School Construction

Page 2 of 2

  • School Construction Project Closure and Audit Procedures

    Pursuant to C.G.S. 10-287i, every school construction project that has received State grant assistance is subject to an audit by the Department of Administrative Services (DAS). Please note that C.G.S. 10-287i references a holdback of each grant prior to DAS completing and authorizing the release of the retained grant.

  • School Construction Project Closure and Audit Procedures

    Pursuant to C.G.S. 10-287i, every school construction project that has received State grant assistance is subject to an audit by the Department of Administrative Services (DAS). Please note that C.G.S. 10-287i references a holdback of each grant prior to DAS completing and authorizing the release of the retained grant.

  • School Construction Project Requirements from the Department of Energy and Environmental Protection (DEEP)

    There are numerous Environmental, Health and Safety requirements that will potentially affect a school construction project. Some of the more common and important of these requirements are listed below. Not every possible requirement is listed, and this information is only intended as a helpful summary.

  • School Construction Site Review and Approval

    If a Local Education Agency (LEA) is seeking a school construction grant from the Office of Grants Administration, the LEA may be required to obtain Site Approval from DAS. To receive Site Approval, file FORM SCG-053 with attachments as required.

  • School Construction State Reimbursement Percentages

    Reimbursement percentages are calculated annually. Each project receives a reimbursement percentage based on the date the town or district secured the local share of funding for the school construction project pursuant to Connecticut General Statutes. Current reimbursement rates subject to each town or district can be found on this page.

  • School Construction State Reimbursement Percentages

    Reimbursement percentages are calculated annually. Each project receives a reimbursement percentage based on the date the town or district secured the local share of funding for the school construction project pursuant to Connecticut General Statutes. Current reimbursement rates subject to each town or district can be found on this page.

  • School Construction State Reimbursement Percentages

    Reimbursement percentages are calculated annually. Each project receives a reimbursement percentage based on the date the town or district secured the local share of funding for the school construction project pursuant to Connecticut General Statutes. Current reimbursement rates subject to each town or district can be found on this page.

  • The Office of Grants Administration - Policies, Memos and Online Training

    All school projects seeking State grant assistance as a “Priority List Project” shall be reviewed by the Office of Grants Administration at the “conceptual design” phase and again at the “schematic design” phase in addition to the currently required reviews.