PETITION NO. 1398A - LSE Pictor, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1.99-megawatt AC solar photovoltaic electric generating facility on an approximately 104 acre parcel located off of Platt Hill Road, Winchester, Connecticut and associated electrical interconnection. Reopening of this petition based on changed conditions pursuant to Connecticut General Statutes §4-181a(b). Link to Petition No. 1398
Motion to Reopen Based on Changed Conditions
LSE Pictor, LLC Motion to Reopen, 01/15/21
PROCEDURAL CORRESPONDENCE
Council Memorandum Regarding Motion to Reopen and Modify, 01/19/21
Council Decision on Motion to Reopen and Modify, 02/17/21
Council Letter to the Town of Winchester, 02/17/21
Council State Agencies Memorandum, 02/17/21
Council Interrogatories to Petitioner, 3/23/21
STATE AGENCY COMMENTS
Department of Transportation Comments, received 3/24/21
MUNICIPAL COMMENTS
Town of Winchester's Comments, 12/04/20
SCHEDULE
Schedule, 02/11/21
SERVICE LIST
Service List, 02/18/21
PETITIONER - LSE Pictor, LLC
Petitioner Responses to Council Interrogatories, Set One, 4/7/21
DECISION
Council Decision and Staff Report, 5/07/21
Cover Letter with Condition 3 - DEEP Stormwater Permit, 09/09/21
Submission of Condition 2 - Final Structural Design, 09/09/21
Council Acknowledgement of Condition Submission, 09/10/21
Council Status Update Letter, 11/15/24