended on 3/5/18. Assistance Agreement fully executed on 2/18/16.

Milford

#7209

Calf Pen Meadow/Beachland Avenue Resiliency

$638,250

$31,425.00

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 2/2/16.

Milford

#7210

Bayview Beach Area Flooding Control

$1,726,150

$252,253.45

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 2/2/16.

Milford

#7211

Milford Point Road Flooding Control,

$501,537

$53,639.07

Time Extension granted to 6/30/19.  Assistance Agreement fully executed on 2/2/16. FMC approved 9/23/16.

New Haven

#7104

Brewery Square Bulkhead Rehab

$940,047

$859,376.79

Construction activity completed. Assistance Agreement fully executed 5/24/16. 

New Haven

#7212

East Shore Erosion Control

$1,900,000

$154,766.75

Time Extension granted to 6/30/19.  Assistance Agreement fully executed   11/27/17. HUD Approved RROF on 7/31/17.

New Haven

#7213

Union Avenue Mitigation and Resiliency

$4,000,000

$17,506.10

Assistance Agreement fully executed 8/4/17. HUD approved RROF on 4/17/17.

New London

#7214

Drainage Improvements

$1,480,875

$171,362.68

Assistance agmt fully executed 10/27/16. Time extension granted to 12/31/18.

Norwalk

#7215

Washington Village Redevelopment

$4,000,000

$3,151,183.66

Assistance Agreement fully executed on 4/6/17. RROF issued by HUD on 12/7/16.

Norwalk

DOT

#7216

Route 136 Bridge Resiliency

$2,625,000

$1,524,850.39

MOU fully executed 12/8/16. RROF issued by HUD on 12/5/16.

Old Lyme

#7217

Sheffield Brook Outfall Resiliency

$318,975.38

$318,975.38

Project Complete. DEEP approval letter rec’d 8/10/16. Received a letter on 3/12/18 requesting an additional $18,975.38. Approved on 3/20/18. Assistance Agreement fully executed on 2/2/16.

Stamford

#7218

Generator Upgrades

$303,795

$132,451.22

Revised AA Returned on 1/31/17. Scope of work changed to only one generator. Assistance Agreement fully executed on 4/14/16.

Stratford

#7219

Bunnell High School Generator

$211,350.00

$211,350.00

Project Complete Assistance Agreement fully executed on 6/21/16.

West Haven

#7221

Beach Street & 1st Avenue Reconstruction

$ 2,946,300

$178,296.35

Assistance Agreement fully executed on 9/27/17. On 7/12/18 received request of $2M for Phase2 and $4M for Phase3. HUD Approved RROF on 7/31/17. FMC submitted to DEEP on 8/4/17

West Haven

#7220

Old Field Creek Dredging

$525,000

$93,452.50

Assistance Agreement fully executed on 1/23/18. Request to Release Funds approved by HUD on 10/12/17.

Rebuild By Design

Town

Project Name

Amount Obligated

Amount Disbursed

Project Status

Waggoner & Ball Arch.

#9301

Rebuild by Design – Architectural & Community Engagement Services

$2,230,000

$2,229,415.15

Completed the 5th Substantial Amendment describing the pilot project and its implementation strategy.