Emergency Burn Ban In Effect 10/26/24 - An emergency burn ban is now in effect for all Connecticut State Parks, Forests, and Wildlife Management areas, prohibiting the use of all outdoor grills, firepits, and campfires, and the kindling and use of flame outdoors. DEEP and local agencies are working to contain several active fires across the state. Please avoid all affected State Parks and Forests, as well as the blue-blazed Mattabesett Trail. The Enduro Trail in Voluntown and portions of North Stonington within the Pachaug State Forest are closed at this time. Please note that today's forest fire danger report remains at an 'extreme' level. More information about the current fire danger, burn ban and recommended safety measures can be found here

Overview of the Connecticut
Coastal Permit Program

Go Paperless with DEEP's ezFile! COP and Structures, Dredging and Fill (SDF) applications can be submitted through DEEP's on-line ezFile system. Learn more on the benefits of ezFile and how to create an account.

The DEEP's Land and Water Resources Division (LWRD) regulates all activities conducted in tidal wetlands and in tidal, coastal, or navigable waters in Connecticut under the Structures, Dredging and Fill statutes, Connecticut General Statutes (CGS) Sections 22a-359 - 22a-363h, inclusive, and the Tidal Wetlands statutes, CGS Sections 22a-28 - 22a-35, inclusive. The major objectives of the permit program are to avoid or minimize navigational conflicts, encroachments into the state's public trust area, and adverse impacts on coastal resources and uses, consistent with Connecticut's Coastal Management Act (CCMA), CGS Sections 22a-90 - 22a-112, inclusive.

Three types of permits are issued for activities conducted in coastal, tidal, or navigable waters or within tidal wetlands, depending on the nature of the work proposed. Each involves a different review process, as explained below.

Individual Permits

Certain activities require an "individual" permit specific to the proposed work. These activities typically include new construction and other work for which a detailed review of potential environmental impacts is needed. The review process for an individual permit provides an opportunity for public comment. Individual permit applications can be completed and submitted through our on-line portal, ezFile.

Certificates of Permission

Minor activities related to previously authorized work may be eligible for a Certificate of Permission (COP). These activities include maintenance dredging and substantial maintenance of existing structures. In some cases, maintenance of unauthorized activities that were completed prior to specific dates may also be eligible for a COP. In addition, certain environmentally beneficial activities, such as the removal of derelict structures and restoration of degraded tidal wetlands, may be approved through the COP process. COP's are issued within 45 days, or within 90 days if additional information is requested by LWRD to complete its review. COP applications can be completed and submitted through our on-line portal, ezFile.

General Permits

General permits are issued to authorize certain minor activities. Because the environmental impacts of those activities are understood, detailed permit reviews are generally not required. General permits are typically issued within 90 days if a complete application is received. The following structures and activities may be eligible for authorization through a general permit:

  • Small residential docks having no navigational or environmental impacts
  • Boat moorings
  • Osprey nesting platforms and perch poles
  • Residential flood hazard mitigation
  • Buoys and markers for navigation and certain recreational activities
  • Swim floats
  • Pump-out facilities at marinas
  • Coastal remedial activities
The Application Review Process

Before submitting a permit application, we advise that you consult with LWRD staff to determine the appropriate permit process. A pre-application meeting is strongly recommended prior to the submittal of an application seeking authorization to work within tidal wetlands, or in tidal, coastal, or navigable waters of the state. We also recommend that you consult with and/or hire a professional such as a land surveyor, engineer, or environmental/marine consultant familiar with our Department's permitting process who can assist you in the preparation of the application and plans.

You may contact the appropriate LWRD staff for your area to request an application package and to schedule a pre-application meeting with the appropriate Permitting analyst. Please be sure to fill out and bring a completed pre-application questionnaire along with supporting documents to the pre-application meeting.

If you are applying for an individual permit, you must publish a Notice of Application in a local newspaper, notify the chief elected official of the municipality in which the activity is proposed, and pay an initial application fee. Following an initial review of your application, you will receive a letter assessing a permit fee based on the project's area of impact, and requesting additional information if necessary. When your application is complete, LWRD will publish a public Notice of Tentative Determination as to its permissibility. The public may submit comments on the application, and in some cases a public hearing may be held. General permits and Certificates of Permission also require application fees, but neither requires a public notice or hearing.

Proposed activities will be reviewed to determine their potential effect on coastal resources and uses. Factors that will be considered include the effect of the project on:

  • The preservation of natural habitats and living marine resources;
  • Shoreline erosion and coastal flooding;
  • Water quality and pollution control;
  • The use and development of all adjoining lands;
  • Coastal and inland navigation;
  • Use of the state's public trust land and water; and,
  • The rights and interests of all persons concerned with the proposed activity.

