PETITION NO. 1604 – Endurant Energy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of an 18.0-megawatt AC battery energy storage facility located at 50 Ucar Street (Parcel No. 70H-55-97), Suffield, Connecticut, and associated electrical interconnection.

 

PETITION (recd. 12/18/23)
Petition Narrative,12/18/23
Appendices
Appendix A - Technical Data Sheets and Renderings
Appendix B - Local Outreach Log
Appendix C - Facility Maps
Photolog
Appendix D - Public Notice
Appendix E - Safety Data Sheets for Hazardous Materials
Appendix F - Natural Diversity Database Report and NDDB Map, USFWS Report
Appendix G - Sound Assessment
Appendix H - National Register of Historic Places Map
Appendix I - FAA Notice Criteria Tool Reports
Appendix J - Decommissioning Plan
Appendix K - Emergency Response Plan



PROCEDURAL CORRESPONDENCE
Council Letter to Town of Suffield, 12/19/23
Council Letter to Town of Windsor Locks, 12/19/23
Council State Agency Comment Memorandum, 12/20/23
Council Set Date for Decision, 02/01/24
Council Interrogatories to Petitioner, Set One, 02/26/24
Petitioner Request for Extension to Submit Interrogatory Responses and Council Decision, 03/18/24


SCHEDULE
Schedule, 12/19/23
Schedule, 02/01/24
Schedule, 02/26/24
Schedule, 03/15/24



SERVICE LIST
Service List, 12/18/23


PETITIONER - Endurant Energy
Request for Extension to Submit Interrogatory Responses, 03/15/24
Petitioner Responses to Council Interrogatories, Set One, 04/01/24

 

COUNCIL FINAL DECISION
Council Decision and Staff Report, 05/10/24