PETITION NO. 1398 - LSE Pictor, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1.99-megawatt AC solar photovoltaic electric generating facility on an approximately 104 acre parcel located off of Platt Hill Road, Winchester, Connecticut and associated electrical interconnection.
PETITION (received 03/27/20)
Cover Letter
Narrative
Exhibit 1 - Site Plans
Exhibit 2 - Equipment Specifications
Exhibit 3 - Operations and Maintenance Plan
Exhibit 4 - Decommissioning Plan
Exhibit 5 - Carbon Debt Analysis
Exhibit 6 - Service List - Abutters Notification
Exhibit 7 - Service List - Agencies and Officials
Exhibit 8 - Environmental Evaluations
Exhibit 9 - Supporting Documentation and Stormwater Management Report
Exhibit 10 - Wetlands Delineation and Impact Analysis
Exhibit 11 - Noise Analysis
Exhibit 12 - FAA Determination of No Hazard
Exhibit 13 - State Historic Preservation Office Correspondence
PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Winchester, 03/30/20
State Agencies Comment Memorandum, 03/30/20
Council Response to the Town of Winchester's Request for an Extension of Time to Submit Comments, 04/17/20
Council Interrogatories to LSE Pictor, LLC, Set One, 04/21/20
Council Response to the Town of Winchester's Request for an Extension of Time to Submit Comments, 05/22/20
Council Set Date for Decision Letter, 06/05/20
Council Acknowledgement of Town of Winchester Comments, 06/10/20
Council Interrogatories to LSE Pictor, LLC, Set Two, 06/22/20
Council Set Date for Decision Letter, 08/14/20
Council Interrogatories to LSE Pictor, LLC, Set Three, 08/14/20
STATE AGENCY COMMENTS
Council on Environmental Quality Comments, 05/27/20
MUNICIPAL COMMENTS
Town of Winchester's Request for an Extension of Time to Submit Comments, 04/17/20
Town of Winchester's Request for an Extension of Time to Submit Comments, 05/22/20
Town of Winchester's Comments, 06/02/20
Town of Winchester's Comments, 12/04/20
SCHEDULE
Schedule, 03/27/20
Revised Schedule, 04/20/20
Revised Schedule, 05/26/20
Revised Schedule, 06/15/20
SERVICE LIST
Petitioner - LSE Pictor, LLC
LSE Pictor, LLC Responses to Interrogatories, Set One, 05/12/20
LSE Pictor LLC Responses to Interrogatories, Set Two, 07/09/20
Exhibit D - Revised Site Plans, Set Two
Exhibit E - NDDB Response
Exhibit F - Cultural Resources Report
LSE Pictor, LLC Correspondence from State Historic Preservation Office, 08/04/20
LSE Pictor LLC Responses to Interrogatories, Set Three, 08/19/20
LSE Pictor LLC Project Update Letter, 09/14/20
LSE Pictor LLC Project Update Letter, 09/22/20
Decision
Decision and Staff Report, 09/28/20
Motion to Reopen Based on Changed Conditions
LSE Pictor, LLC Motion to Reopen, 01/15/21
Council Memorandum Regarding Motion to Reopen and Modify, 01/19/21