If you are proposing to do work which requires a United States Army Corps of Engineers permit for discharge of dredged material or for the placement of rock, soil or other fill material in tidal waters, you may also need to obtain a state Water Quality Certificate. Certificates are issued by DEEP in accordance with Section 401 of the federal Clean Water Act and the Connecticut Water Quality Standards and are generally incorporated in the corresponding DEEP permit. Certain minor activities may qualify for an Army Corps Programmatic General Permit (PGP), which is an expedited process for securing Corps permits. Information about the PGP may be obtained from LWRD staff.

Coastal Regulatory Jurisdiction

The area of the shore subject to Connecticut's regulatory authority includes everything waterward of the Coastal Jurisdiction Line (CJL) or within tidal wetlands. The CJL is a land elevation on the North American Vertical Datum of 1988 (NAVD88) and is based on a specific predicted tide. Mean high water (MHW) is the land elevation indicating the average shoreward extent of all high tides. MHW also denotes the seaward limit of private property ownership in Connecticut. Mean low water (MLW) represents the average extent of all low tides. Navigable waters include tidal rivers upstream to the limit of the first dam or obstruction.

Construction Landward of the Coastal Jurisdiction Line

Construction activities landward of the coastal jurisdiction line within the coastal boundary are subject to Coastal Site Plan Review, as appropriate, by individual municipalities. In addition to undertaking stormwater management practices, precautions must be taken to prevent direct construction-related impacts to adjacent resources.

The Public Trust Doctrine

The submerged lands and waters below MHW in Connecticut belong to all citizens of the state under the ancient common law public trust doctrine. The public trust area is also referred to as tidelands. The general public may freely use these intertidal and subtidal lands and waters for fishing, shell-fishing, hunting, boating, sunbathing and walking along the beach. DEEP works to preserve these rights by regulating the encroachment of private structures into the public trust area and by promoting public access opportunities throughout Connecticut's coast.

Connecticut's Coastal Permit Program

The activities listed here are regulated by the Department of Energy and Environmental Protection's coastal permit programs. The applicable permit program(s) for each activity is abbreviated and listed parenthetically: P = individual permit; GP = general permit; COP = certificate of permission. LWRD regulatory staff are available to discuss permit requirements and to meet with applicants to explain the review process. Please note that COP and Structures, Dredging and Fill applications can be completed and submitted through our online portal ezFile. For further information please contact DEEP.LWRDRegulatory@ct.gov.

Bulkheads

Bulkheads that have been authorized and maintained in functional condition may generally be repaired. Bulkheads should be replaced in-kind and in-place if possible; however, if oversheeting is necessary, the additional encroachment of the rebuilt structure into tidal waters should extend no more than 18 inches. The construction of new bulkheads may only be authorized when all criteria for permissible structural solutions as specified in CCMA section 22a-92(b)(2)(J) have been met. (P,COP)

Revetments

Revetments that have been authorized and maintained in functional condition may generally be repaired, provided there is no further encroachment into intertidal or subtidal habitat. The construction of new revetments may only be authorized when all criteria for permissible structural solutions as specified in CCMA section 22a-92(b)(2)(J) have been met. Revetment construction also requires a municipal Coastal Site Plan Review. (P,COP)

Seawalls

Seawalls that have been authorized and maintained in functional condition may generally be repaired. Seawall repair is ideally conducted from the upland, and silt fencing must be used to protect intertidal habitat. In certain circumstances, seawalls may be capped if necessary to protect existing inhabited structures. Seawalls often perpetuate or exacerbate the erosion of adjacent shoreline, further endangering the structures they are intended to protect; therefore, the construction of new seawalls may only be authorized when all criteria for permissible structural solutions as specified in CCMA section 22a-92(b)(2)(J) have been met. Seawall construction also requires municipal Coastal Site Plan Review. (P,COP)

Groins and Jetties

Groins and jetties that have been authorized and maintained in functional condition may generally be repaired when they are designed to minimize alteration of natural circulation patterns and loss of intertidal and subtidal habitat. Permittees may be required to place sand fill to mitigate past beach erosion associated with the structure. The construction of new groins jetties may only be authorized when all criteria for permissible structural solutions as specified in Section 22a-92(b)(2)(J) of Connecticut's Coastal Management Act have been met. (P,COP)

Maintenance Dredging

Maintenance dredging of marina basins and navigation channels may be authorized if dredging of those areas has been previously authorized by DEEP. Such maintenance dredging must not encroach into previously undisturbed subtidal habitat and is prohibited during periods of shellfish and finfish spawning when drifting sediment could impair reproductive success. New dredging is strongly discouraged, and dredging of tidal wetlands and intertidal flats is not allowed. (P, COP)

Utilities

Installation of submarine cables and pipelines must be sited to minimize impacts on intertidal and subtidal resources, including shellfish beds and submerged aquatic vegetation, and must not interfere with navigation and public access. Cables that are no longer in use must be removed. (P)

Docks, Ramps, Floats and Pilings

Residential docks must be designed to prevent shading of tidal wetland grasses and intertidal flats, avoid areas of submerged aquatic vegetation, minimize encroachment into public trust lands, and allow continued navigation and public access along the shore. A generally acceptable dock design in most settings includes a fixed pier extending to mean low water with a ramp and a 10' x 10' float. (P,COP,GP)

