PETITION NO. 1266 - Doosan Fuel Cell America, Inc. petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the construction, maintenance, and operation of a 1840-kilowatt customer-side fuel cell facility to be located at the Waterbury Water Pollution Control Plant, 210 Municipal Road, Waterbury, Connecticut. (REC. 10/28/2016)
PETITION
PRODECURAL CORRESPONDENCE
Field Review
Interrogatories to Petitioner, 11/22/2016
Doosan Request for Extension to Respond to Interrogatories and CSC Approval of Extension Request, 12/07/16
Doosan's Responses to Council Interrogatories, 12/15/16
Council's Date of Decision Letter, 12/23/16
Council Interrogatories to Doosan, Set II, 12/28/16
Doosan Request for Extension to Respond to CSC Interrogatories, Set II, 1/17/17
Council Decision on Doosan's Request for Extension to Respond to Interrogatories, Set II, 1/18/17
Doosan's Responses to Council Interrogatories, Set II, 1/18/17
Comments from the Department of Transportation, 1/26/17
Doosan's Response to Council Interrogatory 30, Set Two, 02/10/17
DECISION