Due to the personally identifying information contained in written limited appearance statements from the public, any written limited appearance statements that are received by the Council for any matter are available to be viewed at the Council’s office Monday through Friday from 8:30 a.m. to 4:30 p.m. or available to be sent via e-mail upon request. Please allow adequate time for processing.

Long Island Sound Resource and Use Inventory/Long Island Sound Blue Plan Survey

PETITION NO. 1634 – IPB Fuel Cell 1, LLC and IPB Fuel Cell 2, LLC (FuelCell Energy, Inc.) petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a customer-side 1-megawatt fuel cell facility and associated equipment to be located at the Innovation Partnership Building on the University of Connecticut campus, 159 Discovery Drive, Storrs (Mansfield), Connecticut, and associated electrical interconnection.

 

PETITION (recd. 06/27/24)
Narrative, 06/26/24
Exhibit A: Site Plan
Exhibit B: Equipment Specification Sheet
Exhibit C: Public Notice Documentation (Service Lists, Sample Notice Letters, Affidavits and Abutters Map)
Exhibit D: Facility Sound Assessment
Exhibit E: National Register of Historic Places Map
Exhibit F: Environmental Maps
Exhibit G: Emergency Response Plans for the IPB1 and the IPB2 projects

 

PROCEDURAL CORRESPONDENCE
Council Letter to Town of Mansfield, 06/27/24
Council State Agency Comment Memorandum, 06/27/24
Council Set Date for Decision, 08/15/24
Council Interrogatories to Petitioner, Set One, 08/16/24
Council's Response to Petitioner Request for Extension to Submit Interrogatory Responses, 09/04/24
Council Decision on Motion for Protective Order - Response to Council Interrogatory No. 3 Cost Information 10/10/24

 

STATE AGENCY COMMENTS

 

MUNICIPAL COMMENTS

 

SCHEDULE
Schedule, 06/27/24
Schedule, 08/15/24
Schedule, 08/16/24
Schedule, 09/04/24

 

SERVICE LIST
Service List, 06/27/24
Service List, 12/26/24

 

PETITIONER - IPB Fuel Cell 1, LLC and IPB Fuel Cell 2, LLC (IPB)

Exhibits
Petitioner Submission of State Historic Preservation Office Comments, 07/31/24
Petitioner Response to Council Interrogatories, 09/27/24
Interrogatory Response Attachments

Procedural Correspondence
Petitioner Notice of Service List Change, 12/24/24

Motions
Petitioner Request for Extension to Submit Interrogatory Responses, 09/04/24
Petitioner Motion for Protective Order - Response to Council Interrogatory No. 3 Cost Information, 09/27/24
Signed Protective Order - Response to Council Interrogatory No. 3 Cost Information, 10/10/24

 

DECISION
Council Decision and Staff Report, 10/25/24