Due to the personally identifying information contained in written limited appearance statements from the public, any written limited appearance statements that are received by the Council for any matter are available to be viewed at the Council’s office Monday through Friday from 8:30 a.m. to 4:30 p.m. or available to be sent via e-mail upon request. Please allow adequate time for processing.

Long Island Sound Resource and Use Inventory/Long Island Sound Blue Plan Survey

PETITION NO. 1463 - CF Mulnite LLC CF Mulnite Miller LLC Greenskies Clean Energy, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1.0-megawatt (MW) AC solar photovoltaic electric generating facility located at a Mulnite Farms, Inc. parcel off Wapping Road, and a 4.0 MW AC solar photovoltaic electric generating facility located at a Mulnite Farms, Inc. parcel off Miller Road, East Windsor, Connecticut, and associated electrical interconnection.

 

PETITION FILING (recd. 08/25/21)
Petition Cover Letter, 08/24/21
Narrative

LIST OF FIGURES:
Figure 1 – Site Location Map 
Figure 2 – Proposed Project Area Aerial 
Figure 3 – Zoning Map 
Figure 4 – Tax Parcel Map 
Figure 5 – Site Survey 
Figure 6 – Slope Map 
Figure 7 – Proposed Project Layout 
Figure 8 – Construction Schedule 
Figure 9 – Prime Farmland Soils Map 
Figure 10 – Wetlands Delineation Map 
Figure 11 – Core Forest Map 
Figure 12 – Aquifer Protection Area Map 
Figure 13 – Public Water Supply Watershed Map 
Figure 14 – Groundwater Quality Classifications, East Windsor, CT (CTDEEP) 
Figure 15 – NRCS Soils Information
LIST OF APPENDICES:
Appendix A – Permit Plan/Drawing Set 
Appendix B – Electrical Drawings & Equipment Specifications 
 Part I - Mulnite-Miller Site Plan   Part II - Mulnite-Wapping Site Plan  Part III - Inverter - Canadian Solar 3 Phase   Part IV - Canadian Solar Datasheet
Appendix C – Operation & Maintenance Documentation 
Appendix D – Draft Decommissioning Plan 
Appendix E – Phase I Environmental Site Assessment 
Appendix F – Stormwater Report 
Appendix G – Cultural Resource Assessment Documentation 
Appendix H – Wetlands Delineation Report 
Appendix I – Wildlife and Habitat Review Documentation 
 Part I - NDDB Final Determination  Part II - NDDB Map June 2021  Part III - Rare Species Memorandum
Appendix J – Public Outreach Documentation 
Appendix K – Visual Impact Assessment 
Appendix L – FAA Consultation    Part I - Notice Criteria Tool  Part II - Project Submission  Part III - Aviation Report
Appendix M – Core Forest Consultation 
Appendix N – Prime Farmland Consultation  

 

PROCEDURAL CORRESPONDENCE
Council Letter to the Town of East Windsor, 08/27/21
Council State Agency Memorandum, 08/27/21
Council Incomplete Abutter Notice, 09/02/21
Council Acknowledgement of Petitioner's Response to the Council's Incomplete Letter, 09/20/21
Council Set Date for Decision Letter, 10/25/2021
Council Interrogatories to Petitioner, Set One, 10/25/21

 

CGS §16-50k CORE FOREST AND PRIME FARMLAND DETERMINATIONS
Department of Energy and Environmental Protection C.G.S. §16-50k No Material Impact to Core Forest Determination Letter, 08/02/21
Department of Agriculture C.G.S. §16-50k No Material Impact to Prime Farmland Determination Letter, 08/24/21

 

STATE AGENCY COMMENTS
Connecticut Airport Authority Comments, 08/30/21
Connecticut Council on Environmental Quality Comments, 09/23/21 

 

SCHEDULE
Schedule, 08/26/21
Schedule, 10/25/21

  

SERVICE LIST
Service List, 08/26/21
Service List, 04/21/25

 

PETITIONER - Greenskies Clean Energy, LLC
Petitioner Response to Council's September 2, 2021 Incomplete Letter, 09/17/21
Petitioner Supplemental Submission to Appendix L of the Petition (FAA Determination of No Hazard to Air Navigation), 09/22/21
Petitioner Submission of Phase IB Cultural Resources Reconnaissance Survey, 10/13/21
Petitioner Response to Council Interrogatories, 11/12/21  Cover Letter
Exhibit A - Boundary Map
Exhibit B - Revised Site Plans
Exhibit C - Modified Spill Prevention, Control and Countermeasure Plan and Soil Contact Best Practices Plan
Exhibit D - Photo Log
Exhibit E - Visual Impact Study
Exhibit F - HydroCAD Output - Crop Production
Exhibit G - Geotechnical Testing
Request for Service List Change, 04/21/25

 

DECISION
Council Decision and Staff Report, 01/14/22
Transfer of Declaratory Ruling and Council Acknowledgement, 06/02/22
Transfer of Declaratory Ruling and Council Acknowledgement, 11/06/23

 

MOTION TO REOPEN AND MODIFY
CF Mulnite LLC Motion to Reopen and Modify, 02/05/24
Council Memorandum Regarding CF Mulnite LLC Motion to Reopen and Modify, 02/07/24
Town of East Windsor Request for Party Status, 02/26/24
Council Acknowledgement of Town of East Windsor Request for Party Status, 02/27/24
Council Decision on East Windsor Request for Party Status, 03/01/24
Council Decision on Madsen Request for Public Hearing, 03/01/24
Council Decision on Motion to Reopen and Modify and Staff Report, 03/01/24