PETITION NO. 1451 -  C-Tec Solar, LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 3.8-megawatt AC solar photovoltaic electric generating facility and a 2.2-megawatt AC solar photovoltaic electric generating facility located at 277 Sadds Mill Road, Ellington, Connecticut, and associated electrical interconnection.

PETITION (recd. 4/13/21)
Petition Cover Letter, 04/13/21
Petition Narrative
Appendix A - Project Plans
Appendix B - Notices to Abutters and Governmental Officials (see Petition Narrative)
Appendix C - Environmental Assessment
Appendix D - Stormwater Report

 

 

PROCEDURAL CORRESPONDENCE
Council Letter to the Town of Ellington, 04/15/21
Council Letter to the Town of East Windsor, 04/15/21
State Agency Comment Memorandum, 04/15/21
Council Interrogatories to Petitioner, 05/14/21

 

CGS §16-50k CORE FOREST AND PRIME FARMLAND DETERMINATIONSSTATE AGENCY COMMENTS
Department of Energy and Environmental Protection C.G.S. §16-50k No Material Impact to Core Forest Determination Letter, 12/23/20
Department of Agriculture C.G.S. § 16-50k No Material Impact to Prime Farmland Determination Letter, 04/05/21

 

STATE AGENCY COMMENTS
Council on Environmental Quality Comments, 04/29/21
Department of Energy and Environmental Protection Comments, 05/14/21

 

MUNICIPAL COMMENTS

 

SCHEDULE
Schedule, 04/14/21

 

SERVICE LIST
Service List, 04/14/21

 

PETITIONER - C-Tec Solar, LLC 
Petitioner Responses to Council Interrogatories, 06/04/21

DECISION
Council Decision and Staff Report, 07/16/21