PETITION NO. 1581 - KCE CT 8, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 4.9-megawatt AC battery energy storage facility located at 44 Skinner Street, East Hampton, Connecticut, and associated electrical interconnection.

 

PETITION (recd. 06/27/23)
Petition Filing, 06/27/23
List of Figures
Figure 1. Site Location Map (USGS) 
Figure 2. Site Location Map (Aerial) 
Figure 3. Existing Conditions (Survey) 
Figure 4. Proposed Conditions
Figure 5. Wetland Delineation Results 
Figure 6. Water Resources
Figure 7. NRCS Soils 
Figure 8. NDDB Areas
List of Exhibits
Exhibit A – Site Plans/Civil Design 
Exhibit B – Equipment Specifications 
Exhibit C – Site Control
Exhibit D – Natural Resources Survey Report 
Exhibit E – Geotechnical Report
Exhibit F – NDDB Correspondence
Exhibit G – Cultural Resources Survey Report 
Exhibit H – Acoustic Analysis Report
Exhibit I – Visual Impact Analysis 
Exhibit J – Stormwater Report
Exhibit K – Operations and Maintenance Plan, Emergency Response Plan 
Exhibit L – FAA Consultation
Exhibit M– Decommissioning Plan 
Exhibit N – Project Outreach


 

PROCEDURAL CORRESPONDENCE
Council Letter to Town of East Hampton, 06/29/23
Council State Agency Comment Memorandum, 06/29/23
Council Interrogatories to Petitioner, Set One, 07/21/23
Council Set Date for Decision, 08/17/23
Council Decision on Motion for Protective Order, 08/31/23
Signed Protective Order, 08/31/23
Council Interrogatories to Petitioner, Set Two, 9/27/23

 

MUNICIPAL COMMENTS

 

STATE AGENCY COMMENTS

 

SCHEDULE
Schedule, 06/28/23
Schedule, 07/21/23
Schedule, 08/17/23
Schedule, 09/27/23

 

SERVICE LIST
Service List, 06/28/23
Service List, 09/27/23

 

PETITIONER - KCE CT 8, LLC
Petitioner Responses to Council Interrogatories, Set One, 08/11/23
Petitioner Motion for Protective Order - Response to Council Interrogatory No. 3 Cost Information, 08/11/23
Affidavit of Taylor Quarles, 08/04/23
Non-Disclosure Agreement
Protective Order, 08/11/23
Petitioner's Request for Service List Change, 09/26/23
Petitioner Responses to Council Interrogatories, Set Two, 10/19/23

 

DECISION
Council Decision and Staff Report, 11/13/23