Groton WTP Upgrades
1. Post-Scoping Notice for the Groton Water Treatment Plant Upgrade
Municipality where project will be located: Groton
CEPA Determination: On June 3, 2014 the Department of Public Health (DPH) published a Notice of Scoping to solicit public comments for this project in the Environmental Monitor.
Based on the comments provided by the Department of Energy & Environmental Protection (DEEP) dated July 2, 2014 and July 7, 2014, and the DPH determination of consistency with the Conservation and Development Policies Plan for the State of Connecticut, it has been determined that the project does not require the preparation of Environmental Impact Evaluation (EIE) under CEPA. The DPH will coordinate with Groton Utilities to ensure that the recommendations by the DEEP will be implemented.
The agency's conclusion is documented in a Memorandum of Findings and Determination and an Environmental Assessment Summary.
If you have questions about the project, you can contact the agency at:
|
Name: |
Eric McPhee |
|
Agency: |
Department of Public Health |
| Drinking Water Section | |
|
Address: |
410 Capitol Avenue, MS#51WAT |
| PO Box 340308 | |
| Hartford, CT 06134-0308 | |
|
Phone: |
860-509-7333 |
|
Fax: |
860-509-7359 |
|
E-Mail: |
DPH.SourceProtection@ct.gov |
What happens next: The DPH expects the project to go forward. This is expected to be the final notice of the project to be published in the Environmental Monitor.