PETITION NO. 1324 – Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 1.0 Megawatt AC solar photovoltaic electric generating facilities located at Plainfield Pike Road, Plainfield, Connecticut.
 
                           Filing Received, 8/31/2017
 
Procedural Correspondence
 
                           Incomplete Letter from the Council to Windham Solar, LLC 9/6/2017
                           Withdrawal Letter, 10/4/2017
                           CSC Response and Approval of Withdrawal Letter, 10/5/2017