PETITION NO. 1387 – Bloom Energy Corporation Generate C&I Warehouse, LLC Generate Colchester Fuel Cell, LLC declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a grid-side 10-megawatt (MW) fuel cell facility and associated equipment to be located at Eversource Energy’s existing Judd Brook electric distribution substation, 160 Old Amston Road, Colchester, Connecticut.

 

PETITION (received 10/25/19)

 

PROCEDURAL CORRESPONDENCE

 

STATE AGENCY COMMENTS

 

SCHEDULE

 

SERVICE LIST

 

PARTIES AND INTERVENORS
Petitioner - Bloom Energy Corporation

 

 
DECISION

 

DEVELOPMENT & MANAGEMENT PLAN
Development & Management Plan, 2/14/20
Council Development & Management Plan Interrogatories to Bloom Energy Corporation, 3/4/20
Bloom Energy Corporation's Responses to Council D&M Plan Interrogatories, 3/11/20
Council Request for an Extension, 03/12/20
Bloom Response to Council's Extension Request, 03/13/20
Council D&M Plan Decision and Staff Report, 03/27/20 
Bloom D&M Plan Decision Condition Submission, 03/31/20 
Council Response to Incomplete Condition Submission, 04/01/20 
Bloom Revised D&M Plan Decision Condition Submission, 4/01/20 
Council Acknowledgement of Revised D&M Plan Decision Condition, 04/02/20
D&M Condition 2 Submission and Council Acknowledgement, 06/26/20
Council Acknowledgement Change of Ownership, 07/15/21
Council Acknowledgement Change of Ownership, 11/14/22
Council Status Update Letter, 11/15/24