Barnum Train Station

2. Notice of EIE for New Commuter Railroad Station - Barnum Avenue

Municipality where project is proposed: Bridgeport

Address of Possible Project Location: Barnum Avenue between Seaview Avenue and Pembroke Street

Project Description: The proposed project consists of constructing a new commuter rail station on the New Haven Line of Metro North Railroad.  The proposed project will include a new station, two center-island platforms to provide the flexibility to serve both local and express trains, reconstructing track to accommodate these platforms, cross track pedestrian access to the platforms, widening of the retained railroad embankment, catenary structure relocation, a surface parking lot, sidewalks, landscaping, and bicycle and pedestrian amenities as appropriate. The proposed project site is currently vacant, and was previously occupied by structures associated with the Remington Arms Facility. The proposed station would require expanding the railroad right-of-way (ROW) to accommodate the passenger platforms and would require permanently closing or relocating Crescent Avenue between Hallett Street and Waterview Avenue, and potentially to Seaview Avenue.  The vacant site north of the ROW would serve as the surface parking lot.   It is also possible that some type of small facility may be constructed to serve multiple purposes including a waiting area for passengers.  It is proposed that vehicles would access the station from Barnum avenue; pedestrian and cyclists access routes to the station will consider ease of access, surrounding land use, and future development in the vicinity. 

Currently, East Bridgeport suffers from a lack of convenient rail service, needed to sustain existing businesses and meet the areas future transportation demands.  Due in large part to planning and financing efforts of the City of Bridgeport, significant development projects are underway or planned in East Bridgeport.  The proposed station will support this growth.

Project Maps:  Click here to view maps of the project area.

Comments on this EIE will be accepted until the close of business on: Tuesday February 21, 2017

The public can view a copy of this EIE at: The Connecticut Department of Transportation Bureau of Policy and Planning (Room 2155), 2800 Berlin Turnpike, Newington, CT; Bridgeport City Hall, City Clerk Office, 45 Lyon Terrace, Bridgeport, CT; and each of the following City of Bridgeport Public Library branches: Black Rock Branch, Newfield Branch, Old Mill Green Branch, Burroughs-Saden Branch, and North Branch.

The EIE is available electronically by clicking here.

It is also available online at: www.ct.gov/environmentaldocuments       

There is a public hearing scheduled for this EIE on:

DATE: Tuesday February 7, 2017 (Inclement weather date: Tuesday, February 14, 2017 same time and place) 

TIME: Open Forum at 6:00 p.m. and Formal Presentation at 6:30 p.m.

PLACE: Great Oaks Charter School, 1st Floor Cafeteria, 510 Barnum Avenue, Bridgeport, CT 06608

NOTES: The hearing location is accessible to persons with disabilities.  Deaf, hearing impaired persons, and those with Limited English Proficiency wishing to attend this hearing and requiring an interpreter must make arrangements by contacting the Department of Transportation's Office of Communications at 860-594-3062 (voice only) at least five working days prior to the hearing.

Send your comments about this EIE to:

Mr. Mark W. Alexander,
Transportation Assistant Planning Director
Connecticut Department of Transportation
Bureau of Policy and Planning
2800 Berlin Turnpike, Newington, CT 06131
E-Mail: dot.environmentalplanning@ct.gov

If you have questions about the public hearing, or where you can review this EIE, or similar matters, please contact:

Mr. Keith A. Hall, Project Manager
Connecticut Department of Transportation
Bureau of Engineering and Construction
2800 Berlin Turnpike, Newington, CT 06131
E-Mail: Keith.A.Hall@ct.gov
Phone: 860-594-3301