Jet Ski Floats

Floats used for storage of jet skis, and jet boats, including prefabricated floats, must not be located over submerged aquatic vegetation. Adding a jet float to an existing dock requires a permit. (P)

Moorings

Boat moorings (anchored or clothesline-rigged, or an unattached small float) may be installed for private recreational use but must not be located in federal navigation channels or anchorages. Moorings must not be installed in tidal wetlands or over submerged aquatic vegetation. Moorings authorized by a Harbor Master are eligible for General Permit, otherwise they must be approved by LWRD. (P,COP,GP)

Swim Floats

Swim floats may be used for swimming and associated recreation but not for securing or storing boats. Swim floats may not exceed 200 square feet in area, and must be removed from the water from November 15th through April 15th each year. They must not be located over submerged vegetation and must not interfere with navigation or public access along the shore. (GP)

Stairs

Stairs or ladders used to access the beach over slopes and seawalls should be kept above the coastal jurisdiction line where possible. (P)

Public Access Structures

Public access boardwalks, walkways and viewing platforms are encouraged but generally should not be constructed in or encroach upon tidal wetlands, beaches and dunes, or intertidal flats. (P)

Pumpout Stations

Installation of pumpout facilities for boat sewage is required to protect water quality when construction of a new marina is permitted or when an existing marina is substantially modified. (P, GP)

Osprey Platforms and Perch Poles

Osprey nesting platforms must be located a minimum distance from man-made disturbances and from other platforms. (GP)

Beach Nourishment

Sand may be placed and graded on beaches landward of MHW to replace sand lost to erosion or as a non-structural method of erosion control. Imported sand must match the grain size and color of the existing beach sand. Precautions must be taken to prevent newly placed sand from drifting onto nearby fish and shellfish resources and habitat. (P,COP)

Tidal Wetland Restoration

Accurate surveying and specialized low ground pressure equipment must be used in restoring degraded tidal wetlands to prevent further damage to healthy wetland habitat. (COP)

Stormwater Management

Coastal development sites must incorporate proper stormwater management measures. Sites should be developed to retain existing natural vegetation, reduce site disturbance and overall impervious cover, and pretreat runoff to tidal waters and wetlands. Drainage from paved surfaces should be directed to stormwater collection systems that are outfitted with appropriate pretreatment structures, such as swirl concentrators. Stormwater outfalls must be permitted. (P)

Buoys and Markers

Buoys, water skiing ramps, and other markers related to navigation or waterbased recreation are regulated by the DEEP Boating Division. Upon authorization by the Boating Division, they are considered to be concurrently authorized by LWRD. (GP)

ezFile logo
Go Paperless with DEEP's ezFile!

COP and Structures, Dredging and Fill (SDF) applications can be completed and submitted through DEEP's on-line ezFile system.

Benefits of using ezFile include:

  • Applications can be "shared" with ezFile users of your choice allowing others to assist with the registration process.
  • Pre-populated drop-down lists to facilitate appropriate selections.
  • E-mail confirmation of submission, DEEP decision on the application.

Resources to assist with your transition from paper based applications and permits to ezFile:

To get started:

1. Create your user account (use Google Chrome). Refer to detailed instructions, if needed.

Note: The Account Security PIN is only valid for 24 hours. If your PIN has expired, go to the Account Manager and select the "Register User" option from the right hand menu.

If you do not receive the email, check your junk or spam folder and ask your IT department staff to check their spam folder. To help ensure you receive the email:

2. If you have questions concerning your user account, or resetting your password contact Deep.Helpdesk.Footprints@ct.gov.

3. Once you've created your user account, log in to ezFile. Once logged in, scroll to the bottom of the page and click on the blue box that says "Coastal Activities." Then select the “new application” button under the “My Drafts” tab to get started.

4. You will be prompted to create your subscriber agreement before moving on to the next section of the application screen. To create a Subscriber Agreement, select the profile button at the top right of the page and select “Subscriber Agreement” from the drop-down menu.

Questions regarding the Land and Water Resources ezFile applications should be directed to DEEP.LWRDRegulatory@ct.gov.

Please note: There are permit application fees associated with the COP and SDF permitting process. These fees can be found on our Water and Land Use - Permit Overview page. If you chose the “pay later” option when submitting, your application will not be processed until the application fee is paid.

For further information on Connecticut's Coastal Permit Program, please contact:

LWRD Regulatory Staff
Land and Water Resources Division
Bureau of Water Protection and Land Reuse
Department of Energy and Environmental Protection
79 Elm Street
Hartford, CT  06106-5127

This overview is designed to answer general questions and provide basic information. Refer to the appropriate statutes and regulations for the specific criteria of the different regulatory programs. This document should not be relied upon to determine whether or not an environmental permit is required. It is your responsibility to obtain and comply with all required permits.

Coastal Permits

Content Last Updated May 4, 2022.